Full Text
HIGH COURT OF DELHI
Date of
JUDGMENT
NATIONAL HIGHWAYS AUTHORITY OF INDIA..... Appellant
Through Dr. Maurya Vijay Chandra & Ms. Meenu Chandra, Advocates.
Through Mr. Dayan Krishnan, Sr. Advocate with Mr. Rishi Agrawala, Ms. Sanjeevi Sisadhari & Ms. Shrouti Arora, Advocates.
HON'BLE MS. JUSTICE SANGITA DHINGRA SEHGAL G.S. SISTANI, J. (ORAL)
1. Exemption allowed, subject to all just exceptions.
2. The application stands disposed of. CM.APPL 43312/2018 (delay in re-filing)
3. This application has been filed by the applicant/appellant seeking condonation of 4 days delay in re-filing the appeal.
4. Prayer made in this application is not opposed. Accordingly, the same is allowed. Delay of 4 days in re-filing the appeal is condoned.
5. The application stands disposed of. FAO(OS) (COMM) 234/2018
6. The present appeal has been filed under Section 37 of the Arbitration and Conciliation Act, 1996 read with Section 13 of the Commercial 2018:DHC:6769-DB Courts Act, 2015 for setting aside the judgment/order dated 02.07.2018 passed by learned Single Judge of this Court whereby it has been held that the award dated 03.09.2017 to the extent that it refused to award the claim amount has been found to be not perverse.
7. We may also note that the counter claim of the respondent was rejected by the Arbitrator, which was also a subject matter of a separate petition under Section 34 of the Arbitration and Conciliation Act, 1996. However, the learned Single Judge allowed the objections of the appellant herein with respect to counter claim raised by the respondent. Disputes arose between the parties with respect to the agreement dated 21.10.2005 entered into between the parties in relation to works to be carried out at Lucknow-Muzaffarpur Highway project NH-4. The Tribunal rejected the claim of the appellant herein while allowing the counter claim of the respondent with interest. The subject matter of this appeal relates to rejecting the claim of interest of deferment of recovery of mobilization and equipment advance as per clause 60 of the Conditions of Particular Application (COCA) preferred by NHAI.
8. Dr. Chandra, counsel for the appellant submits that no doubt at the request of respondent, NHAI agreed deferment of recovery of mobilization and equipment advances from monthly IPCs with interest at the rate of SBI PLR + 2% on deferred amount for a period of three months but the Arbitrator and the learned Single Judge have completely misread and misunderstood the concessions shown by NHAI to the contractor for the reason that at the end of three months, not only was the respondent/contractor suppose to pay the interest as agreed to but also the actual amount, which had been deferred amounting to Rs.6,24,72,455/-. It is thus contended that the effect of the interpretation given by the Arbitrator and learned Single Judge has resulted in loss to NHAI to the tune of Rs.3,19,14,314/- as the amount of Rs.6,24,72,455/- was merged in the total mobilization advance and deductions were made only at the end of the contract.
9. Mr. Dayan Krishnan, learned senior counsel, appearing for the respondent submits that there is no infirmity, impropriety in the award as also the order passed by the learned Single Judge which would require interference in proceedings arising out of Section 37 of the Arbitration and Conciliation Act, 1996. He submits that the understanding of the parties were crystal clear and the reason for seeking such adjustment was as the work did not progress as scheduled and the respondent had claimed that the delay in execution of the work was attributable to NHAI as it has failed to handover the site within the stipulated period and further the site handed over was not free from encumbrances besides there was other delay beyond the control of the contractor. It is for this reason that 20% of the contract was not complied within the period of 12 months and the recovery of mobilization advance would have resulted in great prejudice and financial loss to the respondent. It is contended that this aspect was appreciated by NHAI and it is only for this reason that NHAI agreed to deferment of recovery of mobilization advance, which was not stipulated, as per the terms of the contract. It is emphasized by Mr. Krishnan, had the respondent been at fault, NHAI would not have granted this concession to the respondent. He further submits that this was the only understanding and only interpretation of the communication exchanged between the parties, which was plausible and in the present proceeding, this Court cannot substitute its own view unless the view taken by the Arbitrator was highly unreasonable, improbable and illegal.
