Full Text
HIGH COURT OF DELHI
Date of Judgement: 5th February, 2018
KAMAL KANT BANSAL & ANR. .....Petitioners
Through: Mr. S.K. Rout and Mr. Aman Mehrotra, Advocates.
Through: Mr. Yeeshu Jain, Adv. with Ms. Jyoti Tyagi, Advocates for L&B/LAC.
HON'BLE MS. JUSTICE SANGITA DHINGRA SEHGAL G.S. SISTANI, J. (Oral)
JUDGMENT
1. This is a petition under Article 226 of Constitution of India filed by the petitioners seeking a declaration that the acquisition proceedings with respect to land bearing Khasra No. 31/20 min, admeasuring (0-12 Biswa) situated in the revenue estate of village Nangloi Jat, New Delhi, (hereinafter referred as the 'subject land') stand lapsed in view of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as '2013 Act') as no compensation has been paid to the petitioners.
2. In this case, a notification under Section 4 of the Land Acquisition Act, 1894 (hereinafter referred to as 'Act') was issued on 28.07.2006 and a declaration under Section 6 was made on 22.11.2006. Thereafter, an Award bearing no.1/2007-08 was 2018:DHC:890-DB passed on 06.08.2007. It is the case of the petitioners that the compensation with respect to subject land has not been tendered even though the possession of the land has been taken.
3. The counsel for the petitioners submits that since the compensation has not been tendered, the petitioners would be entitled to a declaration under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as 'the New Act'). Counsel for the petitioners has drawn the attention of the Court to the Counter Affidavit filed by LAC wherein it has been categorically stated that the compensation has not been paid.
4. Learned counsel for the petitioners further submits that since the compensation has not been tendered to the petitioners, the case of the petitioners would be fully covered by the decision rendered by the Apex Court in Pune Municipal Corporation & Anr. v. Harakchand Misirimal Solanki & ors., reported at (2014) 3 SCC
183.
5. Mr. Yeeshu Jain, learned Counsel for LAC submits that actual vacant physical possession of the subject land was taken on 28.09.2007, however the compensation was not paid. Para.[4] of the Counter affidavit filed by the LAC, reads as under:-
the spot. The compensation however could not be paid."
6. We have heard learned counsel for the parties.
7. Taking into consideration the submissions made and the categorical assertion made in the counter affidavit filed by LAC that the compensation has not been paid, we are of the view that, the case of the petitioners is fully covered by the decision rendered by the Apex Court in the case of Pune Municipal Corporation & Anr.(supra). Paras. 14 to 20 of aforesaid decision read as under:
18. 1894 Act being an expropriatory legislation has to be strictly followed. The procedure, mode and manner for payment of compensation are prescribed in Part V (Sections 31-34) of the 1894 Act. The Collector, with regard to the payment of compensation, can only act in the manner so provided. It is settled proposition of law (classic statement of Lord Roche in Nazir Ahmad[1]) that where a power is given to do a certain thing in a certain way, the thing must W.P. (C) No.866/2017 be done in that way or not at all. Other methods of performance are necessarily forbidden.
19. Now, this is admitted position that award was made on 31.01.2008. Notices were issued to the landowners to receive the compensation and since they did not receive the compensation, the amount (Rs.27 crores) was deposited in the government treasury. Can it be said that deposit of the amount of compensation in the government treasury is equivalent to the amount of compensation paid to the landowners/persons interested? We do not think so. In a comparatively recent decision, this Court in Agnelo Santimano Fernandes[2], relying upon the earlier decision in Prem Nath Kapur[3], has held that the deposit of the amount of the compensation in the state's revenue account is of no avail and the liability of the state to pay interest subsists till the amount has not been deposited in court.
20. From the above, it is clear that the award pertaining to the subject land has been made by the Special Land Acquisition Officer more than five years prior to the commencement of the 2013 Act. It is also admitted position that compensation so awarded has neither been paid to the landowners/persons interested nor deposited in the court. The deposit of compensation amount in the government treasury is of no avail and cannot be held to be equivalent to compensation paid to the landowners/persons interested. We have, therefore, no hesitation in holding that the subject land acquisition proceedings shall be deemed to have lapsed under Section 24(2) of the 2013 Act.”
8. Having regard to the submissions made and the stand taken by the LAC in the counter affidavit, we are of the considered view that the necessary ingredients for the application of Section 24(2) of the 2013 Act, as has been interpreted by the Supreme Court of India and this Court in the following cases stand answered: (1) Pune Municipal Corporation & Anr. v. Harakchand Misirimal Solanki & ors., reported at (2014) 3 SCC 183; (2) Union of India and Ors v. Shiv Raj and Ors., reported at
(3) Sree Balaji Nagar Residential Association v. State of Tamil Nadu and Ors, Civil Appeal no.8700/2013 decided on 10.09.2014; (4) Surender Singh v. Union of India & Others, W.P.(C).2294/2014 decided on 12.09.2014 by this Court; and (5) Girish Chhabra v. Lt. Governor of Delhi and Ors; W.P.(C).2759/2014 decided on 12.09.2014 by this Court.
9. Since the award having been announced more than five years prior to the commencement of the 2013 Act and, having regard to the stand taken by the LAC that the compensation has not been tendered, the petitioners are entitled to a declaration that the acquisition proceedings initiated under the Land Acquisition Act, 1894 with regard to the subject land are deemed to have lapsed. It is ordered accordingly.
9. The writ petition is disposed of. G.S.SISTANI, J. SANGITA DHINGRA SEHGAL, J. FEBRUARY 5, 2018