Full Text
HIGH COURT OF DELHI
CENTRAL GOVERNMENT EMPLOYEES WELFARE HOUSING ORGANISTION ..... Petitioner
Through: Mr. D. Moitra and Mr. Sanjoy Bhaumik, Advocates.
(M:9971075019)
Through: Mr. Aniruddha Deshmukh and Mr. Nikhil Goel, Advocates.
(M:9971633944)
JUDGMENT
1. The present petition challenges the award dated 14th November, 2012 passed by the Ld. Sole Arbitrator. The Respondent – M/s LABH Construction & Industries Ltd. (hereinafter ‗Contractor‘) was the claimant before the Ld. Arbitrator and the Petitioner - Central Government Employees Welfare Housing Organisation (hereinafter ‗CGEWHO‘) is the employer of the Contractor. The Contractor had made various claims before the Ld. Arbitrator and CGEWHO had made various counter claims. 2019:DHC:2222
2. The background of the present dispute is that a turnkey contract was entered into on 11th July, 2001 between CGEWHO and the Contractor for construction of a housing project at Bopal, Ahmedabad. Relevant dates in respect of the award of the contract are set out hereinbelow:
3. The date of completion of the contract, as envisaged in the contract dated 11th July, 2001 was two years from the date of execution of the contract. However, it is not disputed that the actual completion was much later i.e., in May, 2007. The Contractor raised various claims before the Ld. Arbitrator and CGEWHO raised various counter claims. The Ld. Arbitrator had allowed some of the counterclaims of CGEWHO which were challenged by the contractor in a petition under Section 34, being OMP 354/2015 which was dismissed as being time barred on 21st October, 2016. The challenge to the said judgment was also dismissed by the Supreme Court vide order dated 21st January, 2018. Thus, in respect of the rejected (a) Name of work Turnkey Housing Project at Ahmedabad (b) Acceptance of bid from LCIL and issue of LOI by CGEWHO 27.10.1998
(c) Acceptance of LOI by
(d) Issue of MOU and LOI after finalization of specs and dwelling units between
CGEWHO and CAG 31.08.2000 (e) Date of signing of CA 11.07.2001 (f) Date of completion of Project May 2007 counter claims, the award has attained finality.
4. The findings of the Ld. Arbitrator, on the various claims made by the Contractor are as under:
I. Claim No. 9 – Loss of interest on earnest money: The Ld.
Arbitrator held that the Contractor had no bonafide claim over the interest demanded by it over the earnest money deposit, and accordingly, the claim was rejected.
Holding the claim to superfluous and untenable, the Ld. Arbitrator rejected the claim of the Contractor. M.Claim No. 13 Loss due to deployment of manpower for block making machine: The Ld. Arbitrator held that this claim was linked with Claim No.11 and the arguments also being similar, the claim was rejected.
5. The findings of the Ld. Arbitrator, on the various counter-claims made by the CGEWHO are as under:
Arbitrator, awarded a sum of Rs.1,01,53,823/- in full to CGEWHO. B. Claim No.2 – Loss of Interest on capital by CGEWHO: The factor of interest on this count not being mentioned in the contract, the Ld. Arbitrator rejected the claim of the CGEWHO.
Arbitrator rejected this claim as CGEWHO was held to not be entitled to any relief on this claim on the ground that factum of loss having not been proved by CGEWHO. D. Claim No.4 – Loss due to failure of LCIL to get drawing approved from IIT Mumbai: Ld. Arbitrator held that there was no contractual obligation on the Contractor to pay any amount to the consultant nominated by CGEWHO, and accordingly, rejected the claim.
Ld. Arbitrator held that since the Contractor was not put to proper notice of with respect to claimed loss and additional expenditure for completing the unfinished work, by CGEWHO, nor was the decision to revise the design communicated, this claim was rejected.
I. Claim No.9 – Unintended benefit for change of sewage treatment plant: On various grounds urged by the Contractor in respect of not being put to notice of the decisions taken, failure to justify calculation of the amount due and lump sum cost, the claim of CGEWHO was rejected.
