Rudra Developers and Contractors v. H. S. Oberoi Buildtech Pvt. Limited

Delhi High Court · 20 Aug 2025 · 2025:DHC:7341
Purushaindra Kumar Kaurav
ARB.P. 985/2025
2025:DHC:7341
civil petition_allowed Significant

AI Summary

The Delhi High Court appointed an arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996, holding that judicial scrutiny at this stage is limited to prima facie existence of an arbitration agreement, leaving merits to the arbitral tribunal.

Full Text
Translation output
$-O-10 HIGH COURT OF DELHI
ARB.P. 985/2025
Date of Decision: 20.08.2025 IN THE MATTER OF:
RUDRA DEVELOPERS AND CONTRACTORS 203, SRI VARI ENCLAVE, HORAMAVU AGARA, BANGALORE, BENGALURU, KAMATAKA - 560043 ..... PETITIONER
Through: Mr.Kunal Kumar, Advocate.
VERSUS
H. S. OBEROI BUILDTECH PVT. LIMITED KHASRA NO. 593, MANDI ROAD, GADAIPUR BUS STAND, MEHRAULI, NEW DELHI - 110030 .... RESPONDENT
Through: Mr.Yugansh Mittal, Mr.Pawan Mittal, Mr.Keshav Poonia and Mr.Mridur
Gupta, Advocates.
HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
JUDGEMENT
PURUSHAINDRA KUMAR KAURAV, J. (ORAL)
JUDGMENT

1. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (the 1996 Act) by the petitioner, seeking appointment of an Arbitrator, to adjudicate upon the disputes that have arisen between the parties under the Work Order dated 14.04.2023.

KUMAR KAURAV

2. The facts of the case indicate that the petitioner was engaged as an Interior Designer for the Tiruchirappalli International Airport, pursuant to a main contract between the respondent (contractor) and the Airports Authority of India (AAI). A Work Order amounting to INR 3,04,03,922 (Indian Rupees Three Crores Four Lakhs Three Thousand Nine Hundred and Twenty-Two only), exclusive of GST ("Work Order"), was issued to the petitioner in April 2023 on a back-to-back payment basis, wherein the petitioner’s payment was contingent upon disbursement by AAI.

3. As per the case set up by the petitioner, despite the petitioner’s prompt commencement of work, execution was hindered due to incomplete site handover (with certain portions held by another contractor), delayed payments (despite AAI having released funds), and unprofessional conduct by the respondent (including verbal abuse and threats). It is further submitted that the respondent arbitrarily and illegally terminated the contract in July 2023, falsely attributing the delay to the petitioner. Post-termination, the respondent allegedly withheld payments, unlawfully retained the petitioner’s materials, and subsequently raised baseless counterclaims amounting to INR 3,12,212 (Indian Rupees Three Lakhs Twelve Thousand Two Hundred and Twelve only), along with a demand for interest at the rate of 24%. The petitioner refuted the respondent’s claims and issued legal notices dated 05 July 2024 and 02 September 2024. Although meetings were held between the parties in an attempt to reach an amicable settlement, no resolution was achieved. Accordingly, the petitioner was constrained to issue a notice invoking arbitration on 07 February 2025. However, the respondent has failed to respond to the said notice to date. It is submitted that despite the aforementioned efforts, the dispute remains unresolved, and hence, the petitioner has filed the present petition.

4. On notice being issued, learned counsel, who appears on behalf of the respondent without admitting to the contents of the petition submits that the matter can be sent for mediation, however, the same is not agreeable to the learned counsel for the petitioner and he contends that earlier efforts were made but the dispute remained unresolved.

