GEPS Projects v. Indiabulls Estate Limited

Delhi High Court · 24 Jul 2025 · 2025:DHC:5993-DB
Navin Chawla; Madhu Jain
FAO (COMM) 191/2025
2025:DHC:5993-DB
civil appeal_dismissed Significant

AI Summary

The Delhi High Court upheld the dismissal of an interim injunction against encashment of an unconditional bank guarantee, affirming that such guarantees are independent contracts and can only be restrained on limited grounds.

Full Text
Translation output
FAO (COMM) 191/2025
HIGH COURT OF DELHI
Date of Decision: 24.07.2025
FAO (COMM) 191/2025
GEPS PROJECTS .....Appellant
Through: Mr.Akshay Srivastava and Mr.Suryansh Vashisth, Advs.
VERSUS
INDIABULLS ESTATE LIMITED .....Respondent
Through: None
CORAM:
HON'BLE MR. JUSTICE NAVIN CHAWLA
HON’BLE MS. JUSTICE MADHU JAIN
NAVIN CHAWLA, J. (ORAL)
JUDGMENT

1. Allowed, subject to all just exceptions. CM APPL. 44309/2025 (Exemption)

2. This appeal has been filed by the appellant, challenging the Order dated 08.07.2025 passed by the learned District Judge, Commercial Court-01, Patiala House Courts, New Delhi (hereinafter referred to as the, ‘Trial Court’) in OMP (I) COMM 01/2025, titled GEPS Projects v. Indiabulls Estate Limited, whereby the application filed by the appellant herein under Section 9 of the Arbitration and Conciliation Act, 1996 was dismissed. FAO (COMM) 191/2025 & CM APPL. 44308/2025

3. The appellant had filed the said application seeking an interim injunction against the respondent, restraining it from encashing the bank guarantee that had been submitted by the appellant to the respondent in terms of the Work Orders bearing Nos. 3210100078 and

3228105495.

4. The learned District Judge, however, placing reliance on the Judgment of the Supreme Court in Standard Chartered Bank v. Heavy Engineering Corporation. Ltd., (2020) 13 SCC 574; Vinitec Electronics Pvt. Ltd. v. HCL Infosystems Ltd., (2008) 1 SCC 544, and of this Court in CRSC Research and Design Institute Group Co. Ltd. v. Dedicated Freight Corridor Corpn. of India Ltd., 2020 SCC OnLine Del 1526, held that a bank guarantee being a separate contract, its invocation can be injuncted only on the limited grounds of fraud of an egregious nature, irretrievable injustice resulting to the parties, or special equities, and that no such case was made out in the present case.

5. The learned counsel for the appellant submits that the invocation of the bank guarantee was not in terms of Clause 18 (c) of the Work Order dated 09.10.2017, inasmuch as the bank guarantee could have been invoked only to the extent of the loss incurred by the respondent.

6. We are unable to accept the above submission of the learned counsel for the appellant.

7. The bank guarantee was unconditional in nature and, therefore, could be invoked on its own terms. The underlying contract, that is, the Work Order, being separate, the terms thereof would not override the unconditional nature of the bank guarantee.

8. Accordingly, we find no merit in the present appeal. The same, along with the pending application, is dismissed.

NAVIN CHAWLA, J MADHU JAIN, J JULY 24, 2025/sg/DG