The Ld. Arbitrator held that the arguments and assertions for this claim being the same as Claim No.10, this claim is not validated and is liable to be rejected.
Arbitrator held that the expenditure incurred being on a case of the Contractor with their debtor GTB, the claim of CGEWHO was fully justified and awarded an amount of Rs.74,696/-.
Contractor failed to inform CGEWHO about the existing road and also did not intimate them about the dispute in time, a sum of Rs.65,000/- was awarded to CGEWHO. P. Claim No.16 – Loss due to non-provision of access road: Since method of calculating loss was not as per the contractual stipulations, this claim was rejected.
Since this claim was not substantiated this claim with any detailed analysis of loss to the third parties, this claim of CGEWHO was rejected.
6. The award in favour of CGEWHO in the counter claims came to be challenged by the Contractor in OMP 354/2015, which was dismissed as being time barred on 21st October, 2016. Thereafter, the matter was appealed to the Supreme Court, which vide order dated 21st January, 2018, dismissed it. Submissions by the Petitioner
7. The objections in respect of the following claims have been pressed and argued by Mr. D. Moitra Ld. Counsel for the Petitioner: Claim No.1 – Contractor’s claim for escalation from period of LOI (27.10.1998) to the date of Contract Agreement (11th July, 2001). Claim No.3 – Contractor’s claim for additional payment for increase in cost of power supply and electrification. Claim No.14 – Loss due to rejection of cement blocks.
8. In addition, Mr. Moitra also challenges the non-grant of liquidated damages in favour of CGEWHO, as claimed in counter claim no.3. The non-grant of interest per counterclaim No.20 i.e. pre-award and pendente lite interest is also challenged.
9. The basic submission of Mr. Moitra in respect of Claim No.1, wherein the Contractor had claimed escalation for the period between the Letter of Intent to the date of contract i.e. from 27th October, 1998 to 11th July 2001, is that the contract had a stipulation that escalation would only be payable from the date of the contract and the date of contract would be treated as the base date for grant of any escalation. He relies on clause 9 of the contract (at page 60), and submits that grant of escalation of a sum of Rs.22,78,564/in favour of the Contractor is in the teeth of this clause and thus, the same is not sustainable. Mr. Moitra relies upon the following judgments in support: State of Orissa v. Sudhakar Das, (2000) 3 SCC 27. Rajasthan State Mines and Minerals Ltd. v. Eastern Engineering Enterprises and Anr. (1999) 9 SCC 283
10. He further submits that insofar as liquidated damages are concerned, the Ld. Arbitrator erred in not granting liquidated damages in favour of CGEWHO as the contract had a specific stipulation that if there is slow progress of work, the organization would be entitled to recover liquidated damages as per clause 26.1.[2] and 28.2.0. He further submits that the law permits a genuine pre-estimate of the liquidated damages to be allowed in favour of the employer, so long as the Contractor is in breach and has delayed the performance. Ld. counsel for CGEWHO further submits that the Contractor’s conduct in this case lacks bonafides. In fact, it is submitted that the Contractor had undergone severe financial distress, and CGEWHO had extended enormous help to the Contractor, at its request, by making payment to various third parties including labour and suppliers. Reliance is placed on letter dated 11th March, 2004 (page 298), wherein the Contractor has specifically requested the CGEWHO to make payment to the material suppliers directly, as per its advice. He submits that this clearly established that the Contractor did not execute the project in time and as per the stipulation in the contract, levy of liquidated damages was completely justified. He relies upon the following judgments in support of his case: Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd. 2003 (2) Raj 1 (SC); Construction and Design Services v. DDA (2015) 14 SCC 263;
11. Mr. Moitra further submits that in a turnkey contract, the Contractor is not entitled to be paid anything more than what is stipulated in the contract itself. He vehemently relies upon the definition of `turnkey contracts’ as contained in various well-known commentaries and authorities. He submits that the entire purpose of a turnkey contract would be defeated if amounts, over and above the amount specified in the contract, are awarded in favour of the Contractor. On the issue of turnkey projects, reliance is placed on: Delhi Jal Board v. M/s Kaveri Infrastructure Pvt. Ltd. & Anr. 2014 (2) R.A.J. 286 (Del) (hereinafter, ‗Kaveri Infrastructure‘); P.C. Markanda on Building and Engineering Contracts, 5th Edn., Volume 1, Lexis Nexis.
