Full Text
CIVIL APPEAL NO.11866 OF 2018
(@ SPECIAL LEAVE PETITION (C) NO 17521 OF 2017)
M/S SIMPLEX INFRASTRUCTURE LTD ..APPELLANT
JUDGMENT
1. The present appeal arises from the judgment of a learned Single Judge of the High Court of Calcutta by which the respondent’s application for condoning a delay of 514 days in filing an application under Section 34 of the Arbitration and Conciliation Act, 1996 (‘the 1996 Act’) was allowed.[1]
2. The appellant, who is a contractor, entered into an agreement for the construction of 821 units of permanent shelters in the tsunami-hit Andaman and Nicobar Islands with the Union of India, represented by the Executive Engineer, Andaman Central Division, Central PWD, Port Blair.[2] The scope of
2 The date of the agreement is 5 January 2006 work involved the construction of single storied permanent shelters, including internal water supply, sanitary installation and internal electrification. Due to differences with regard to the performance of the construction work, the parties were referred to arbitration. On 27 October 2014, the arbitrator made an award in favour of the appellant and directed the respondent to pay a sum of ₹9,96,98,355/- with simple interest @ 10% per annum from 1 January 2009 till actual payment. The respondent received the copy of the award on 31 October 2014.
3. Aggrieved by the award, the respondent filed an application[3] under Section 34 of the 1996 Act on 30 January 2015 before the District Judge, Port Blair for setting aside the arbitral award. During the pendency of the arbitration proceedings, the appellant had filed an application[4] under Section 9 of the 1996 Act before the High Court of Calcutta praying for an injunction on encashment of bank guarantee against the respondent and the application was duly contested by the respondent.
4. On 12 February 2016, the District Judge dismissed the respondent’s application under Section 34 of the 1996 Act for want of jurisdiction. The District Judge observed: “…According to the provision of Section 42 of the Arbitration and Conciliation Act, when an application has been made regarding an arbitration agreement before any Court under the same part; that Court shall only have jurisdiction over the arbitration proceedings and all subsequent application arising 3 O.A No.2/2015 4 AP No 91 of 2008 out of that agreement and the arbitral proceedings shall be made in that court and in no other court. In this case the parties have preferred an application under Section 9 of the Arbitration and Conciliation Act before the Hon’ble High Court of Kolkata… Thus, it is clear to me that this Appellant Court has no jurisdiction to entertain this appeal according to Section 42 of the Arbitration and Conciliation Act.”
5. On 28 March 2016, the respondent filed an application[5] under Section 34 before the High Court of Calcutta for challenging the arbitral award dated 27 October 2014, along with an application[6] for condonation of a delay of 514 days. The respondent justified the delay on ground of there being a bona fide mistake in filing the application before the wrong forum and the respondent’s counsel causing delay due to which necessary formalities were not complied with within the prescribed time.
6. On 27 April 2016, the learned Single Judge of the High Court allowed the respondent’s application and condoned the delay of 514 days. The High Court held: “After considering the submissions made by the learned advocate for the applicant/petitioner and upon perusing the application for condonation of delay, it appears that sufficient cause has been shown to explain the delay in filing the application, being AP No. 224 of 2016 and as such the delay is condoned…”
7. The issue which has been raised before this Court is whether the learned Single Judge was justified in condoning a delay of 514 days by the 5 A.P. No. 224/2016 6 G.A. No. 958/2016 in A.P. No. 224/2016 respondent in filing the application under Section 34. In dealing with this issue, this Court needs to assess whether the benefit of Sections 5 and Section 14 of the Limitation Act can be extended to the respondent, and if so, whether a delay beyond the specific statutory limitation prescribed under Section 34(3) of the 1996 Act could be condoned.
8. Section 34 of the Arbitration and Conciliation Act, 1996 provides thus:
Section 34 provides that recourse to a court against an arbitral award may be made only by an application for setting aside such award “in accordance with” sub-section (2) and sub-section (3). Sub-section (2) relates to the grounds for setting aside an award. An application filed beyond the period mentioned in sub-section 3 of Section 34, would not be an application “in accordance with” that sub-section. By virtue of Section 34(3), recourse to the court against an arbitral award cannot be beyond the period prescribed. Sub-section (3) of Section 34, read with the proviso, makes it abundantly clear that the application for setting aside the award on one of the grounds mentioned in sub-section (2) will have to be made within a period of three months from the date on which the party making that application receives the arbitral award. The proviso allows this period to be further extended by another period of thirty days on sufficient cause being shown by the party for filing an application. The intent of the legislature is evinced by the use of the words “but not thereafter” in the proviso. These words make it abundantly clear that as far as the limitation for filing an application for setting aside an arbitral award is concerned, the statutory period prescribed is three months which is extendable by another period of upto thirty days (and no more) subject to the satisfaction of the court that sufficient reasons were provided for the delay.
