Sharda Nand v. Govt. of NCT of Delhi

Delhi High Court · 12 Jul 2016 · 2016:DHC:4881-DB
Badar Durrez Ahmed; Ashutosh Kumar
W.P.(C) No. 8214/2015
2016:DHC:4881-DB
property petition_allowed Significant

AI Summary

The Delhi High Court held that acquisition proceedings under the 1894 Act lapse under Section 24(2) of the 2013 Act if compensation remains unpaid for over five years after the award.

Full Text
Translation output
W.P.(C) No. 8214/2015 HIGH COURT OF DELHI
JUDGMENT
delivered on: 12.07.2016
W.P.(C) 8214/2015 & CM 17217/2015
SHARDA NAND AND ORS. .... Petitioners
versus
GOVT. OF NCT OF DELHI AND ORS. ..... Respondents
Advocates who appeared in this case:
For the Petitioners : Ms. Richa Oberoi For the Respondent L&B/LAC : Mr Siddharth Panda with Ms Jyoti Tyagi
For the Respondent DDA : Mr Pawan Mathur
CORAM:-
HON’BLE MR JUSTICE BADAR DURREZ AHMED
HON’BLE MR JUSTICE ASHUTOSH KUMAR
JUDGMENT
BADAR DURREZ AHMED, J (ORAL)

1. The petitioners seek the benefit of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as ‘the 2013 Act’) which came into effect on 01.01.2014. A declaration is sought to the effect that the acquisition proceeding initiated under the Land Acquisition Act, 1894 (hereinafter referred to as ‘the 1894 Act’) in respect of which Award No.13/2005-06 dated 29.07.2005 was made, inter alia, in respect of the petitioners’ land comprised in Khasra Nos. 22/18/1 (2-07), 22/19/1 2016:DHC:4881-DB (2-0), 22/9 (4-16), 22/17 (4-16) and 22/18/2 (2-07) measuring 16 bighas 6 biswas in all in village Begumpur, New Delhi, shall be deemed to have lapsed.

2. The learned counsel for the respondents state that possession of the entire land except khasra no. 22//17 (4-16) was taken on 27.02.2006. The petitioners claim that the entire possession is with them. However, insofar as the issue of compensation is concerned, it is an admitted position that it has not been paid.

3. Without going into the controversy of physical possession, this much is clear that the Award was made more than five years prior to the commencement of the 2013 Act and the compensation has also not been paid. The necessary ingredients for the application of Section 24(2) of the 2013 Act as interpreted by the Supreme Court and this Court in the following cases stand satisfied:- (1) Pune Municipal Corporation and Anr v. Harakchand Misirimal Solanki and Ors: (2014) 3 SCC 183; (2) Union of India and Ors v. Shiv Raj and Ors: (2014) 6 SCC 564; (3) Sree Balaji Nagar Residential Association v. State of Tamil Nadu and Ors: Civil Appeal No. 8700/2013 decided on 10.09.2014; (4) Surender Singh v. Union of India & Others: WP(C) 2294/2014 decided on 12.09.2014 by this Court; and (5) Girish Chhabra v. Lt. Governor of Delhi and Ors: WP(C) 2759/2014 decided on 12.09.2014 by this Court.

4. As a result, the petitioners are entitled to a declaration that the said acquisition proceedings initiated under the 1894 Act in respect of the subject land are deemed to have lapsed. It is so declared.

5. The writ petition is allowed to the aforesaid extent. There shall be no order as to costs.

BADAR DURREZ AHMED, J JULY 12, 2016 ASHUTOSH KUMAR, J kb