Full Text
$-2 // HIGH COURT OF DELHI
ARB.P. 58/2015
M/S KALPATARU POWER TRANSMISSION LTD Petitioner
Through Dr.Sunil Mittal, Adv. with Mr.Kumar Vivek Vibhu, Adv.
Through None
18.04.2016 Learned counsel for the petitioner admits that respondents No.2 & 3, who are the Directors of respondent No.l, are not parties to the agreement.
Upon instructions, he has made the statement that the petitioner has no objection if their names be deleted jfrom the array of the parties. He is allowed to file the amended memo of parties within oneweek.
The respondent-Company is served through publication. No one appears on its behalf; even reply was not filed. Under these circumstances, the matter is beingproceeded further in its absence.
Brieffacts are that on 24^'' February, 2011, the Eastern Railway issued
Letter of Acceptance to M/s. KPTL-JMC-Yadav (Joint Venture) bearing
Ref. No.CAO/Con/WT/8672 for construction work between Dakuni to
Baruipara. The Joint Venture was formally entered at New Delhi vide
Supplementary Agreement dated 15^*^ March, 2011 among the petitioner.
2016:DHC:8312 V JMC and Yadav. As per the said Joint Venture, the petitioner was made th lead partner. The Joint Venture through Execution Agreement dated 30 March, 2011 delegated power up to the petitioner-Company to ensure timely and successful completion of the project. On the same date, the petitioner entered into execution agreement with therespondent whereby thepetitioner sub-contracted theentire project asperterms and conditions agreed.
It is submitted that in between April, 2011 to February, 2012, the petitioner made advances to the respondent-Company totalling to Rs.77.36
Lakhs as per clause 9 ofthe execution agreement. The petitioner due tonon- til completion of the project by the respondent-Company by notice dated 6 June, 2012 called upon it to return Rs.69.76 Lakhs after deducting Rs.7.60
Lakhs, the value for the work done. Thereafter, on 3'''^ September, 2012, the petitioner's counsel issued legal notice to the respondent demanding
Rs.69.76 Lakhs with interest. On 29"" July, 2013, the petitioner received reply from the respondent's counsel whereby the respondent demanded
Rs.4.44 Crore from the petitioner. The respondent also proposed the name ofSh.G.P.Thareja (Retired District &Sessions Judge) as an arbitrator. On
20^^ February, 2014, the petitioner invoked the arbitration clause as per clause 23 of the execution agreement appointing Hon'ble Mr. Justice ^ C.K.Thakkar, Former Judge of the Supreme Court of India and requiring respondent to give consent within 30 days of the receipt of the notice. On
12^^" March, 2014, the petitioner again sent the arbitration notice to the respondent reiterating contents in the previous notice but to no response.
Hence, the present petition has been filed by the petitioner under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of a sole
Arbitrator for reference and adjudication of the disputes that have arisen f p between the parties.
For the reasons stated in the petition coupled with the documents placed on the record, the prayer made in the petition is allowed. These are five petitions. The parties are same in all sets of disputes, thus, it is appropriate that single sole Arbitrator is to be appointed, in order to save time, cost and to avoid conflicting findings.
Accordingly, Mr. Justice S.S. Nijjar, Retired Judge ofSupreme Court
(Mobile No.9560453535) is appointed as sole Arbitrator to adjudicate the disputes arising between the parties as mentioned in the present petition as well as four other petitions. The parties are also allowed to file their respective claims and counter-claims before the Arbitrator.
The Arbitrator shall ensure the compliance of the provisions of
Arbitration and Conciliation (Amendment) Act, 2015 before commencing the arbitration. The fees of the learned Arbitrator shall be in terms of the schedule under the amended Act. The parties to appear before theCentre on
20^^ May, 2016 at 5.00 pm for directions.
The petition isaccordingly disposed of.
Copy ofthis order be given dasti to the learned counsel for the parties and a copy thereof be communicated to the learned Arbitrator forthwith.
APRIL 18,2016/ka 'S r $-48.
HIGH COURT OF DELHI
A
ICALPATARU POWER TRANSMISSION LTD Petitioner
Through: Mr. Ashish Dholakia, Ms. Anu Tiwari, Mr. Sunil Mittal & Mr. D.Kishore Kumar, Advocates.
