Full Text
HIGH COURT OF DELHI
Date of Decision: 12.08.2025
GOVT OF NCT OF DELHI .....Appellant
Through: Mr. Tushar Sannu, ASC, Ms. Akita Bhadouriya, Mr Parvin Bansal, Advocates and Mr Ajay Shrivastava, AE(L) in person.
Through: Ms. Priya Kumar, Sr. Advocate
HON'BLE MR. JUSTICE VINOD KUMAR V. KAMESWAR RAO, J. (ORAL)
JUDGMENT
1. This is an appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 whereby, challenge is made to order dated 29.11.2016 passed by the learned Single Judge in OMP No. 218/2015, which is a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 for setting aside the award dated 08.09.2014 passed by the Arbitrator.
2. The learned Single Judge while dismissing the petition has in paragraph 26 stated as under:-
3. Some of the facts to be noted are that on 26.03.2003, an agreement in respect of construction of District Court Complex at Sector-16, Dwarka, New Delhi was entered between the appellant and the respondent. As per the agreement, the date of commencement of work was decided by the parties to be 05.04.2003 and the stipulated date of completion of work was 04.10.2005.On 26.07.2003, a letter was issued by the appellant stating that it is evident from the progress of work that the respondent was not able to achieve the required progress.
4. It was the case of the appellant that the respondent was not executing the contract as per the schedule stipulated in the agreement. It was also the case of the appellant that the Superintending Engineer has imposed penalty on the respondent on the ground of delay in execution of the work. This according to the appellant, empowers the Superintending Engineer to take such an action in terms of Clause 2. The contract also stipulated that the decision of the Superintending Engineer would be final and binding as per the Arbitration Clause 25. Such a dispute would be outside the purview of the arbitration clause. The effect of the decision of the Superintending Engineer was the bank guarantee furnished by the respondent, was encashed by the appellant.
5. As dispute(s) arose, the same became the subject matter of adjudication before the learned Arbitrator appointed by this Court. The learned Arbitrator has granted an amount of ₹2,93,57,480/- which is a claim made by the respondent herein. The amount is of the bank guarantee which has been furnished by the respondent. It may be necessary to state here that even the appellant herein has also made a counter claim for ₹1,32,27,380/on the ground that the said amount is the balance amount remaining to be recovered from the respondent after adjusting the amount of ₹2,93,57,480/-. Suffice to state that the learned Arbitrator has awarded the claims in favour of the respondent herein. The counter claim of the appellant was rejected. The subject matter of the present appeal is only in respect of claim no. 11 against which a sum of ₹2,93,57,480/- has been awarded.
6. The plea advanced before the learned Single Judge was that the claim no.11 was not arbitrable, in as much as, on a reading of clauses 2 and 25, the same is an excepted matter.
7. The said plea was rejected by the learned Single Judge by holding in paragraphs 21, 22 & 23 as under:-
would not fall for consideration and adjudication before the Arbitrator. If there is a concluded and undisputed fact regarding the contractor being responsible for the delay, no doubt under those circumstances the compensation determined by the Authority may not be arbitrable. However, the plea raised by the petitioner was not raised when the performance bank guarantees were invoked. The stand at that time was that the small part of the work was not completed by the contractor. Even then, what is made final and binding under the said clause is only the calculation of damages found payable by the contractor at a rate lower than those prescribed in the contract. No doubt, it is true that the clause 2 of the contract deals with the compensation for delay if the contractor fails to maintain the required progress. This compensation can be maintainable only if there is no dispute regarding the responsibility of the contractor for the failure to maintain the progress.
22. The said provision of Clause 2 of the GCC does not prohibit the claims raised. What is made final and binding under the said Clause is only the calculation of damages if found payable by the Contractor at a rate lower than those prescribed in the contract. This decision can be made by the Superintending Engineer only if there was no dispute in respect of the Contractor being in breach of the contract or responsible for the delays/prolongation. Such disputes cannot be adjudicated by the authority mentioned in the Contract, and this would necessarily fall in the jurisdiction of the Arbitrator or the Court, as the case may be. It is based on the principle that no party can be a judge in its own cause.
23. Clause-2 has been discussed by the Supreme Court in the case of J.G. Engineers Pvt. Ltd. v. Union of India and Anr., (2011) 5 SCC 758, the Court held as under:
breach and the forfeiture was illegal and directed that the said sum of rupees one lakh should be refunded to the contractor.