12. He further submits that the Ld. Arbitrator has also erred in not granting pre-reference and pendente lite interest. He relies upon the judgment in Indian Hume Pipe Company Limited v. State of Rajasthan, (2009) 10 SCC 187 to argue that once the Contractor has been held in breach, interest ought to be allowed by the Ld. Arbitrator. He further submits that, as no reasons have been recorded for refusal of interest, that finding is not sustainable. Submissions on behalf of the Respondent.
13. On the other hand, Mr. Aniruddha Deshmukh, Advocate for the Contractor submits that the escalation in such a case is payable even if there is a negative stipulation in the contract. He vehemently relies upon the judgment of the Supreme Court in K. N. Sathyapalan v. State of Kerala & Anr., (2007) 13 SCC 43 (hereinafter, ‗K.N. Satyapalan‘). It is his submission that the said judgment is authority to the proposition that irrespective of whether the contract has a negative stipulation or does not provide for escalation to be granted, the Ld. Arbitrator’s jurisdiction exists for grant of escalation depending on the facts of each case. He also relies upon National Highways Authority of India v. Elsamex-TWS-SNC-JV, 2015 (1) RAJ 565 (Del), a judgment of the Division Bench of this Court, which followed K. N. Sathyapalan (supra) and held that escalation can be granted despite a negative stipulation in the contract.
14. Insofar as liquidated damages are concerned, Ld. counsel for the Contractor submits that the law on this aspect is well settled in the judgment of the Supreme Court in Kailash Nath Associates v. DDA (2015) 4 SCC 136, which was reiterated by the Supreme Court in Mahanagar Telephone Nigam Ltd. v. Tata Communications Ltd. [Civil Appeal No.1766/2019 decision dated 27th February, 2019] (hereinafter, ‗MTNL‘), that liquidated damages can only be granted if actual loss or damage is shown, even though the quantum may not be shown. Ld. counsel for the Contractor has taken the Court to the specific claim in the claim petition at page 354 to submit that there is no justification, whatsoever, in the said claim petition for claiming liquidated damages. It is a completely arbitrary amount, which has been mentioned in the claim petition and such an arbitrary amount, in the absence of any proof of actual loss or damage having been suffered, is not awardable in favour of the CGEWHO.
15. It is further submitted by ld. counsel for the Contractor that as held in Indian Oil Corporation v. M/s. LLOYDS Steel Industries Ltd. 144 (2007) DLT 659, the stipulated sum in the contract is to be a genuine pre-estimate of losses, and if not it would be considered as a penalty, and would not be liable to be granted in favour of the CGEWHO.
16. The main contention in respect of the grant of escalation to the Contractor is that there was a long-time gap between the issuance of letter of intent and execution of MOU and final contract, which was a factor to which the Contractor did not contribute in any manner. The delay being close to almost three years, escalation would be liable to be awarded. He also relies upon the minutes of meeting dated 17th September, 2001 which is extracted in the award at page 8. According to Ld. Counsel, it was agreed in the said meeting that escalation would be considered by the Governing Council and office of CAG, at an appropriate time after approximately 2/3rd of the work is completed. The Ld. Arbitrator having arrived at the conclusion that 2/3rd work is completed by the Contractor and the said conditions as contained in the minutes are satisfied, has partially allowed the claim of the Contractor. Thus, this finding would not liable to be challenged under a Section 34 petition.
17. He further relies upon the rejection of the counter claim of the employer wherein, repeatedly, the Ld. Arbitrator has held that no loss has been suffered by CGEWHO to support the stand that since no loss has been suffered, even liquidated damages are not liable to be awarded. The scope of challenge under Section 34 of the Act being restricted, the escalation which is granted is not liable to be set aside and the liquidated damages ought not to be granted.