5. Under the aforesaid circumstances, the Court has looked into Clause 27 of the Work Order dated 14.04.2023 which provides for arbitration. The said Clause is extracted as under:-

“27 Arbitration clause: This clause will be as per tender document. If the contractor be dissatisfied with the client or with the consultant on terms and conditions or any matter, under such cases either party (the client or the contractor) may seek settlement through arbitration proceedings in accordance with the Indian Arbitration and Conciliation Act 1996 in force. The venue of arbitration shall be in New Delhi. The governing law of this agreement and of the relations of the parties arising from it and of any arbitration pursuant to it shall be the laws of the Republic of India provided always that the employer shall not withhold the payment of any interim certificate or the contractor except with the consent in writing of the consultant in any way delay the carrying out of the works by any reasons of any such matters, question or dispute being referred to arbitration but shall proceed with the work with all due diligence and shall, until completion of the arbitration proceedings, relieve the main contractor of his obligations to adhere strictly to the client and Consultant's instructions with regards to the actual carrying out of the works. Further disagreement, if any, after Arbitration Award may be resolved through Court of Law. All such disputes arising out of the matters in connection with this agreement shall be deemed to have arisen at New Delhi and only courts in New Delhi shall have the jurisdiction to determine the same. The same shall however be progressed as per time schedule, independent of such exigencies unless the client desires otherwise.”

6. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. This Court as well in the order dated 24.04.2025 in the case of ARB.P. 145/2025 titled as Pradhaan Air Express Pvt Ltd v. Air Works India Engineering Pvt Ltd has extensively dealt with the scope of interference at the stage of Section

11. The Court held as under:-

“9. The law with respect to the scope and standard of judicial scrutiny
under Section 11(6) of the 1996 Act has been fairly well settled. The
Supreme Court in the case of SBI General Insurance Co. Ltd. v. Krish
Spinning1, while considering all earlier pronouncements including the
Constitutional Bench decision of seven judges in the case of Interplay
between Arbitration Agreements under the Arbitration & Conciliation
12,451 characters total
Act, 1996 & the Indian Stamp Act, 1899, In re 2 has held that scope of
inquiry at the stage of appointment of an Arbitrator is limited to the
extent of prima facie existence of the arbitration agreement and nothing
else.
10. It has unequivocally been held in paragraph no.114 in the case of
SBI General Insurance Co. Ltd that observations made in Vidya Drolia
v. Durga Trading Corpn.3, and adopted in NTPC Ltd. v. SPML Infra Ltd.,4 that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non-arbitrable and frivolous disputes would not apply after the decision of Re: Interplay. The abovenoted paragraph no.114 in the case of SBI General Insurance Co. Ltd reads as under:- “114. In view of the observations made by this Court in In Re: Interplay (supra), it is clear that the scope of enquiry at the stage of appointment of arbitrator is limited to the scrutiny of prima facie existence of the arbitration agreement, and nothing else. For this reason, we find it difficult to hold that the observations made in Vidya Drolia (supra) and adopted in NTPC v. SPML (supra) that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non-arbitrable and frivolous disputes would continue to apply despite the subsequent decision in In

2024 SCC OnLine SC 1754 2 2023 SCC OnLine SC 1666.

11. Ex-facie frivolity and dishonesty are the issues, which have been held to be within the scope of the Arbitral Tribunal which is equally capable of deciding upon the appreciation of evidence adduced by the parties. While considering the aforesaid pronouncements of the Supreme Court, the Supreme Court in the case of Goqii Technologies (P) Ltd. v. Sokrati Technologies (P) Ltd.5, however, has held that the referral Courts under Section 11 must not be misused by one party in order to force other parties to the arbitration agreement to participate in a timeconsuming and costly arbitration process. Few instances have been delineated such as, the adjudication of a non-existent and malafide claim through arbitration. The Court, however, in order to balance the limited scope of judicial interference of the referral Court with the interest of the parties who might be constrained to participate in the arbitration proceedings, has held that the Arbitral Tribunal eventually may direct that the costs of the arbitration shall be borne by the party which the Arbitral Tribunal finds to have abused the process of law and caused unnecessary harassment to the other parties to the arbitration.