14. Claim 11 was for Rs. 54,03,669 being the loss of anticipated profit in regard to the value of the unexecuted work which would have been executed by the contractor if the contract had not been rescinded by the respondents. The contractor contended that the termination was in breach of the contract and but for such termination the contractor would have legitimately completed the work and earned a profit of 15%. The arbitrator held that the respondents were responsible for the delay, that the contractor was not in breach and the termination was therefore illegal. He held that the value of the work which could not be executed by the contractor due to wrongful termination, was Rs. 3,91,21,589 and 10% thereof would be the standard estimate of the loss of profits and consequently awarded Rs. 39,12,000 towards the loss of profits, which the contractor would have earned but for the wrongful termination of the contract by the respondents.
15. As per the arbitration agreement [contained in Clause (25) of the contract] all questions and disputes relating to the contract, execution or failure to execute the work, whether arising during the progress of the work or after the completion or abandonment thereof, “except where otherwise provided in the contract”, had to be referred to and settled by arbitration. The High Court held that Claims 1, 3 and 11 of the contractor were not arbitrable as they related to excepted matters in regard to which the decisions of the Superintending Engineer or the Engineer-in-charge had been made final and binding under Clauses (2) and (3) of the agreement.
16. We may refer to the relevant provisions of the said contract document, that is, Clauses (2), (3)(Part) and (25)(Part) to decide whether Claims 1, 3 and 11 were excepted matters, excluded from arbitration: Clause (2) “The time allowed for carrying out the work as entered in the tender shall be strictly observed by the contractor and shall be deemed to be essence of the contract and shall be reckoned from the tenth day after the date on which the order to commence the work is issued to the contractor. The work shall throughout the stipulated period of the contract be proceeded with all due diligence and the contractor shall pay as compensation an amount equal to one per cent or such smaller amount as the Superintending Engineer (whose decision in writing shall be final) may decide on the amount of the estimated cost of the whole work as shown in the tender, for every day that the work remains uncommenced or unfinished after the proper dates. And further to ensure good progress during the execution of the work, the contractor shall be bound in all cases in which the time allowed for any work exceeds one month (save for special jobs) to complete one-eighth of the whole of the work before one-fourth of the whole time allowed under the contract has elapsed, threeeighths of the works before one-half of such time has elapsed and three-fourths of the work before three-fourths of such time has elapsed. However for special jobs if a time schedule has been submitted by the contractor and the same has been accepted by the Engineer-in-charge. The contractor shall comply with the said time schedule. In the event of the contractor failing to comply with this condition, he shall be liable to pay as compensation an amount equal to one per cent or such small amount as the Superintending Engineer (whose decision in writing shall be final) may decide on the said estimated cost of the whole work for every day that the due quantity of work remains incomplete. Provided always that the entire amount of compensation to be paid under the provisions of this clause shall not exceed ten per cent, on the estimated cost of the work as shown in the tender.” Clause (3) “The Engineer-in-charge may without prejudice to his right against the contractor in respect of any delay or inferior workmanship or otherwise or to any claims for damage in respect of any breaches of the contract and without prejudice to any rights or remedies under any of the provisions of this contract or otherwise and whether the date of completion has or has not elapsed by notice in writing absolutely determine the contract in any of the following cases:
(i) If the contractor having been given by the Engineerincharge a notice in writing to rectify, reconstruct or replace any defective work or that the work is being performed in any inefficient or other improper or unworkmanlike manner, shall omit to comply with the requirements of such notice for a period of seven days thereafter or if the contractor shall delay or suspend the execution of the work so that either in the judgment of the Engineer-in-charge (whose decision shall be final and binding) he will be unable to secure completion of the work by the date of completion or he has already failed to complete the work by that date…. (ii) (not relevant)
(iii) If the contractor commits breach of any of the terms and conditions of this contract.