18. Mr. Moitra, in rejoinder, on the other hand, submits that the minutes of meeting are mis-interpreted by the Contractor and the said minutes merely agree to consider the claim of escalation and did not agree to grant the sum. Analysis and Findings
19. The notice inviting tender in the present case was called in July, 1998. The Contractor submitted its bid. The letter of intent was issued on 27th October, 1998. The letter of intent provided all the responsibilities of the Contractor and specified the rates for construction of Type-A, Type-B and Type-C dwelling units and stilts. Payments were to be made in five stages. It was described as a `turnkey project‘. The clause relating to escalation in the Letter of Intent reads as under: “ESCALATION Labour and Material Escalation shall be payable to you as per the Clause No.29.0.0 of the General Conditions of Contract. Cost of Cement and Tor Steel will be absorbed by the organisation. The date of signing of the Contract Agreement will be the base date for application of escalation clause.‖
20. The Letter of Intent was accepted by the Contractor on 3rd November,
1998. Thereafter, a Memorandum of Understanding (hereinafter, ‗MOU‘) was entered into between the parties on 31st August, 2000. It was agreed that some portion of the dwelling units were to be built for the employees of the Comptroller and Auditor General of India (CAG) apart from the employees of the CGEWHO. The total value of the contract as per this MOU was to be approximately Rs.20.59 corers. Finally, a detailed agreement was entered into on 11th July, 2001. The contract was to be a turnkey contract for the full complex with the total value of Rs.137,08,37,330/-. The exact dwelling units, that were to be constructed for the CAG and CGEWHO who were the beneficiaries, were stipulated. The contract provided a definition of turnkey project, which reads as under: “1.a Definition of Turnkey contract It has been agreed and accepted that under a Turnkey Contract, a fully functional complex shall have to be constructed for the Organisation in two parts (CAG Complex and CGEWHO Complex) by the Company on the land provided by the Company upto and including handing over of the complete functional complex to the Organisation, performing defect rectifications during the Defect Liability Period and obtaining completion certificates from local authorities etc. A Memorandum of Understanding has also been signed by the Organisation with the Company as on 31 Aug 2000, which is also a part of this Contract Agreement and is annexed at Annexure-―I‖ 1.b The rates quoted by the Company in its price bid for Alternate-II are as per the Annexure-J. However, as per the requirements of the Organisation and the discussions held with the firm, it has been decided to execute the project in the form of two separate functional complexes and as per the revised specifications, and hence it has therefore been agreed and accepted that the rate for execution of project as per the scope of work mentioned in the succeeding clauses including provisioning of land, complete planning, designing and approval of project plans, development of land and all external services and inclusive of all taxes/levies etc. shall be calculated as per Schedule ‗A‘ below, on per sq. ft. of super built up area (S.B.A.) of dwelling units and stilt area (if provided)‖
21. The escalation clause in the contract also reads as under:
32. A perusal of the above letter shows that the Contractor was in a dire financial position and had made special requests to CGEWHO to make payments on its behalf. The same was acceded to by CGEWHO, which walked the extra mile, to help the contractor and to ensure that the project is not completely derailed. Thus, this is not a case covered by the ratio in K.N. Sathyapalan (supra), where CGEWHO was unable to fulfil its obligations.
