Full Text
HIGH COURT OF DELHI
Date of Decision: 27th February, 2020
BIBHUTI BHUSHAN MISHRA & ANR. ..... Petitioners
Through: None
Through: Ms. Mini Pushkarna, Standing Counsel-Delhi Urban Shelter Improvement Board with Ms. Swagata Bhuyan, Ms. Khushboo Nahar and ms. Latika Malhotra, Advs. for R-1/DUSIB
Ms. Urvi Kapoor for Mr. Sameer Vashisht, Addl.
Standing Counsel(Civil)-GNCTD
HON'BLE MR. JUSTICE C.HARI SHANKAR O R D E R 27.02.2020
D.N. PATEL, CHIEF JUSTICE (ORAL)
JUDGMENT
1. When the matter is called out, nobody appears for the petitioner.
2. This Public Interest Litigation has been preferred with the following prayers: 2020:DHC:1412-DB “(A) Issue a writ of mandamus or any other writ directing the respondents to ensure that the poor people are provided Community toilet blocks as per the Swachh Bharat Mission in guidelines (SBM (Urban) Component II: Community toilets) in T Huts, H Block, Jhuggi under Metro Bridge, Near Yamuna Bridge, Shashtri Park, New Delhi be constructed within a period of four weeks. (B) Issue a writ of mandamus or any other writ directing tine respondents to ensure immediate installation of mobile public toilets till the time permanent public toilets are constructed.
(C) Issue a writ of mandamus or any other writ directing the respondents to take care of the problem of water logging as currently being faced by the residents.
(D) Pass an order directing the Department of women and child development for the proper arrangement of Aganwadis for hundreds of poor and deprived children. So, that they are able to get basic nutrition. (E) Pass an order directing the Delhi Urban Shelter Improvement Board and Department of women and child development for the proper medication and care to these poor slum dwellers. (F) Pass any such directions or order which this Hon'ble court deems fit and proper in the facts and circumstances of the above mentioned case.”
3. We have heard learned counsel appearing for the respondent nos. 1 and 2 at length who have taken us to their respective counter affidavit filed by them in detail.
4. Learned counsel appearing for the respondent no.1 submits that detailed counter affidavit has been filed. Paragraph nos. 5, 6 and 7 of the counter affidavit of respondent no.1 read as under:
5. In view of the aforesaid submissions, it appears that due to low laying areas near Yamuna Bridge, for which this writ petition has been preferred, development of drainage system is not possible for construction of Community Toilet Blocks. However, learned counsel for the Delhi Urban Shelter Improvement Board (DUSIB) submits that they will explore the possibility of installation of bio digester toilet facilities after receiving the response from Electrical Division in this regard.
6. As far as providing the facilities under the Integrated Child Development Scheme (ICDS) of the respondent no.2 are concerned, paragraphs 3 and 4 of the affidavit of the respondent no.2 read as under:
7. In view of the above, we see no reason to further monitor this case as the respondents are already taking care of the issues raised in this petition.
8. Moreover, respondent no.1/DUSIB is also exploring the possibility of installation of bio digester toilet facilities as construction of Community Toilet Blocks are not possible due to low lying areas in question where development of sewage/drainage system is not possible at all. Similarly respondent no.2 is ready to provide nearby Anganwadi facilities from nearly Anganwadi Centre, i.e. AWC No. 49 to the residents of the area in question.
9. We hope and expect from the respondent no.1 that after getting a response from the Electrical Division, looking to the priority of the works pending with them, bio digester toilet shall be provided at the aforesaid place as early as possible and practicable.
10. With these observations, this writ petition is hereby disposed of.