(iv) If the contractor commits any acts mentioned in Clause
(21) hereof. When the contractor has made himself liable for action under any of the cases aforesaid, the Engineer-incharge on behalf of the President of India shall have powers: (a) To determine or rescind the contract as aforesaid (of which termination or rescission notice in writing to the contractor under the hand of the Engineer-incharge shall be conclusive evidence) upon such determination or rescission the security deposit of the contractor shall be liable to be forfeited and shall be absolutely at the disposal of the Government. (b) (not relevant)
(c) After giving notice to the contractor to measure up the work of the contractor and to take such part thereof as shall be unexecuted out of his hands and to give it to another contractor to complete in which case any expenses which may be incurred in excess of the sum which would have been paid to the original contractor if the whole work had been executed by him (of the amount of which excess the certificate in writing of the Engineer-in-charge shall be final and conclusive) shall be borne and paid by the original contractor and may be deducted from any money due to him by the Government under this contract or on any other account whatsoever or from his security deposit or the proceeds of sales thereof or a sufficient part thereof as the case may be. In the event of any one or more of the above courses being adopted by the Engineer-in-charge the contractor shall have no claim to compensation for any loss sustained by him by reason of his having purchased or procured any materials or entered into any engagements or made any advances on account of or with a view to the execution of the work or the performance of contract. And in case action is taken under any of provisions aforesaid, the contractor shall not be entitled to recover or be paid any sum for any work thereof or actually performed under this contract unless and until the Engineer-in-charge has certified in writing the performance of such work and the value payable in respect thereof and he shall only be entitled to be paid the value so certified.” Clause (25) “Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, designs, drawings and instructions hereinbefore mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or the execution of failure to execute the same whether arising during the progress of the work or after the completion or abandonment thereof shall be referred to the sole arbitration of the person appointed by the Chief Engineer, CPWD in charge of the work at the time of dispute or if there be no Chief Engineer the administrative head of the said CPWD at the time of such appointment. It will be no objection to any such appointment that the arbitrator so appointed is a government servant, that he had to deal with the matters to which the contract relates and that in the course of his duties as government servant he has expressed views on all or any of the matters in dispute or difference.”
17. Clauses (2) and (3) of the contract relied upon by the respondents no doubt make certain decisions by the Superintending Engineer and Engineer-in-charge final/final and binding/final and conclusive, in regard to certain matters. But the question is whether Clauses (2) and (3) of the agreement stipulate that the decision of any authority is final in regard to the responsibility for the delay in execution and consequential breach and therefore exclude those issues from being the subject-matter of arbitration. We will refer to and analyse each of the “excepted matters” in Clauses (2) and (3) of the agreement to find their true scope and ambit:
(i) Clause (2) provides that if the work remains uncommenced or unfinished after proper dates, the contractor shall pay as compensation for every day's delay an amount equal to 1% or such small amount as the Superintending Engineer (whose decision in writing shall be final) may decide on the estimated cost of the whole work as shown in the tender. What is made final is only the decision of the Superintending Engineer in regard to the percentage of compensation payable by the contractor for every day's delay, that is, whether it should be 1% or lesser. His decision is not made final in regard to the question as to why the work was not commenced on the due date or remained unfinished by the due date of completion and who was responsible for such delay.
(ii) Clause (2) also provides that if the contractor fails to ensure progress as per the time schedule submitted by the contractor, he shall be liable to pay as compensation an amount equal to 1% or such smaller amount as the final) may decide on the estimated cost of the whole work for every day the due quantity of the work remains incomplete, subject to a ceiling of ten per cent. This provision makes the decision of the Superintending Engineer final only in regard to the percentage of compensation (that is, the quantum) to be levied and not on the question as to whether the contractor had failed to complete the work or the portion of the work within the agreed time schedule, whether the contractor was prevented by any reasons beyond its control or by the acts or omissions of the respondents, and who is responsible for the delay.
(iii) The first part of Clause (3) provides that if the contractor delays or suspends the execution of the work so that either in the judgment of the Engineer-incharge (which shall be final and binding), he will be unable to secure the completion of the work by the date of completion or he has already failed to complete the work by that date, certain consequences as stated therein, will follow. What is made final by this provision is the decision of the Engineer-in-charge as to whether the contractor will be able to secure the completion of the work by the due date of completion, which could lead to the termination of the contract or other consequences. The question whether such failure to complete the work was due to reasons for which the contractor was responsible or the Department was responsible, or the question whether the contractor was justified in suspending the execution of the work, are not matters in regard to which the decision of the Engineer-in-charge is made final.
(iv) The second part of Clause (3) of the agreement provides that where the contractor had made himself liable for action as stated in the first part of that clause, the Engineer-incharge shall have powers to determine or rescind the contract and the notice in writing to the contractor under the hand of the Engineer-in-charge shall be conclusive evidence of such termination or rescission. This does not make the decision of the Engineer-in-charge as to the validity of determination or rescission, valid or final. In fact it does not make any decision of the Engineer-in-charge final at all. It only provides that if a notice of termination or rescission is issued by the Engineer-in-charge under his signature, it shall be conclusive evidence of the fact that the contract has been rescinded or determined.
