Full Text
CIVIL APPEAL NO. 2439 OF 2018
(ARISING OUT OF SLP (CIVIL) NO. 29519 OF 2015)
M/S. ELITE ENGINEERING AND
CONSTRUCTION (HYD.) PRIVATE LIMITED
REP. BY ITS MANAGING DIRECTOR .....APPELLANT(S)
PRIVATE LIMITED REP. BY ITS MANAGING
DIRECTOR .....RESPONDENT(S)
JUDGMENT
2) National Highway Authority of India (NHAI) had entered into agreement dated July 19, 2007 (hereinafter referred to as the ‘Concession Agreement’) whereby it had awarded a contract to M/s. T.K. Toll Road Pvt. Ltd. (hereinafter referred to as the ‘Concessionaire’) for undertaking, inter alia, the design, engineering, financing, procurement, construction, operation and Civil Appeal No. 2439 of 2018 (arising out of SLP(C) No. 29519 of 2015) 2018 INSC 192 maintenance of the Project Highway on Build Operate and Transfer (BOT) basis on the National Highway 67 connecting Coimbatore and Nagapattinam. The Concessionaire vide EPC agreement (Engineering, Procurement and Construction Agreement) dated January 31, 2008 awarded the said work on a fixed lump sum turnkey basis to M/s. Utility Energytech and Engineers Private Limited (hereinafter referred to as the ‘EPC Contractor’). EPC Contractor, in turn, executed a Construction Agreement dated March 14, 2008 with the respondent herein (M/s. Techtrans Construction India Pvt. Ltd.) to execute the works as per terms and conditions entailed in that agreement. Clause 8 of that agreement permitted the respondent to sub-contract the structural work. Pursuant thereto, the respondent floated a tender for sub-contracting their work in which the appellant also submitted its bid and was ultimately awarded the said work by the respondent vide agreement dated July 29, 2009.
3) Some disputes arose between the appellant and the respondent in connection with the execution of the said work and the appellant vide its letter dated March 25, 2013 raised certain claims against the respondent. The appellant also filed Original Petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) on the file of Principal Judge, Karur. This petition was contested by the respondent who in its reply denied all the allegations raised by the appellant and also submitted that since there was no arbitration agreement between the parties, the petition under Section 9 of the Act was not maintainable. While this was pending, the appellant moved application under Section 11(3) and (5) of the Act for appointment of an arbitrator in the High Court of Judicature at Madras on January 28, 2014. Notice in this petition was issued by the High Court. In the meantime, on June 30, 2014, the Principal Judge, Karur allowed the petition of the appellant under Section 9 of the Act, but left open the issue of existence of arbitration agreement.
4) Insofar as the appellant’s petition under Section 11 of the Act is concerned, it was contested by the respondent taking the objection to the maintainability of the petition on the ground of absence of any agreement. The High Court has vide impugned orders dated September 18, 2015 dismissed the said petition of the appellant upholding the contention of the respondent that there is no arbitration agreement between the parties and, therefore, remedy under the Act for appointment of arbitrator or constitution of Arbitral Tribunal is not available.
5) It may be clarified at this juncture that Agreement dated July 29, 2009 entered into between the appellant and the respondent does not contain any arbitration clause. There is no independent arbitration agreement between the parties either. However, case set up by the appellant was that this Agreement dated July 29, 2009 entered into between the parties, by implication, incorporates the arbitration agreement that is contained in the Agreement dated March 14, 2008 that was entered into between the EPC Contractor and the respondent.
6) Indubitably, clause 45 of the Agreement dated March 14, 2008 between EPC Contractor and the respondent contains procedure for resolution of disputes and sub-clause (3) thereof refers to arbitration procedure. In case of any dispute, as per clause 45.1, first attempt is for ‘amicable resolution’. Thereafter, under clause 45.2, process of ‘mediation’ is to be resorted to and if that also fails then the ‘arbitration procedure’ is provided. Clause 45.[3] and clause 45.[4] read as under: “45.3.Arbitration Procedure: Subject to the provisions of Article 45.[1] and 45.2, any dispute, which is not resolved by amicable resolution between the parties or by a reference to mediation, shall be finally settled by binding arbitration under the Arbitration and Conciliation Act, 1996. The arbitration shall be by a panel of three arbitrators, one to be appointed by each Party and the third to be appointed by the two arbitrators appointed by the Parties. The Party requiring arbitration shall appoint an arbitrator in writing, inform the other party about such appointment and call upon the other party to appoint its arbitrator. If within 15 days of receipt of such intimation the other party fails to appoint its arbitrator, the Party seeking appointment of arbitrator may take further steps in accordance with Arbitration Act.
45.4. Place of Arbitration: The place of arbitration shall be Mumbai for all Disputes.” 7) According to the appellant, this clause gets incorporated in the Agreement dated July 29, 2009 that was entered into between the respondent and the appellant, by virtue of following clauses in the said agreement: “'2.Subcontractor hereby agrees, undertakes to execute the said value of work, and is responsible for the efficient and successful execution of the work and is to be completed as per the contract period specified in the contract document. a........ b........ All the conditions and special conditions of contract, specifications (general and additional clauses relating to the works and quality specified in the relevant agreement between the Construction Contractor and the Employer are binding on the Subcontractor.” Annexure-I specifying the 'Terms and Conditions' Annexed thereto inter alia provides Clause - 9.10 as under: “9.10. For items which are not mentioned in this Agreement Clauses, terms and conditions of Agreement between Contractor and EPC Concessionaire will be applicable.''
