Gurnam Kaur v. BSES Rajdhani Power Ltd. & Ors.

Delhi High Court · 14 Jul 2016 · 2016:DHC:4951
Rajiv Sahai Endlaw
CS(OS) 2691/2015
2016:DHC:4951
civil appeal_allowed Significant

AI Summary

The Delhi High Court granted a mandatory injunction directing removal of an unauthorized transformer and electric pole from the plaintiff's property, affirming her ownership and rejecting defendants' delay and lack of legal right to retain the installations.

Full Text
Translation output
CS(OS) 2691/2015
HIGH COURT OF DELHI
CS(OS) 2691/2015
GURNAM KAUR ..... Plaintiff
Through: Mr. Sameer Vashisht, Adv.
VERSUS
BSES RAJDHANI POWER LTD. & ORS. ..... Defendants
Through: Mr. Deepak Pathak for D-1&3.
Mr. Jayendra, Adv for SDMC.
CORAM:
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW O R D E R
14.07.2016
JUDGMENT

1. The plaintiff has sued for mandatory injunction directing the defendants BSES Rajdhani Power Limited, South Delhi Municipal Corporation (SDMC) and Divisional Head (O&M) of the defendant No.1 BSES Rajdhani Power Limited to remove the transformer and the electric pole installed in the portion of the properties No. D1/20 and D1/21, Rajouri Garden, New Delhi of the plaintiff and for recovery of arrears and future mesne profits/damages for the use and occupation.

2. The suit was entertained.

3. The defendants No. 1 and 3 have filed a written statement inter 2016:DHC:4951 alia pleading that the subject transformer has been in existence for over 30 years, though the said defendants are unable to locate the documents executed by the then owner of the property permitting installation of the said transformer and have sought the same from Delhi Power Corporation Limited (DPCL) being the holding company created while unbundling erstwhile Delhi Vidyut Board (DVB) during whose regime the subject transformer and electric pole were installed.

4. Defendant No.2 SDMC has not filed any written statement and the counsel for the plaintiff states that the defendant No.2 SDMC was impleaded only because it was the stand of the defendant No.1 in response to the legal notice preceding the suit that SDMC had to allocate alternative place to them for shifting of the said transformer; else no relief has been claimed against the defendant No.2 SDMC.

5. The suit is ripe for framing of issues, if any.

6. Counsel for the plaintiff states that the written statement of defendants No. 1 and 3 does not disclose any defence to the suit in so far as for the relief of mandatory injunction and the plaintiff is entitled to decree forthwith.

7. On enquiry, the counsel for the plaintiff in support of the title of the plaintiff to the subject property has drawn attention to the judgment dated 10th April, 2015 of this Court in CS(OS) No.1350/1995 titled Gurnam Kaur Vs. Pritam Singh Bhatia and in Test.Cas. 81/2008 titled Administrator General Sanjay Dewan Vs. State declaring the plaintiff as the owner of the properties and to the judgment dated 14th August, 2015 of the Division Bench of this Court in RFA(OS)70/2015 Sanjeev Bansal Vs Gurnam Kaur preferred thereagainst. It is further informed that SLP preferred against the said judgment of the Division Bench was also dismissed though copy of that order has not been filed and is not available with the counsel today. On further inquiry whether there is any challenge from any quarter to the title of the plaintiff to the subject properties as of today, the reply is in the negative. It is however informed that the plaintiff has since sold property No.D-1/21, Rajouri Garden, New Delhi but the transformer and the electricity pole qua which the suit has been filed is in property No.D-1/20.

8. The counsel for the defendants No. 1 and 3 on inquiry confirms that the transformer and the electricity pole are as shown in the site plan filed by the plaintiff i.e. within the boundary wall of property No.D-1/20. The said site plan, for identification, is Ex.C-1.