(v) After determination or rescission of the contract, if the
Engineer-in-charge entrusts the unexecuted part of the work to another contractor, for completion, and any expense is incurred in excess of the sum which would have been paid to the original contractor if the whole work had been executed by him, the decision in writing of the Engineer-in-charge in regard to such excess shall be final and conclusive, shall be borne and paid by the original contractor. What is made final is the actual calculation of the difference or the excess, that is, if the value of the unexecuted work as per the contract with the original contractor was Rs. 1 lakh and the cost of getting it executed by an alternative contractor was Rs. 1,50,000 what is made final is the certificate in writing issued by the Engineer-in-charge that Rs. 50,000 is the excess cost. The question whether the determination or rescission of the contractor by the Engineer-in-charge is valid and legal and whether it was due to any breach on the part of the contractor, or whether the contractor could be made liable to pay such excess, are not issues on which the decision of
18. Thus what is made final and conclusive by Clauses (2) and (3) of the agreement, is not the decision of any authority on the issue whether the contractor was responsible for the delay or the Department was responsible for the delay or on the question whether termination/rescission is valid or illegal. What is made final, is the decisions on consequential issues relating to quantification, if there is no dispute as to who committed breach. That is, if the contractor admits that he is in breach, or if the arbitrator finds that the contractor is in breach by being responsible for the delay, the decision of the Superintending Engineer will be final in regard to two issues. The first is the percentage (whether it should be 1% or less) of the value of the work that is to be levied as liquidated damages per day. The second is the determination of the actual excess cost in getting the work completed through an alternative agency. The decision as to who is responsible for the delay in execution and who committed breach is not made subject to any decision of the respondents or its officers, nor accepted from arbitration under any provision of the contract.
19. In fact the question whether the other party committed breach cannot be decided by the party alleging breach. A contract cannot provide that one party will be the arbiter to decide whether he committed breach or the other party committed breach. That question can only be decided by only an adjudicatory forum, that is, a court or an Arbitral Tribunal.”
8. We may also at this stage state paragraphs 14-15 of the order of the learned Single Judge which we reproduce as under:-
9. The plea of Mr. Tushar Sannu, learned counsel for appellant, is that the learned Single Judge has erred in deciding the issue which was raised by the appellant before the learned Single Judge, that the claim no. 11 is not arbitrable as untenable. He states, no doubt that the aspect of the delay in execution of work being attributable to the respondent is collateral issue, which can be decided, but there is no finding on that. In the absence of any finding on delay, the claim no.11 could not have been allowed in favour of the respondent. He submits that there is enough evidence on record to show that the delay in executing the contract was attributable to the respondent and as such, on no ground the claim could have been allowed in favour of the respondent.
10. On the other hand, Ms. Priya Kumar, learned Senior counsel for respondent justifies the conclusion drawn by learned Arbitrator in awarding claim no. 11. She states that a reading of clauses 2 and 25 only denotes that it is the penalty imposed by the Superintending Engineer which is final and not a collateral issue that is at whose behest the delay has occurred in executing the work, which is the basis for imposing penalty by the Superintending Engineer. The learned Arbitrator has rightly held that the issue of refund sought by the respondent from the appellant in terms of claim no. 11 is arbitrable and could be decided and granted by holding that the delay occurred not at the behest of the respondent. In this regard, she draws our attention to the award of the learned Arbitrator to contend that there is a clear finding of the learned Arbitrator that the delay, if any, was not attributable to the respondent herein.