33. Moreover, the entire purpose of the turnkey contract is to bind the parties to the initial terms. As held in Kaveri Infrastructure (supra), since the contract is a turnkey project, the payment of amounts not contemplated in the contract is not tenable. For all the above reasons, the grant of escalation is liable to be set aside. Claim No.3 – Additional payment of increase in the cost of power supply and electrification
34. The claim on this count was to the tune of Rs. 115 lakhs. The Contractor’s case was that extra amounts, than what were contemplated in the contract initially, were incurred as expenditure. A total expenditure of Rs.115 lakhs was incurred in view of the payments made to the Gujarat Electricity Board for providing transformers and giving feeders to the complex. An amount of Rs.71,84,460/- was paid on this account by the Contractor. The Ld. Arbitrator, after considering the initial estimates that had been worked out at the time of execution of the contract, held as under: “6.3.4. Consequent to pursuing all arguments and counter arguments and documents provided by both the parties, my findings are as under a) On my query whether detailed estimates were prepared by the claimant or respondent for electrification work during tender stage or DPR stage, it was pointed out in the negative by the Respondent. However, the Claimant produced an approximate cost amounting to Rs. 57,89,168, wherein Rs.15 Lac is kept for payment to the GEB. They pointed out that this amount had actually risen to Rs.71,84,460. b) The Respondent brought out that they are not aware of this estimate and it cannot be linked to the cost given in the CA. Though the cost given in the CA is notional, the actual cost has increased abnormally high. The notional cost given in the CA caters for normal increase/decrease in actual cost and not substantial increase/decrease. I, therefore, find both the parties responsible for not assessing the actual cost of external electrification work based on the prevailing site conditions. An extremely rough/tentative figure has been given in the CA which had no relevance to the site requirements. Though the Claimant has now given that he envisaged Rs.25 Lac out of contract amount of Rs.58 Lac for payment to GEB, I find it only an afterthought and no initial estimate from GEB has been obtained by the Claimant before bidding for this project. I, therefore, regard this as a tentative figure and provide at least 50% of the CA amount i.e. Rs.29 Lac as a cost towards payment to the GEB which could be the bases for total cost of Rs.58 Lac for external electrification work. c) Pursuant to the argument that both parties are equally responsible for wrong bidding and wrong acceptance without applying any Engineering tools for preparation of estimates, the additional amount paid to the GEB shall be equally shared by both the parties. An amount of Rs.21,42,000 i.e. 50% of the extra payment to GEB is payable to the Claimant (LCIL) by the Respondent (CGEWHO).‖
35. The CGEWHO has relied upon the clause 4(g)(ii) and 4(aa), which read as under: “(ii) External electrification should cater for total electric power requirement of all dwelling units, area/street lighting, ancillaries buildings like shopping complex, community centre, etc. and other facilities like lift, water supply, system, sewerage disposal system etc. of the Complex. The total power requirement will be worked out as per specifications and in consultation with the Organisation. The electric power shall be arranged by the Company through the State Electricity Board and the scope shall include:- (aa) All charges to be paid to the State Electricity Board for bringing in HT power lines upto the plot, work of external HT overhead or underground lines by the SEB upto the receiving sub-station within the plot, construction of receiving sub stations, installation of required equipments in the receiving sub station. HT power lines from the receiving sub-station to other distribution step down sub-stations within the plot. LT power lines from sub stations to meter boards of each dwelling unit/building.‖
36. The Ld. Arbitrator has concluded that both the parties committed a mistake at the time of bidding and acceptance. In view thereof, the extra payments ought to be shared equally by both the parties. This being a factual analysis of the Ld. Arbitrator this Court is of the opinion that the same cannot be interfered with. Claim 14 – Losses due to rejection of cement blocks