9. Section 5 of the Limitation Act, 1963 provides thus:
10 Section 14 of the Limitation Act, 1963 provides thus:
11 The respondent submitted an application under Section 34 of the 1996 Act on 30 January 2015 before the District Judge, Port Blair for setting aside the arbitral award dated 27 October 2014. On 12 February 2016, the District Judge dismissed the respondent’s application for want of jurisdiction. It was only on 28 March 2016, that the respondent filed an application under Section 34 of the 1996 Act before the High Court of Calcutta challenging the arbitral award, along with an application for condonation of delay of 514 days.
12 The contention of Mr Aryama Sundaram, learned senior counsel for the appellant is that even if the benefit of Section 14 of the Limitation Act is extended to the respondent in filing the application under Section 34 of the 1996 Act, there would still be a delay of 131 days which could not be condoned in view of the specific statutory limitation prescribed under Section 34(3) of the 1996 Act. The learned senior counsel has tendered the following tabulated chart: DELAY CHART Particulars No. of Days No. of Days
D. TOTAL DELAY 131
The appellant has, in this connection, relied on Union of India v Popular Construction Company (supra) and Consolidated Engineering Enterprises v Principal Secretary, Irrigation Department (supra) to support its case. On the other hand, it is the respondent’s contention that there were no willful latches on its part and the delay was caused due to inevitable administrative difficulties of obtaining directions from higher officials.
13 A plain reading of sub-section (3) along with the proviso to Section 34 of the 1996 Act, shows that the application for setting aside the award on the grounds mentioned in sub-section (2) of Section 34 could be made within three months and the period can only be extended for a further period of thirty days on showing sufficient cause and not thereafter. The use of the words “but not thereafter” in the proviso makes it clear that the extension cannot be beyond thirty days. Even if the benefit of Section 14 of the Limitation Act is given to the respondent, there will still be a delay of 131 days in filing the application. That is beyond the strict timelines prescribed in sub-section (3) read along with the proviso to Section 34 of the 1996 Act. The delay of 131 days cannot be condoned. To do so, as the High Court did, is to breach a clear statutory mandate.
14 The respondent received the arbitral award on 31 October 2014. Exactly ninety days after the receipt of the award, the respondent filed an application under Section 34 of the 1996 Act before the District Judge, Port Blair on 30 January 2015. On 12 February 2016, the District Judge dismissed the application for want of jurisdiction and on 28 March 2016, the respondent filed an application before the High Court under Section 34 of the 1996 Act for setting aside the arbitral award. After the order of dismissal of the application by the District Judge, the respondent took almost 44 days (excluding the date of dismissal of the application by the District Judge and the date of filing of application before the High Court) in filing the application before the High Court. Hence, even if the respondent is given the benefit of the provision of Section 14 of the Limitation Act in respect of the period spent in pursuing the proceedings before the District Judge, Port Blair, the petition under Section 34 was filed much beyond the outer period of ninety days.
15 The respondent has relied on the decision of this Court in Union of India v Tecco Trichy Engineers & Contractors[9], where this Court had to decide the effective date from which the limitation within the meaning of subsection (3) of Section 34 of the Act shall be calculated. The Chief Project Manager on behalf of the Southern Railway had entered into a contract with a contractor for construction of a railway bridge. Disputes between the parties were referred to arbitration and an award was delivered in the office of the General Manager, Southern Railway. The Chief Engineer preferred an application against the award under Section 34 of the 1996 Act before the High Court. The learned Single Judge and the Division Bench of the High Court rejected the application holding it as barred by limitation. This Court reversed the order of the High Court and condoned the application for delay. This Court observed that in huge organisations like the Railways having different divisional heads and various departments within the division, the copy of the award had to be received by the person who had knowledge of the proceedings and who would be the best person to understand and appreciate the award and grounds for challenge. This Court found that all arbitral proceedings for the Railways were being represented by the Chief Engineer and the General Manager had simply referred the matter for arbitration as required under the contract. While condoning the delay of three months and 27 days, this Court found that the service of the arbitral award on the General Manager could not be taken to be sufficient notice to constitute the starting point of limitation for the purpose of Section 34(3) of the 1996 Act. The decision in this case has no applicability to the facts of the present case as there is no dispute with respect to the party who received the arbitral award. It is an admitted position that on 27 October 2014, the arbitrator made an award in favour of the appellant and on 31 October 2014, the Union of India received a copy of the award. One of the reasons stated by the respondent for delay in filing an application under Section 34 of the 1996 Act was that the departmental office was located at Port Blair, Andaman and it was a timeconsuming process for obtaining permission from the circle office at Chennai. Administrative difficulties would not be a valid reason to condone a delay above and beyond the statutory prescribed period under Section 34 of the 1996 Act.
16 Under the circumstances, we are of the considered opinion that in view of the period of limitation prescribed in Section 34(3), the learned Single Judge of the High Court was not justified in condoning the respondent’s delay of 514 days in filing the application. The judgment rendered by the learned Single Judge of the High Court of Calcutta on 27 April 2016, in GA No. 958 of 2016 is set aside and the appeal is allowed. The petition under Section 34 stands dismissed on the ground that it is barred by limitation. There shall be no order as to costs......................................................J [Dr Dhananjaya Y Chandrachud].....................................................J [Vineet Saran] New Delhi; December 05, 2018