12. It is thus seen that the Supreme Court has deferred the adjudication of aspects relating to frivolous, non-existent and malafide claims from the referral stage till the arbitration proceedings eventually come to an end. The relevant extracts of Goqii Technologies (P) Ltd. reads as under:-

“20. As observed in Krish Spg. [SBI General Insurance Co. Ltd. v. Krish Spg., (2024) 12 SCC 1 : 2024 SCC OnLine SC 1754 : 2024 INSC 532] , frivolity in litigation too is an aspect which the referral court should not decide at the stage of Section 11 as the arbitrator is equally, if not more, competent to adjudicate the same. 21. Before we conclude, we must clarify that the limited jurisdiction of the referral courts under Section 11 must not be misused by parties in order to force other parties to the arbitration agreement to participate in a time consuming and costly arbitration process. This is possible in instances, including but not limited to, where the claimant canvasses the adjudication of non-existent and mala fide claims through arbitration.

22. With a view to balance the limited scope of judicial interference of the referral courts with the interests of the parties who might be constrained to participate in the arbitration proceedings, the Arbitral Tribunal may direct that the costs of the arbitration shall be borne by the party which the Tribunal ultimately finds to have abused the process of law and caused unnecessary harassment to the other party to the arbitration. Having said that, it is clarified that the aforesaid is not to be construed as a determination of the merits of the matter before us, which the Arbitral Tribunal will rightfully be equipped to determine.”

13. In view of the aforesaid, the scope at the stage of Section 11 proceedings is akin to the eye of the needle test and is limited to the extent of finding a prima facie existence of the arbitration agreement and nothing beyond it. The jurisdictional contours of the referral Court, as meticulously delineated under the 1996 Act and further crystallised through a consistent line of authoritative pronouncements by the Supreme Court, are unequivocally confined to a prima facie examination of the existence of an arbitration agreement. These boundaries are not merely procedural safeguards but fundamental to upholding the autonomy of the arbitral process. Any transgression beyond this limited judicial threshold would not only contravene the legislative intent enshrined in Section 8 and Section 11 of the 1996 Act but also risk undermining the sanctity and efficiency of arbitration as a preferred mode of dispute resolution. The referral Court must, therefore, exercise restraint and refrain from venturing into the merits of the dispute or adjudicating issues that fall squarely within the jurisdictional domain of the arbitral tribunal. It is thus seen that the scope of enquiry at the referral stage is conservative in nature. A similar view has also been expressed by the Supreme Court in the case of Ajay Madhusudan Patel v. Jyotrindra S. Patel”6.

9. In view of the fact that disputes have arisen between the parties and there is an arbitration clause in the contract, this Court is inclined to appoint an Arbitrator to adjudicate upon the disputes between the same.

10. Accordingly, Ms. Narayani Sepaha, Advocate (Mobile No.+91 8827949336, e-mail id:- narayanisepaha.legal@gmail.com ) is appointed as the sole Arbitrator.

11. The Sole Arbitrator may proceed with the arbitration proceedings, subject to furnishing to the parties the requisite disclosures as required under Section 12 of the Arbitration and Conciliation Act.

12. The Sole Arbitrator shall be entitled to fee in accordance with the IVth Schedule of the Arbitration and Conciliation Act or as may otherwise be agreed to between the parties and the learned Sole Arbitrator.

13. The parties shall share the arbitrator's fee and arbitral cost, equally.

14. All rights and contentions of the parties in relation to the claims/counter claims are kept open, to be decided by the Sole Arbitrator on their merits, in accordance with law.

15. Needless to state, nothing in this order shall be construed as an expression of opinion of this Court on the merits of the controversy. All rights and contentions of the parties in this regard are reserved. Let the copy of the said order be sent to the newly appointed Arbitrator through the electronic mode as well.

16. Accordingly, the instant petition stands disposed of.

PURUSHAINDRA KUMAR KAURAV, J AUGUST 20, 2025 Nc/sph