VIRENDER KUMAR TREHAN & ORS ..... Petitioners
Through Mr. Ashwin Vaish, Mr. Vinod Pandey, Mr. Kunal Arora & Mr. Sekh Zakir Hussain, Advocates.
Through Mr. Bhagvan Swarup Shukla with Mr. Kamaldeep, Advocates for UOI.
Mr. Yeeshu Jain, Standing Counsel with Ms. Jyoti Tyagi, Advocate for
L&B/LAC.
HON'BLE MS. JUSTICE SANGITA DHINGRA SEHGAL G.S.SISTANI, J. (ORAL)
1. By the present writ petition under Article 226 of the Constitution of India, petitioners seek a direction to quash the notification bearing no.F(11)(17)/91 L&B/LA/6518 dated 28.04.1995 issued under Section 4 of the Land Acquisition Act, 1894 (in short „the Act‟) as also the notification bearing no.F.11(17)/91/L&B/LA/Pt.V/1285 dated 26.04.2013 issued under Section 6 of the Act.
2. The necessary facts to be noticed for disposal of this writ petition are that the petitioners claim to be owners and in possession of 4 bighas 4 biswas of land comprised in Khasra no.244, situated in the revenue estate of village Shahibabad Daulatpur, Delhi, having purchased the same by means of a registered sale deed dated 30.05.1985 prior to the 2018:DHC:1968-DB notifications having been issued. It is also claimed that the land of the petitioners forms part of the unauthorized colony, which has been issued a provisional certificate for regularization known as Prahlad Vihar. In this case, post the issuance of a notification under Sections 4 & 17 of the Act i.e. 28.04.1995, a notification under Section 6 of the Act was issued on 26.04.1996. Aggrieved by the aforesaid notifications, similarly situated land owners had filed a writ petition in Delhi High Court being W. P. (C) 2326/2000 titled as “Bhupender Singh & Ors. Vs. Union of India & Ors.”.
3. It is also pointed out that vide order dated 09.07.2007 passed by the Delhi High Court, the case of the land owners was dismissed. Aggrieved by the order dated 09.07.2007 passed by the Delhi High Court various similarly situated land owners approached the Hon‟ble Supreme Court vide CA No. 3514-3517/2007 and various other connected matters. The Hon‟ble Supreme Court issued notice and granted interim stay of the order passed by the High Court of Delhi on 03.08.2007. By an order dated 21.03.2012, the Supreme Court was pleased to quash the declaration under Section 17 of the Act and directed the respondents to issue a notice under Section 5A of the Act to the petitioners.
4. It is not in dispute that pursuant to the order passed by the Hon‟ble Supreme Court, the LAC issued a general public notice thereby inviting objections under Section 5A of the Act. The petitioners approached the LAC and filed objections in his individual capacity and also through the Residents Welfare Association.
5. It is the case of the petitioners that a fresh declaration under Section 6 of the Act was made on 26.04.2013 after a lapse of the statutory period of one year. Learned counsel for the petitioners additionally submits that neither the possession of the land in question was taken nor the compensation has been paid. He further submits that since the fresh Section 6 notification was made after a lapse of more than one year, the case of the petitioners would be covered by the decision rendered by the Coordinate Bench of this Court in W. P. (C) 3049/2013 titled as Sunil Goel & Others Vs. The State and Others decided on 29.04.2014 when batch of cases were decided. Reliance is placed on para 18 of the judgment, which is reproduced as under:
6. It is further pointed out that the case of Sunil Goel (Supra) has attained finality as SLP preferred by the respondents stands dismissed in limine.
7. Learned counsel for the petitioners has also relied upon the relevant dates to draw the attention of the Court that the period of one year has lapsed and fresh notification under Section 6 of the Act is delayed by one year six months and eight days.
8. Mr. Jain, learned Standing Counsel for LAC has also drawn the attention of this Court to para 5 of the counter affidavit which is reproduced below:
9. Mr. Jain further submits that a fresh notification under Section 6 of the Act was issued within a period of one year of the judgment rendered by the Apex Court on 21.03.2012.
10. We have heard learned counsel for the parties.
11. Submissions of learned counsel for the petitioners are in two folds. Firstly, that since a Section 6 notification was issued post the statutory period of one year after deducting the period during which the acquisition proceedings remain stayed. Secondly, it is contended relying on the stand taken by the LAC in the counter affidavit that since neither the actual physical possession has not been taken nor compensation has been tendered, the case of the petitioners would squarely fall within the provisions of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as the „2013 Act‟).
12. Counsel for the petitioners has placed reliance on a notice dated 20.02.2015 issued to the petitioners by the Land Acquisition Collector to show that the Khasra numbers forming part of the present writ petition were included and the same also finds mentioned in the list filed at page 53 of the paper book.
13. The case of the petitioners is in our view is fully covered by the decision rendered in the case of Sunil Goel (Supra), wherein the Division Bench has relied on a decision of Hon‟ble Supreme Court in Padmasundara Rao (supra). The details of the time period applicable to the present case, is detailed below in the form of a chart. Time Lapse Date of Section 4 notification 28.04.1995 Date of stay granted by High Court 15.10.1996 16 months 12 days Date of dismissal from High Court 09.07.2007 Date of Notice and stay by the Hon‟ble Supreme Court 03.08.2007 1 month 24 days Date of decision by Hon‟ble Supreme Court quashing the declaration u/s & urgency clause u/s 17 of the Land Acquisition Act, 1894 21.03.2012 Declaration u/s 6 26.04.2013 1 year 1 month 1 day Total time lapse 2 years 6 months 8 days
14. Considering the time line we have detailed hereinabove leaves no room for doubt that the fresh notification under Section 6 of the Act was not issued within a period of one year after deducting the time spent in Court and covered by the stay order granted by the Court i.e. before the stay granted by the High Court and 24 days from 03.08.2007 being the period of stay granted by the Supreme Court. Resultantly, the writ petition is allowed. The notification dated 28.04.1995 under Section 4 of the Act and the fresh notification dated 26.04.2013 under Section 6 of the act are quashed.