9. The counsel for the defendants No. 1 and 3 states that the defendants No. 1 and 3 have sought details of the documents of occupation of the property from the DPCL and the same are awaited and seeks adjournment. It is argued that owing to the process of unbundling of the DVB which had installed the subject transformer, the documents are not immediately available. It is yet further contended that the removal of transformer is a time consuming process and subject to availability of alternative location and if the transformer is removed immediately, the electric supply to the locality would suffer.

10. I have considered the rival contentions. Merit is found in the contention of the counsel for the plaintiff that the plaintiff, on the pleadings of the parties, is entitled to a decree forthwith for the relief of mandatory injunction.

11. Order XV of the CPC requires the Court to frame issues only substantial disputed questions of law and the written statement of the defendants No. 1 and 3 does not raise any substantial question of fact which if proved would disentitle the plaintiff to the relief of mandatory injunction.

12. As far as the pleas of the counsel for the defendants No. 1 and 3 of adjournment and of difficulty in removal of transformer are concerned, suffice it is to state that the written statement was filed by the defendants No. 1 and 3 as far back as in January, 2016 and if the defendants No. 1 and 3 in the last about six months have been unable to find any document, the suit cannot be kept pending indefinitely for the said purpose and the plaintiff cannot be deprived of her property. The question of the difficulty in shifting of the transformer even otherwise is to be considered at the stage of execution of the decree for mandatory injunction.

13. I may in this regard notice that with respect to transformers similarly installed in other private properties, WP(C)s. No. 6032/2008 and 1035/2011 were filed and the directions for shifting of the transformers to the alternative site issued.

14. I have in this regard enquired from the counsel for the defendants No. 1 and 3 whether defendants No. 1 and 3 have initiated the process for shifting of the transformer and the electricity pole.

15. The reply is in the negative.

7,827 characters total

16. The same is also indicative of the fact that till an order is passed, the defendants No. 1 and 3 will not be spurred into action for relocating the transformer.

17. The plaintiff, from certified copies of judgments supra of this Court has proved her ownership of the property. The defendants No. 1 and 3 have not claimed any ownership right in the property. The only possible right of the defendants No. 1 and 3 could be either of a licencee or as a lessee. It is not the case that there is any registered lease. For this reason also, the question of the defendants No. 1 and 3 having any right to continue with the transformer and electrical pole in the property of the plaintiff does not arise.

18. The suit insofar as for the relief of mandatory injunction is accordingly decreed and a decree for mandatory injunction is passed, in favour of the plaintiff and against the defendant No.1 directing the defendant No.1 to remove the transformer and the electricity pole in property No.D-1/20, Rajouri Garden, New Delhi within three months from today.

19. Decree sheet be drawn up.

20. As far as the claim of the plaintiff for recovery of damages/mesne profit is concerned, the plaintiff has claimed the arrears of damages of Rs.23,32,000/- and future damages / mesne profits.

21. The counsel for the plaintiff on enquiry states that the plaintiff, for the first time called upon the defendants No. 1 and 3 to remove the transformer and electricity pole, on 15th April, 2015.

22. The claim for mesne profits/damages for use and occupation can be thereafter only say w.e.f. 1st May, 2015.

23. On the pleadings of the parties with respect to the said claim of the plaintiff, the following issues are framed:

1. To damages / mesne profits with effect from 1st May, 2015 at what rate, is the plaintiff entitled to from the defendant No.1 for not removing the transformer and electricity pole from Property No.D-1/20 Rajouri Garden, New Delhi of the plaintiff? OPP

2. Relief.

24. No other issue arise or is pressed.

25. The Parties to file their list of witnesses within 15 days.

26. The plaintiff to file affidavits by way of examination in chief of all her witnesses within eight weeks.

27. List before the Joint Registrar on 22nd September, 2016 for fixing dates of trial. IA.No.18536/2015 (u/O 39 Rules 1 and 2 CPC) & IA.No.7105/2016 (U.O 11 Rule 1 CPC)

28. Dismissed as not pressed.

RAJIV SAHAI ENDLAW, J JULY 14, 2016 M..