37. The Ld. Arbitrator has conducted a detailed analysis in respect of this claim. The findings of the Ld. Arbitrator are as under: “6.14. CLAIM N0.14 - LOSS DUE TO REJECTION OF CEMENT BLOCKS 6.14.1. The Claimant (LCIL) has brought out that at the time of finalization of the contract, the cement blocks to be used need to conform to M-20 grade strength. The blocks were to be manufactured by the existing plant with the client. Subsequently, the job mix for manufacture of cement blocks was decided by IIT Mumbai for M-20 grade concrete. The manufacturer could not achieve this strength and as many as 1,30,000 blocks were rejected by the Respondent. The Claimant has claimed a loss of Rs.[4] per block on this account as they said that it was not their fault because it was not possible to achieve a strength of M-20 grade for cement blocks with grade-43 cement being supplied to them by the Respondent. They have claimed that the Respondent was asked a number of times and also their consultants to change the cement to grade-53 but was rejected. The consultant had pointed out faults in the Claimant's quality control. Subsequently, the Respondent changed the consultant to CBRI, Roorkee, thereafter, the strength of cement blocks was reduced to M-15 grade with grade 43 cement. Consequently, there was no rejection thereafter. The Claimant has therefore, claimed a loss of Rs.5.20 Lac on account of this as he had to sell the rejected blocks in the market at a loss of Rs.[4] per block. 6.14.2. The Respondent (CGEWHO), pleaded that the manufacture of cement blocks of M-20 grade was entirely the responsibility of the Claimant. The Respondent was only responsible for the supply of cement of grade-43 as laid down in the contract. The Respondent pointed out that the Claimant was informed a number of times by their consultant (IIT Mumbai) for poor quality control at site as well as poor quality of sand and grit brought by him for manufacture of cement blocks. In some communications of LCIL they have themselves accepted the poor quality of sand and grit. The Respondent argued that they had rejected the blocks as per conditions of the contract and are not responsible for any loss of the Claimant on this ground. The Claimant has also not brought to their notice regarding this aspect during the concurrency of the project. 6.14.3. On request from the Claimant, 3 witnesses were called to know the factual position on the ground. The witnesses deposed on 19.02.2010 during 19th hearing at Ahmedabad, they were
1. Sri. V. A. Shah - who worked as project engineer and manager on behalf of CGEWHO from November 2000 to March 2006.
2. Sri. Amit Bhai Pandya - Worked with LCIL from Oct.2002 to Jan.2006.
3. Sri. K. C. Ghai - working with CGEWHO Oct.2002 The witnesses were duly cross examined by both the parties with regards to their questions and to know the factual positions on the ground. Their statements were duly recorded.
FINDINGS AND AWARD 6.14.4. From the statements, counter statements of both the parties and also after examining the 3 witnesses, I find that the Claimant originally started the manufacture of blocks with M-20 grade mix as designed by IIT - Mumbai. The consultant had in various communications to the Claimant brought out that they have not been able to achieve the desired strength of the blocks due to poor quality control and inferior quality of sand and grit. Subsequently, the Claimant opined that M-20 strength of block cannot be achieved with grade-43 cement introduced by the Respondent, and grade-52 cement would be required. However, a lot of 20,000 blocks was also manufactured using grade-52 cement but these also failed to achieve the desired strength. I, there conclude that quality control and quality of grit and sand being one of the cause of not achieving the M-20 grade strength in field as per the designed job mix of IIT- Mumbai. However, when the new consultant (CBRI- Roorkee) changed the mix to M-15 grade, no blocks were rejected. It appears that the insistence of IIT Mumbai for achieving M-20 grade strength without regard to prevailing ground conditions could be the other cause of rejection of so many blocks. 6.14.5. The Claimant has claimed a loss of Rs.[4] per rejected block but they have not given any cost analysis of the same. In view of above, I conclude that though the respondent were within their contractual rights to reject the low quality blocks, they had allowed too heavy a rejection without considering the change in job mix to M-15 which was practical in prevailing site conditions and was subsequently done on advice of their new consultant (CBRI-Roorkee). I, therefore consider both the parties responsible for waste of materials and labor for manufacture of such huge number of rejected cement blocks and awards 50% of the claim put forwards by the Claimant i.e. Rs.2,60,000 in favor of the Claimant.‖
38. A perusal of the above shows that there was a mismatch between the specifications suggested by IIT, Mumbai and the question as to whether Cement of M-20 grade mix or M-50 grade mix was to be used. The confusion having been created due to the advice given by IIT, Mumbai and thereafter by CBRI, Roorkee the conclusion was that both the parties were responsible for waste of material and labour for manufacturing of large number of rejected cement blocks. Accordingly, 50% of the claim was awarded to the Contractor. The factual position, that M-20 grade strength was initially insisted upon by IIT, Mumbai, which was thereafter changed to M-50 grade by CBRI, Roorkee being not disputed, the award of this amount cannot be faulted with. Counter Claim No.3 by CGEWHO - Levy of penalty in the form of liquidated damages.