10. We have heard learned counsels for the parties. In para aforegoing, we have set out the relevant clauses around which the disputes between the parties revolved. The operative portion of two communications dated 19.04.2007 and 17.05.2007 exchanged between the parties read as under: “19.04.2007 In pursuance of the further discussions on the above subject, we do hereby undertake that the interest @ SBI PLR + 2%, on the recoverable amounts of advance (30% of the gross IPC value), which will actually be deferred from various interim payment certificate, beyond the actual date of recovery for a further period of 3 months or till the progress reaches 20%, whichever is earlier would be borne by us.” “17.05.2007 Sir, With reference in the above mentioned subject it is to inform that NHAI has agreed for the following:i. Deferment of recovery of mobilization and equipment advances from monthly IPCs with interest rate at SBI PLR + 2% on deferred amount for the period of next three months from the date of issue of this letter. This issues with the approval of competent authority.”
11. It is not in doubt and not in dispute that for IPC nos.8, 9 & 10, NHAI did not recover the proportionate figure of mobilization advance from the respondent. It is also not disputed that the respondent paid interest as agreed between the parties, which is reflected in table given below: IPC No. Gross IPC Amount (Rs.) 30% of Gross IPC Amount (Rs.) Amount of Interest @ SBI – PLR + 2% (i.e. 12.75% + 2%) Rs. Recovery of Interest in IPC No. a b=ax30% c=bx(12.75+2)%/12 d=c 8 7,71,90,097 2,31,57,029 2,84,638 IPC No.8 9 7,47,65,702 2,24,29,711 5,60,337 IPC No.9 10 5,62,85,718 1,68,85,715 13,28,228 IPC No.10 Total: 6,24,72,455 21,73,203
12. It is also not disputed before us during the course of hearing that post IPC no.10 i.e. IPC no.11 onwards the sailing was smooth, the mobilization advance was recovered and no concession was sought.
13. Dr. Chandra has strongly urged before us that at the end of IPC no.10, the respondent was liable to pay the amount recoverable and this amount could not have merged with the remaining amount. In our view, the interpretation of a contract purely lies within the domain of the Arbitrator and we see no reason to interfere in the view of the Arbitrator, which is found to be accepted by the learned Single Judge, the same is neither illegal nor irrational but plausible. In the case of Associate Builders Vs. Delhi Development Authority, reported at (2015) 3 SCC 49, it has been held as under:
14. Even otherwise, the scope of interference in proceeding under Section 37 of Arbitration and Conciliation Act, 1996 is even narrower. In the case of State Trading Corporation of India Vs. Helm Dungemittel GMBH & Anr., FAO (OS) (COMM) 76/2016 decided on 30.05.2018, this Court has held as under:
29. The scope of judicial scrutiny and interference by an appellate court under Section 37 of the Act is even more restricted in comparison to deciding objections to the Award under Section 34 of the Act. In the case of State Trading Corporation of India Ltd. v. Toepfer International Asia Pte. Ltd, reported at 2014(144) DRJ 220(DB), in para 16 it has been held as under:
30. In the case of Steel Authority of India v. Gupta Brothers Steel Tubes Limited, (2009) 10 SCC 63, the Supreme Court has laid down that an error relatable to interpretations of the contract by an Arbitrator is an error within his jurisdiction and such error is not amenable to correction by Courts as such error is not an error on the face of the award. The Supreme Court has further laid down that the Arbitrator having been made the final arbiter of resolution of disputes between the parties, the award is not open to challenge on the ground that the Arbitrator has reached a wrong conclusion. The courts do not interfere with the conclusion of the Arbitrator even with regard to the construction of contract, if it is a plausible view of the matter.”
15. Applying the law to the facts of the present case, the table which we have extracted above, in clear terms would show, that in terms of the arrangement arrived at between the parties, the respondent paid the interest for IPC nos.8, 9 & 10 and the mobilization advance, which was received by the respondent stands completely paid to the appellant herein. We find no ground to interfere. Accordingly, the appeal is dismissed.
16. No costs. G.S.SISTANI, J. SANGITA DHINGRA SEHGAL, J. OCTOBER 15, 2018 ck