11. She says that the aforesaid conclusion of the learned Arbitrator negates the submission of Mr. Sannu that there is no finding of the learned Arbitrator on the said issue. ANALYSIS:
12. Having heard the learned counsel for the parties, we agree with the conclusion drawn by the learned Arbitrator, as upheld by the learned Single Judge, as highlighted by Ms. Kumar. Ms. Kumar is justified in relying upon the judgment of the Supreme Court in the case of J.G. Engineers Pvt. Ltd Vs. Union of India and Anr. (2011) 5 SSC 758, wherein, the Supreme Court has, on a similar issue held in paragraph 17 stated as under:- “17. Clauses (2) and (3) of the contract relied upon by the respondents no doubt make certain decisions by the Superintending Engineer and Engineer-in-charge final/final and binding/final and conclusive, in regard to certain matters. But the question is whether Clauses (2) and (3) of the agreement stipulate that the decision of any authority is final in regard to the responsibility for the delay in execution and consequential breach and therefore exclude those issues from being the subject-matter of arbitration. We will refer to and analyse each of the “excepted matters” in Clauses (2) and (3) of the agreement to find their true scope and ambit:
(i) Clause (2) provides that if the work remains uncommenced or unfinished after proper dates, the contractor shall pay as compensation for every day's delay an amount equal to 1% or such small amount as the Superintending Engineer (whose decision in writing shall be final) may decide on the estimated cost of the whole work as shown in the tender. What is made final is only the decision of the Superintending Engineer in regard to the percentage of compensation payable by the contractor for every day's delay, that is, whether it should be 1% or lesser. His decision is not made final in regard to the question as to why the work was not commenced on the due date or remained unfinished by the due date of completion and who was responsible for such delay.
(ii) Clause (2) also provides that if the contractor fails to ensure progress as per the time schedule submitted by the contractor, he shall be liable to pay as compensation an amount equal to 1% or such smaller amount as the final) may decide on the estimated cost of the whole work for every day the due quantity of the work remains incomplete, subject to a ceiling of ten per cent. This provision makes the decision of the Superintending Engineer final only in regard to the percentage of compensation (that is, the quantum) to be levied and not on the question as to whether the contractor had failed to complete the work or the portion of the work within the agreed time schedule, whether the contractor was prevented by any reasons beyond its control or by the acts or omissions of the respondents, and who is responsible for the delay.
(iii) The first part of Clause (3) provides that if the contractor delays or suspends the execution of the work so that either in the judgment of the Engineer-incharge (which shall be final and binding), he will be unable to secure the completion of the work by the date of completion or he has already failed to complete the work by that date, certain consequences as stated therein, will follow. What is made final by this provision is the decision of the Engineer-in-charge as to whether the contractor will be able to secure the completion of the work by the due date of completion, which could lead to the termination of the contract or other consequences. The question whether such failure to complete the work was due to reasons for which the contractor was responsible or the Department was responsible, or the question whether the contractor was justified in suspending the execution of the work, are not matters in regard to which the decision of the
(iv) The second part of Clause (3) of the agreement provides that where the contractor had made himself liable for action as stated in the first part of that clause, the Engineer-incharge shall have powers to determine or rescind the contract and the notice in writing to the contractor under the hand of the Engineer-in-charge shall be conclusive evidence of such termination or rescission. This does not make the decision of the Engineer-in-charge as to the validity of determination or rescission, valid or final. In fact it does not make any decision of the Engineer-in-charge final at all. It only provides that if a notice of termination or rescission is issued by the Engineerin-charge under his signature, it shall be conclusive evidence of the fact that the contract has been rescinded or determined.
(v) After determination or rescission of the contract, if the
Engineer-in-charge entrusts the unexecuted part of the work to another contractor, for completion, and any expense is incurred in excess of the sum which would have been paid to the original contractor if the whole work had been executed by him, the decision in writing of the Engineer-in-charge in regard to such excess shall be final and conclusive, shall be borne and paid by the original contractor. What is made final is the actual calculation of the difference or the excess, that is, if the value of the unexecuted work as per the contract with the original contractor was Rs. 1 lakh and the cost of getting it executed by an alternative contractor was Rs. 1,50,000 what is made final is the certificate in writing issued by the Engineer-in-charge that Rs. 50,000 is the excess cost. The question whether the determination or rescission of the contractor by the Engineer-in-charge is valid and legal and whether it was due to any breach on the part of the contractor, or whether the contractor could be made liable to pay such excess, are not issues on which the decision of Engineer-in-charge is made final.” (Emphasis supplied)
13. She is also justified in highlighting the conclusion drawn by the learned Arbitrator to hold that because five agencies were engaged by the appellant and were simultaneously working in the premises of Court building, hindrances were caused due to interconnected nature of works being exercised by the five agencies. This conclusion of the learned Arbitrator has not been contested by the appellant.
14. From the above, it is clear that the learned Arbitrator has rightly held that the delay in executing the work cannot be attributed to the respondent herein. We agree with the said conclusion. The same has been upheld by the learned Single Judge. We do not see any merit in the appeal. The same is dismissed.
15. The pending applications also stand dismissed, being infructuous.
V. KAMESWAR RAO, J
VINOD KUMAR, J AUGUST 12, 2025 rk