39. In support of this claim, the CGEWHO relies upon clause 26.1.[2] of the notice inviting tender, which reads as under: “26.1.[2] However, if the work is progressing distinctly slow without any justification, the Organisation at its sole discretion may allow the work to progress. The RA Payments will be made only to the extent of the cash flow necessary for the physical completion of work and may defer the recovery for compensation for delay under clause 28.2.0. The Organisation reserves the right to enforce the penalty clause to be levied in these cases at any stage of construction including final bill stage.”
40. According to CGEWHO, even if the Contractor is allowed to continue with the work, it has a right to claim compensation/liquidated damages. This is a claim for sum of Rs.1.171 crores. According to CGEWHO, clause 28.2.[7] provides a genuine pre-estimate of the compensation that can be awarded to it in case of delays. The amount claimed is the maximum permitted i.e. 10% of the cost at stages 4 & 5. Clause 28.2.[7] is relevant and extracted hereinbelow: “28.2.[7] Further, the Company shall pay as compensation for delay an amount equal to half (1/2) percent of the cost of stages IV & V of the work including extra items, and escalations if any for every week that the work remains unfinished after the stipulated or extended date of completion subject to maximum of 10% of cost of stage IV & V of the work. This will include the compensation for interim delays being claimed by Organisation in accordance with clause 28.2.[4] above. The Organisation may without prejudice to any other method of recovery, deduct the amount of such compensation from any money in its hands due or which may become due to the Company. The payment or deduction of such compensation shall not, however, relieve the Company from its obligation to complete the works or from any other of its obligations and liabilities under the contract.”
41. Ld. counsel for CGEWHO has vehemently relied upon the judgment in Construction and Design Services (supra) and ONGC v. Saw Pipes (supra). It is his submission that the admitted position is that the Contractor delayed the project beyond reasonable period and though the work was allowed to be completed by the Contractor that did not take away the right of CGEWHO to claim compensation for delay. A perusal of the claim petition shows that the claim simply reads as under: “Claim No.3: Levy of penalty in the form of liquidated damages as stipulated in the contract due to delay in completion of the project by the company Rs.1,06,41,846/-. Liquidated damages as per the conditions of the contract payable by the company work out to Rs.1,06,41,846/-.‖
42. The Ld. Arbitrator has clearly recorded that considering the various extensions given, time was not of the essence of the contract. The Ld. Arbitrator also rejected the contention that the claim was barred by limitation. The findings of the Ld. Arbitrator on this claim are as under: “7.3.4. After examining the statements, counter statements, arguments and documents placed on record, my findings and award to this claim of CGEWHO are as under: a) The claim of the Respondent (LCIL) that the CGEWHO claim is time barred is not borne out due to the fact that the Claimant has given sufficient notices to them as per their letters dated 14.12.2004 and 8.4.2005, which are within the 3 year period of the original date of completion as per contract i.e. 10.07.2003. b) I, accept the argument of the Respondent that time does not remain the essence of this contract as the Claimant (CGEWHO) did not specifically extend the date of completion and allowed the work to continue even amending the contract conditions by paying directly to the Respondent's supplier/labor. c) The contention of the Claimant (CGEWHO) that LD clause 24.2.[7] is to be mechanically applied for imposing on the Respondent is not valid due to: i) The Claimant himself had modified the working clauses of the contract and allowed the work to continue indefinitely in the interest of completion of the project. ii) The court rulings sighted by the Claimant and Respondent clearly laid down that while applying LD clause given in the contract, the Claimant has to justify the "FACTUM" of loss while the quantum of loss is not required to be proved. The Claimant has not been able to place on record any document showing the factum of loss to them in order to apply clause 28.2.[7] of the contract for mechanically calculating liquidity damages to be applied on the Respondent. d) In view of the above, I conclude that the Claimant is not entitled to any relief in account of admitting liquidity damages to be admissible to them and their claim is accordingly rejected.‖
43. The Ld. Arbitrator has correctly concluded that the factum of loss has to be established even in the case of compensation/liquidated damages, which may be claimed. This is in line with the legal position as per the judgments in Kailash Nath (supra) and MTNL (supra). The Supreme Court in MTNL (supra) has recently held as under: