IN THE SUPREME COURT OF INDIA
I.A. NO.4
IN
CIVILAPPEAL NO. 2851 OF 2009
RATTAN SINGH .. APPELLANT
W I T H
I.A.NO.5
IN
CIVILAPPEAL NO. 2852 OF 2009
SARDAR SINGH .. APPELLANT
JUDGMENT
1. These Appeals were admitted before the commencement of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (for brevity ‘2013 Act’). Upon commencement thereof, the Appellants have changed the tack of their challenge by seeking to invoke the deemed lapse of proceedings under Section 24(2) of the 2013 Act. As we have repeatedly opined, any determination under this Section must proceed sequentially. First, the factum of an Award under Section 11 of the Land Acquisition Act, 1894, must be clearly established. The said Award must predate the commencement of the Act, i.e., 1.1.2014, by at least five years, i.e., the Award must have been passed on or before 1.1.2009. This having been established, if possession is found to not have been taken, or compensation not paid, then the proceedings shall be deemed to have lapsed. Thereafter, the appropriate Government, if it so chooses, may reinitiate acquisition proceedings in respect of the same land, but under the regime of the 2013 Act.
2 In the matter before us, a Section 4 Notification was issued on 13.11.1959, followed by a Section 6 Declaration on 12.7.1966. An Award was finally passed on 24.6.1968. The first requirement is thus made out. The possession of the land appears to be in dispute, as the Appellants allege that mere paper possession has been taken by the Respondent, while the Respondent alleges that possession was taken on 18.1.2000. Sagaciously, learned Counsel for the Appellants has steered away from this controversy. Instead, the Page 3 Appellants allege that compensation has not been paid to them as is evident from the affidavit of the Respondent where it has asseverated thus: “That the procedure adopted for payment of compensation is that after announcement of the Award, the land owner makes an application before the Land Acquisition Collector for payment of compensation awarded to him under the Award by submitting the documents showing his title to the land. The land owner is also required to execute a surety bond before receiving the payment of compensation. The aforesaid procedure was adopted by other land owners of this acquisition for whom different Awards were passed.” ….. “Contents of para (11) are not correct in the manner they have been stated. The possession of the land was taken on 18.01.2000 after announcement of the Award. It is submitted that the Appellant had filed his claim in pursuance of notice issued under Sections 9 and 10 of the Land Acquisition Act and had participated in the acquisition proceedings. The Appellant was even present when the Award was announced and yet he did not take any steps to receive compensation. He neither filed any application nor presented his document to show his title on the land. These are the steps required to be taken by the land owners to receive compensation. The other owners of the land, which was acquired under the same Notification, had filed the appropriate application and submitted the documents showing their title and also filed surety bond before receiving compensation. When the Appellant himself did not come forward to receive the compensation, the authorities cannot be faulted with for non-payment of compensation”.
3 The Respondent, on the other hand, has sought to contend that the procedure for payment of compensation is that after the announcement of the Award, the land owners make applications before the Land Acquisition Collector for payment of compensation by submitting documents showing their Page 4 title to the land and by executing a surety bond. This procedure was followed by other land owners who then received the compensation due to them. Since the Appellants chose not to comply with this procedure, it cannot be said that the compensation was not paid to them.
4 This Court has, in a number of decisions including (1) Pune Municipal Corporation vs. Harakchand Misirimal Solanki (2014) 3 SCC 183, (2) Union of India vs. Shiv Raj (2014) 6 SCC 564, (3) Bimla Devi vs. State of Haryana (2014) 6 SCC 583, (4) Competent Automobiles Co. Ltd. vs. Union of India AIR 2015 SC 3186, (5) Radiance Fincap (P) Ltd. vs. Union of India (2015) 8 SCC 544 and (6) Rajiv Chaudhari HUF vs. Union of India (2015) 3 SCC 541, elucidated the manner in which Section 24(2) is to be interpreted. In Pune Municipal Corporation, a three Judge Bench of this Court (which should bind all lesser as well as coordinate Benches) clarified the meaning of the expression “compensation has not been paid”. It discussed Section 31(1) of the 1894 Act, which enjoins the Collector, on making an Award under Section 11, to tender payment of compensation to persons interested entitled thereto. Section 31 mandates the Collector to make payment of compensation to such persons unless prevented by one of the contingencies contemplated in sub-section (2), namely (i) the persons interested entitled to compensation do not consent to receive it, (ii) there is no person competent to alienate the land, and (iii) there is dispute as to the title to receive compensation or as to the apportionment of it. If Page 5 due to any of these contingencies the Collector is prevented from making payment of compensation to the persons entitled to compensation, the Collector is required to deposit the compensation in the Court to which reference under Section 18 may be made. Thus compensation can be regarded as “paid” if the compensation has literally been paid to the person interested, or after being offered to such person, it has been deposited in the Court. The deposit of the Award in a Government Treasury would not amount to compensation being paid to the person interested. In order to send the matter to rest, since the same arguments are being regurgitated without end, the following paras from Pune Municipal Corporation are extracted:
18. The 1894 Act being an expropriatory legislation has to be strictly followed. The procedure, mode and manner for payment of compensation are prescribed in Part V (Sections 31-34) of the 1894 Act. The Collector, with regard to the payment of compensation, can only act in the manner so provided. It is settled proposition of law (classic statement of Lord Roche in Page 7 Nazir Ahmad) that where a power is given to do a certain thing in a certain way, the thing must be done in that way or not at all. Other methods of performance are necessarily forbidden.” 5 This Court in IVO Agnelo Santimano Fernandes vs. State of Goa (2011) 11 SCC 506, relying upon the earlier decision in Prem Nath Kapur vs. National Fertilizers Corporation of India Ltd. (1996) 2 SCC 71, had held that the deposit of the amount of the compensation in the State’s revenue account is of no avail and the liability of the State to pay interest subsists till the amount has not been deposited in Court.
6 In the current Appeals, compensation was neither paid to the Appellants nor deposited in the appropriate Court. The retention of it by the Land Acquisition Collector till such time as the Appellants made applications for it would not amount to compensation being paid to them. The contention of the Respondent is thus entirely erroneous. Since the Award predated the commencement of the 2013 Act by well over five years and compensation has not paid to the Appellants, Section 24(2) comes into operation in favour of the Appellants. Whether possession was taken by the Respondent need not be dilated upon nor need it detain us any further. The acquisition is deemed to have lapsed in these circumstances. The Respondent may initiate fresh acquisition proceedings in accordance with the provisions of the 2013 Act, if it so wishes. Page 8
7 In view of the foregoing, it is not necessary to consider the correctness of the impugned Judgment on merits. These Appeals are allowed with no orders as to costs. ……………………….…J [VIKRAMAJIT SEN] …………………………..J [SHIVA KIRTI SINGH] New Delhi; December 08, 2015.