$-16 HIGH COURT OF DELHI
O.M.P.(MISC.)(COMM.)145/2019
RENEWABLE ENERGY SYSTEM LTD. Petitioner
Through: Ms.Ankita Bajpai,Advocate.
VERSUS
BHARAT SANCHAR NIGAM LTD. Respondent
Through: Mr.Samdarshi Sanjay,Advocate.
CORAM:
HON'BLE MR.JUSTICE RAJIV SHAKDHER
16.04.2019 I.A. No.5592/2019(Exemption)
ORDER

1. Allowed,subjecttojust exceptions. O.M.P.(MISC.VCOMM.)145/2019

2. Issue notice to the respondent.

3. Learned counsel for the respondent says that he does not wish to file a reply as he does not oppose the prayer made in the petition for extension of time.

4. The record shows that the learned Arbitrator entered upon reference on 23.09.2017.

5. The record also shows that on 30.11.2018,parties mutually agreed for extension of time by further period of six months beyond the statutory period of 12 months provided under the Arbitration and Conciliation Act,

1996. O.M.P.(MISC.)(COMM.)145/2019 page1of[2] 2019:DHC:7657 'U

6. I am told by counsel for the parties that 18 months period came to an end on 25.03.2019.

7. Counsel for the parties inform me that matter is at the stage of evidence.

8. In these circumstances, given the time and money invested by the parties in the Arbitration proceedings, I am inclined to allow the prayer made for extension oftime.

9. Accordingly,further six months are granted for concluding arbitration proceedings and for pronouncementofthe award.

10. The time for this purpose will commence from today i.e. 16.04.2019.

11. Consequently, the time between 25.03.2019 and today shall stand regularised.

12. The petition is disposed ofin the aforesaid terms.

RAJIV SHAKDHER,J. APRIL 16,2019 O.M.P.(MJSC.)(COMM.)145/2019 page2of[2]