Full Text
HIGH COURT OF DELHI
Date of
JUDGMENT
SOM DATT LANDMARK HOTELS AND RECREATIONS PRIVATE LIMITED ..... Petitioner
Through: Mr.Jitender Mehta, Advocate
LIMITED(IRCTC) AND ANR. ..... Respondents
Through: Mr.Nikhil Majithia, standing counsel for IRCTC/R-1.
Mr.Manish K.Bishnoi, Mr.Umang Raj, Mr.Sachin Sharma and
Mr.Anurag Sarda, Advts. for R-2.
HON'BLE MR. JUSTICE ANUP JAIRAM BHAMBHANI G.S. SISTANI, J. (ORAL)
1. With the consent of the parties, the writ petition is set-down for final hearing and disposal.
2. The challenge in this writ petition is to the process followed by respondent no.1, whereby, the petitioner contends the respondents have illegally opened the financial and technical bids simultaneously. In the writ petition following prayers have been made: “(i) To pass any writ petition under article 226 of constitution of India for the issuance of writ of certiorari or any other writ or direction for declaring the process adopted by the IRCTC i.e. illegally and unofficially opening of the financial bids without opening the technical bids of the bidders in the Notice Inviting 2020:DHC:74-DB Tender (NIT) for open e-tenders i.e. Open E-Tender NO. 2019/1RCTC/CATG./DCS/VGT for provision of onboard catering services in Vande Bharat/GATIMAN/Tejas Express Trains in Partial/Complete unbundling model for the Train NO. 22435-36 as illegal, arbitrary, unconstitutional, null and voidab-initio and is liable to be quashed and set aside;
(ii) To pass any writ petition under article 226 of constitution of India for the issuance of writ of mandamus or any other appropriate writ, order or direction thereby directing the respondent to cancel the said tender i.e. Open E-Tender No.2019/IRCTC/CATG./DCS/VGT for provision of onboard catering services in Vande Bharat/GATIMAN/Tejas Express Trains in Partial/Complete unbundling model for the Train NO. 22435-36;
3. In the month of September 2019 Respondent no.1 issued a Notice Inviting Tender for E-Tender no. 2019/IRCTC/CATG./DCS/VGT for provision of onboard catering services in Vande Bharat/GATIMAN/Tejas Express Trains in the Partial/Complete unbundling model. The last date for submission and opening of the bids was 04.10.2019.
4. It is the case of the petitioner that as per Clause 4.0 of the Tender Document, relating to ‘Evaluation of Offer’, the process of evaluation of bids was to be in two stages i.e. the Technical Bid was to be opened first and thereafter, the Financial Bid was to be opened of the persons shortlisted on the basis of their Technical Bids. The complaint of the petitioner is that since as per the terms of the tender, the Technical and Financial Bids were to be opened separately and not together, the entire tendering process stands vitiated and the tender should be recalled and cancelled.
5. Notice was issued in this matter vide order dated 27.11.2019.
6. Learned counsel appearing for respondent No.1 has candidly admitted the inadvertent error in the opening of the technical and financial bids simultaneously. In the reply filed by respondent No.1, the procedure adopted for receiving and opening of bids has been explained in para 3 of the reply, which we reproduce below:
7. The reasons for the inadvertent error of opening both bids together are stated in para 6 of the reply, which is also reproduced below:
8. Mr.Nikhil Majithia, counsel for respondent No.1 has submitted that the committee deliberated upon the inadvertent error and was satisfied that no prejudice has been caused to any of the bidders on account of this error; and accordingly, a decision was taken to go ahead with the tendering process and consider the tender as a single packet bid. Para 8 of the reply is also reproduced below:
9. The original record has also been produced by Mr.Majithia. Relevant extracts of the Minutes of Meeting of the tender committee to shortlist applicants are reproduced below: “In view of above, TC recommends to decide the tender as Single bid as this is most suitable option in present circumstances and recommends to send the bids of successful bidders for forensic audit. Advantages of this option are as follows: • Takes care of legitimate rights of H[1] bidders as there is no fault of bidder in this lapse. Thus prevents litigation in court. • Prevents likely loss to IRCTC. • Avoids cartelization of bidders. • More judicious and transparent process in prevailing circumstances. It may be again noted, being e-Tender no uploaded documents and uploaded financial bids can now be changed.”
10. We have heard learned counsels for the parties and have considered their rival submissions.
11. The petitioner is justified in raising an objection that respondent No.1 did not follow its own tender conditions; but despite the persistent queries raised by the court, the petitioner is unable to show any prejudice caused to it on account of simultaneous opening of the technical and financial bids. We have also examined the explanation given in the reply filed by respondent No.1, which is duly supported by the affidavit of the Joint General Manager of respondent No.1. Even otherwise, it is not disputed that the petitioner was ‘L-3’ and as such would not have been awarded the tender in any case.
12. We may also take note of the fact that since both technical and financial bids were digitally uploaded by the bidders, there was no room for any tampering. Additionally, none of the bids was rejected as being technically unresponsive, which in our view, works to the benefit of all bidders and not to their disadvantage.
13. We therefore find no material infirmity in the tendering process. The law is well settled that the court would be slow in interfering in decisions relating to tender matters; and the scope of judicial review is restricted. It would be useful at this point to refer to the judgement in the case of Afcons Infrastructure Limited v. Nagpur Metro Rail Corporation Limited and Another reported as (2016) 16 SCC 818, wherein the Supreme Court has held as under:
14. xxxx xxxx xxxx xxxx
15. Also, in Silppi Constructions Contractors v. Union of India and Another reported as 2019 SCC OnLine SC 1133, the Supreme Court has held as under:
instrumentalities; the courts should give way to the opinion of the experts unless the decision is totally arbitrary or unreasonable; the court does not sit like a court of appeal over the appropriate authority; the court must realise that the authority floating the tender is the best judge of its requirements and, therefore, the court's interference should be minimal. The authority which floats the contract or tender, and has authored the tender documents is the best judge as to how the documents have to be interpreted. If two interpretations are possible then the interpretation of the author must be accepted. The courts will only interfere to prevent arbitrariness, irrationality, bias, mala fides or perversity. With this approach in mind we shall deal with the present case."
16. In the light of the above discussion, we find no ground to interfere by way of this writ petition. The same is accordingly dismissed. G.S.SISTANI, J ANUP JAIRAM BHAMBHANI, J JANUARY 07, 2020 rb