8) It is, thus, argued by the learned counsel for the appellant that as per the aforesaid clause, when the appellant had agreed and undertaken to execute the work as per contract specified in the contract document and the said clause also specifically provided that all the special conditions of the contract, specifications etc. relating to the works and qualities specified in the relevant agreement between the construction contractor and the employer are binding on the respondent, the clause relating to arbitration agreement i.e. 45 entered into between EPC Contractor and the respondent also became applicable by incorporation. It was submitted that the aforesaid clause read with clause 9.10 of Annexure 1 which categorically mentions that in respect of items which are not mentioned in the Agreement clauses, terms and conditions of the Agreement between the Contractor and EPC Concessionaire will be applicable, would also lead to same result.
9) These very arguments were raised before the High Court. The appellant had also referred to certain communications addressed by it to the respondent before invoking legal remedy wherein it has stated that the parties had agreed for settlement of disputes in accordance with clause 45.3. The respondent, on the other hand, had drawn attention of the High Court to paragraph 23 of the petition filed by the appellant under Section 9 of the Act wherein it had categorically stated that the appellant would be constrained to initiate legal proceedings against the respondent for recovery of amount by approaching the competent civil court. The High Court, thus, opined that from the communications only, it could not be said that parties had agreed for arbitration and, in fact, the appellant in his petition filed under Section 9 of the Act had professed ignorance of the agreement between the respondent and the employer. As it had gone to the extent of making an averment to the effect that ‘the petitioner is totally kept in dark about the terms and conditions of the agreement till now’. The High Court thereafter construed clauses 2 and 9.10 of the Agreement that was entered into between the appellant and the respondent and came to the conclusion that those clauses never meant to incorporate arbitration agreement into the Agreement dated July 29, 2009 executed between the parties. On this aspect, discussion goes as follows:
14) After considering the respective submissions, we are inclined to agree with the respondent and, therefore, do not find any fault with the impugned judgment of the High Court.
15) In M.R. Engineers and Contractors Private Limited case, this Court considered the true intent and scope of Section 7 of the Act which deals with ‘arbitration agreement’. Relevant portion of Section 7 reads as under:
16) As per sub-section (5), an arbitration clause contained in an independent document can also be imported and engrafted in the contract between the parties, by reference to such independent document in the contract, even if there is no specific provision for arbitration. However, the Court noted that such a recourse can be adopted only ‘if the reference is such as to make the arbitration clause in such document, a part of the contract.’ This interpretation to sub-section (5) of Section 7 was elaborated in the following manner:
17) After some further discussion on this aspect with reference to the existing case law as well as extracts from Russell on arbitration, the Court summed up the position as under:
18) When we apply the aforesaid ratio, we find that the High Court has correctly held that, in the instant case, it was not intended to make the arbitration clause as a part of the contract between the appellant and the respondent. Clause 2 and clause 9.10 are given correct interpretation by the High Court and discussion in this behalf has already been extracted above. By these clauses, only those conditions and sub-conditions of the contract, specification etc. which relate to the works and quality are incorporated. Clause 9.10 only talks of ‘items’ which are not mentioned in the contract and terms and conditions relating to the execution of those items are to be taken from the main contracts. Reference to clause 8.[7] is also inconsequential. By this clause only, those terms contained in the main agreement which relate to ‘terms of work’ are incorporated. Procedure relating to ‘termination’ is altogether different from resolution of disputes. Dispute may arise even de hors the termination of the contract and is an altogether different aspect, not necessarily connected with the termination of work.
19) In Alimenta S.A. v. National Agricultural Coop. Mktg. Federation of India Ltd.5, the question was as to whether the arbitration clause in Fosfa-20 was incorporated in the first contract by way of clause 11 and in the second contract by virtue of clause 9. The Court held that while the arbitration clause was incorporated in the first contract, the same was not incorporated in the second contract. How the matter has to be looked into, for determining the same, was discussed in the following manner:
“13. … There is a good deal of difference between Clause 9 of this contract and Clause 11 of the first contract. Clause 11 has been couched in general words, but Clause 9 refers to all other terms and conditions for supply. The High Court has taken the view that by Clause 9 the terms and conditions of the first contract which had bearing on the supply of HPS were incorporated into the second contract, and the term about arbitration not being incidental to supply of goods, could not be held to have been lifted as well from the first contract into the second one.
14. It is, however, contended on behalf of the appellant that the High Court was wrong in its view that a term about arbitration is not a term of supply of goods. We do not think that the contention is sound. It has been rightly pointed out by the High Court that the normal incidents of terms and conditions of supply are those which are connected with supply, such as, its mode and process, time factor, inspection and approval, if any, reliability for transit, incidental expenses, etc. We are unable to accept the contention of the appellant that an arbitration clause is a term of supply. There is no proposition of law that when a contract is entered into for supply of goods, the arbitration clause must form part of such a contract. The parties may choose some other method for the purpose of resolving any dispute that may arise between them. But in such a contract the incidents of supply generally form part of the terms and conditions of the contract. The first contract includes the terms and conditions of supply and as Clause 9 refers to these terms and conditions of supply, it is difficult to hold that the arbitration clause is also referred to and, as such, incorporated into the second contract. When the incorporation clause refers to certain particular terms and conditions, only those terms and conditions are incorporated and not the arbitration clause. In the present case, Clause 9 specifically refers to the terms and conditions of supply of the first contract and, accordingly, only those terms and conditions are incorporated into the second contract and not the arbitration clause. The High Court has taken the correct view in respect of the second contract also.” (emphasis supplied)
20) This judgment is noted in M.R. Engineers and Contractors Private Limited case as well and in the facts of M.R. Engineers and Contractors Private Limited, the Court held that there was no incorporation of arbitration clause. Following discussion throws light to decide the issue in this case as well:
21) In view of the aforesaid, the appeal stands dismissed .............................................. J. (A.K. SIKRI) ............................................. J. (ASHOK BHUSHAN) NEW DELHI; FEBRUARY 23, 2018.