ORDER
1. On 18^*^ April 2016 this Court had passed the following ex parte order: "Learned counsel for the petitioner admits that respondents No.2 & 3, who are the Directors of respondent No.l, are not parties to the agreement. Upon instructions, he has made the statement that the petitioner has no objection if their names be deleted from the array ofthe parties. He is allowed to file the amended memo of parties within one week. The respondent-Company is served through publication. No one appears on its behalf; even reply was not filed. Under these circumstances, the matter is being proceeded further in its absence. Brief facts are that on 24^*^ February, 2011, the Eastern Railway issued Letter of Acceptance to M/s. KPTL-JMC-Yadav (Joint Venture) bearing Ref. No.CAO/Con/WT/8672 for construction work between Dakuni to Baruipara. The Joint Venture was formally entered at New Delhi vide Supplementary Agreement dated IS^*" March, 2011 among the petitioner, JMC and Yadav. As per the said Joint Venture, the Arb. P. No. 58/2015 Page 1 of[4] petitioner was made the lead partner. The Joint Venture through Execution Agreement dated 30"^ March, 2011 delegated power up to the petitioner-Company to ensure timely and successful completion of the project. On the same date, the petitioner entered into execution agreement with the respondent whereby the petitioner sub-contracted the entire project as per terms and conditions agreed. It is submitted that in between April, 2011 to February, 2012, the petitioner made advances to the respondent- Company totalling to Rs.77.36 Lakhs as per clause 9 of the execution agreement. The petitioner due to noncompletion of the project by the respondent-Company by notice dated 6^*^ June, 2012 called upon it to return Rs.69.76 Lakhs after deducting Rs.7.60 Lakhs, the value for the work done. Thereafter, on 3'^'' September, 2012, the petitioner's counsel issued legal notice to the resppndent demanding Rs.69.76 Lakhs with interest. On 29"" July, 2013, the petitioner received reply from the respondent's counsel whereby the respondent demanded Rs.4.44 Crore from the petitioner. The respondent also proposed the name of Sh.G.P.Thareja (Retired District &Sessions Judge) as an arbitrator. On 20"^ February, 2014, the petitioner invoked the arbitration clause as per clause 23 of the execution agreement appointing Hon'ble Mr. Justice C.K.Thakkar, Former Judge of the Supreme Court of India and requiring respondent to give consent within 30 days of the receipt of the notice. On 12'^ March, 2014, the petitioner again sent the arbitration notice to the respondent reiterating contents in the previous notice but to no response. Hence, the present petition has been filed by the petitioner under Section 11 of the Arbitration and Conciliation Act, 1996 for appointment of a sole Arbitrator for reference and adjudication of the disputes that have arisen between the parties. For the reasons stated in the petition coupled with the Arb. P. No. 58/2015 ^"8^ ^ documents placed on the record, the prayer made in the petition is allowed. These are five petitions. The parties are same in all sets of disputes, thus, it is appropriate that single sole Arbitrator is to be appointed, in order to save time, costand to avoid conflicting findings. Accordingly, Mr. Justice S.S. Nijjar, Retired Judge of Supreme Court (Mobile No.9560453535) is appointed as sole Arbitrator to adjudicate the disputes arising between the parties as mentioned in the present petition as well as four other petitions. The parties are also allowed to file their respective claims and counter-claims before the Arbitrator. The Arbitrator shall ensure the compliance of the provisions of Arbitration and Conciliation (Amendment) Act, 2015 before commencing the arbitration. The fees of the learned Arbitrator shall be in terms of the schedule under the amended Act. Theparties to appear before the Centre on 20"" May, 2016 at 5.00 pm for directions. The petition is accordingly disposedof. Copy of this order be given dasti to the learned counsel for the parties and a copy thereof be communicated to the learned Arbitrator forthwith." O
2. A letter dated 2C September 2016 has been received from Mr. Justice Surinder Singh Nijjar stating that due to unavoidable circumstances he is unable to act as an Arbitrator in these matters in terms of the order dated th • 18 April 2016 passed by this Court. It is seen that the initial appointment by this Court is also an exparte order.
3. The Court accordingly modifies the above order and appoints Mr.Justice K.S. P. Radhakrishnan, former Judge of the Supreme Court of India (Mob. No.9560013636) as the sole Arbitrator to adjudicate the disputes between Arb. P. No. 58/2015 Page 3 of[4] the parties including their claims and counter claims. It is clarified that it will be for the learned Arbitrator to decide whether the arbitration should take place under the aegis ofthe Delhi International Arbitration Centre.
4. The learned Arbitrator is requested to endeavour to complete the arbitration within a period of twelve months from the date he enters upon reference.
5. A certified copy of this order be delivered to the learned Arbitrator forthwith.
SEPTEMBER 26, 2016 S. MURALIDHAR, J. b 'nesh