Full Text
HIGH COURT OF DELHI
Date of Decision: 13.08.2019
M/S. INTERNATIONAL DESIGN AND ENGINEERING SOLUTIONS PVT. LTD. ..... Petitioner
Through: Ms.Anne Mathew, Adv.
Through: Mr.S.Ravishankar, Ms.Ruhini Dey, Advs.
JUDGMENT
(25) O.M.P. (COMM) 308/2019
VERSUS
(26) O.M.P. (COMM) 309/2019
VERSUS
VERSUS
(28) O.M.P. (COMM) 311/2019
VERSUS
(29) O.M.P. (COMM) 312/2019
VERSUS
OMP (COMM)Nos.307, 308, 309, 310, 311, 312/2019 Page 3 CORAM: HON'BLE MR.
JUSTICE NAVIN CHAWLA NAVIN CHAWLA, J. (Oral) IA 10778/2019 in OMP(COMM) 307/2019 IA 10787/2019 in OMP(COMM) 308/2019 IA 10790/2019 in OMP(COMM) 309/2019 IA 10793/2019 in OMP(COMM) 310/2019 IA 10796/2019 in OMP(COMM) 311/2019 IA 10799/2019 in OMP(COMM) 312/2019
1. These applications have been filed by the petitioner praying for condonation of 19 days delay in re-filing the present petitions.
2. The petitions challenge the Arbitral Awards dated 22.02.2019 passed by the Sole Arbitrator. The petitions were filed on 22.05.2019, that is, within the period of limitation prescribed in Section 34 (3) of the Arbitration and Conciliation Act, 1996. The applications state that the delay in re-filing the petitions occurred as the defects were notified by the Registry first on 23.05.2019, which were removed and the petitions were OMP (COMM)Nos.307, 308, 309, 310, 311, 312/2019 Page 4 re-filed on 28.05.2019. However, the Registry again notified certain defects on 29.05.2019. Thereafter, due to summer vacation, the petitions could be re-filed only on 01.07.2019. By that time, as delay had occurred in re-filing of the petitions, the Registry insisted on a formal application seeking condonation of this delay. However, as the Director of the petitioner company was travelling to the United Kingdom, he was not available for signing the affidavits in support of the applications. This led to a total delay of 19 days in re-filing of the petitions.
3. I find the above to be a sufficient cause for condoning the delay in re-filing of the petitions. Consequently, the delay is condoned and the applications are allowed. OMP(COMM) 307/2019 OMP(COMM) 308/2019 OMP(COMM) 309/2019 OMP(COMM) 310/2019 OMP(COMM) 311/2019 OMP(COMM) 312/2019
1. These petitions challenge the Arbitral Award(s) dated 22.02.2019 passed by the Sole Arbitrator in relation to the Contracts executed between the parties. As a common OMP (COMM)Nos.307, 308, 309, 310, 311, 312/2019 Page 5 question of law and fact arises in these petitions, they are being disposed of by this common judgment.
2. These petitions have been taken up for final hearing at this stage with the consent by the counsels for the parties.
3. The parties have entered into Structural Engineering Consulting Agreement(s) for various construction projects of the respondent. In terms of these Agreements, the petitioner was to provide services for the purpose of Architectural design, drafting, engineering drawings and other consulting related services to the respondent.
4. Clause 3 of the Agreements provides for ‘non-hire clause’ and is reproduced hereinunder:
5. The petitioner claiming that the respondent has breached Clause 3 of the Agreement, raised a claim for compensation in terms of the said Clause. In defence, the respondent contended that the four employees who had allegedly left the service of the petitioner and joined the service of the respondent had, infact, formed a separate company by the name and style of M/s MGI Infra Pvt. Ltd. and therefore, the respondent could not be said to be in breach of the Agreement.
6. The Arbitrator by the Impugned Award has found that M/s MGI Infra Pvt. Ltd., though may not be a subsidiary company of the respondent, but is an associate of the respondent. I may herein quote the relevant findings of the Arbitrator on this issue:
OMP (COMM)Nos.307, 308, 309, 310, 311, 312/2019 Page 7
7. Having concluded the above, the Arbitrator has rejected the claim of the petitioner holding that the Clause 3 of the Agreement is void and unenforceable against the respondent as if enforced, it would curtail the rights of the employees to go for a better employment. I may again quote from the Arbitral Award as under:
8. The learned counsel for the petitioner places reliance on the judgment of this Court in Wipro Ltd. vs. Beckman Coulter International S.A. 2006 SCC OnLine Del 743, to contend that this finding of the Sole Arbitrator cannot be sustained and is totally contrary to the judgment of this Court.
9. I find merit in the submissions of the learned counsel for the petitioner. In Wipro Ltd. (supra), this Court, considering OMP (COMM)Nos.307, 308, 309, 310, 311, 312/2019 Page 8 clause similar to Clause 3 of the Agreements in question, held that though the employees cannot be restrained from taking employment with the respondent, at the same time, if it is proved that the respondent, in breach of the Agreement, had enticed such employees, the petitioner would be entitled to be compensated by grant of damages. I may quote the ratio of the judgment of this Court as under:
10. Though the learned counsel for the respondent submits that in the facts of the present case the respondent cannot be made liable to pay damages under Clause 3 of the Agreement inasmuch as the employees themselves had formed a new company after tendering their resignation to the petitioner, as this aspect has not been considered by the Arbitrator in the Impugned Award(s) and the petitioner has been non-suited on a preliminary finding of law by the Arbitrator that such Agreement/Clause would be void, the same cannot be considered by this Court. This submission would first have to be considered by the Arbitrator on a scrutiny of evidence led by the parties.
11. In view of the above, the Impugned Award(s) are liable to be set aside, leaving it open to the petitioner to agitate its claims in accordance with law. There shall be no order as to costs.
NAVIN CHAWLA, J AUGUST 13, 2019 RN