Full Text
HIGH COURT OF DELHI
JINDAL STEEL & POWER LIMITED ..... Petitioner
Through: Mr.Gopal Jain, Sr Advocate with Ms.Gauri Rasgotra, Mr.Saket Sikri, Mr.Sumit
Attri, Mr.George Varghese, Ms.Nikitha Shenoy and
Mr.Sidharth Sharma, Advocates.
Through: Mr.Tarkeshwar Nath Advocate with Mr.Jeyakumar, Director and
Mr.Akhil Mathur, DGM of respondent No.1.
JUDGMENT
1. The hearing has been conducted through Video Conferencing.
2. This petition is filed under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred as the ‘Act’) with the following reliefs:i) Direct the Respondent No. 1 to release the Performance Bank Guarantees No.2158IGPER003116 for INR 81,94,00,000 and No.2158IGPER003216 for INR 90,000/- respectively both dated March 3, 2016; 2020:DHC:1831 ii) Direct the Respondent No. 1 not to invoke and/or encash the Performance Bank Guarantees No. 2158IGPER003116 for INR 81,94,00,000 and No. 2158IGPER003216 for INR 90,000/- respectively both dated March 3, 2016 till further orders; iii) Restrain the Respondent No.1 from taking any coercive steps against the Petitioner in relation to Performance Bank Guarantees No.2158IGPER003116 for INR 81,94,00,000 and No.2158IGPER003216 for INR 90,000/- respectively both dated March 3, 2016 till further orders; iv) Pass ad-interim order(s) in terms of prayers (i) to (iii) above; v) Direct that the costs of this application/petition be paid by the Respondent No. 1; vi) Pass any other order(s) as this Hon‘ble Court may deem fit and proper in the facts and circumstances of the present case.‖
3. The brief facts as alleged in this petition are:a) on 14.03.2014, the respondent No.1 entered into an Memorandum of Understanding with the Foreign Buyer and thereafter on 24.09.2014 the petitioner No.1 and respondent No.1 entered into an agreement in the nature of back to back contract as per above MOU wherein the petitioner was to supply the steel rails to respondent No.1; b) on 12.10.2014, purchase contract was entered into between respondent No.1 and foreign buyer and on the basis of this MOU Steel Rails were to be supplied by respondent No.1 to foreign buyer; c) on 20.11.2014 an addendum to the agreement (addendum No.1) was executed between the petitioner and respondent No.1. In terms of clause No.17 of the agreement the petitioner had executed a Corporate Guarantee in favour of the respondent No.1 for an amount of Rs.88.40 Crores which was to be enforceable and shall remain in full force for a period of six years in the first instance from the date of the said guarantee; d) on 17.06.2015 clause No.21A of the said Corporate Guarantee was amended by way of addendum e) on 23.06.2015, another addendum to the agreement was executed between the petitioner and respondent No.1 (addendum No.2) by which the petitioner was required to provide Performance Bank Guarantee (PBG) for a total sum of Rs.81,94,90,000/-; f) on 03.03.2016, following two performance bank guarantees were furnished viz i) No.2158IGPER003116 for INR 81,94,00,000; and ii) and No.2158IGPER003216 for INR 90,000/g) on 05.05.2016, the respondent No.2 wrote a letter to respondent No.3 stating interalia that respondent No.2 has no objection in assigning the said PBGs in favour of the foreign buyer and subjecting the same to the Iranian law and jurisdiction of Iran; h) on 26.07.2016, respondent No.1 through the respondent No.3 also issued the PBGs through Parsian bank; i) on 13.08.2016, the petitioner started the production of rails and the final shipment of rails under the agreement was supplied to the Iranian company on 11.11.2017. On 20.11.2017, an inspection certificate in relation to the final shipment was issued; j) on 01.12.2017, the petitioner requested respondent No.1 to release the payment against 12th final shipment at the earliest. On 14.12.2017, the respondent No.1 requested the petitioner to extend validity of the bank guarantees till 11.01.2022; k) on 16.01.2018 the petitioner wrote to respondent No.1 stating the PBGs were issued in terms of the agreement and they were valid for eight months from the date of release of final shipment i.e. only upto 03.06.2018. It was expressly stated in the said letter since the petitioner has already completed the shipment well within the contractual period, the said PBGs be released in terms of the agreement. The petitioner requested for release of the PBGs and the payments due to the petitioner from the respondent No.1; l) on 13.11.2018, respondent No.1 wrote a letter to petitioner stating inter alia that vide letter dated 11.01.2018 the respondent No.1 had requested the foreign buyer for release of its counter PBGs, however, the foreign buyer informed as the custom clearance of rails is in process and hence condition of release of such PBGs by the foreign buyer having not been fulfilled as yet; m) it is alleged though the PBGs were valid only till 8 months after the final shipment but the petitioner extended the validity of their performance till 21.04.2020; n) on 11.07.2018 the counter PBGs of respondent No.1 were released by the foreign buyer. On 16.07.2018, the petitioner wrote to respondent No.1 informing and providing it the clearance received from the Parsian Bank, advising the respondent No.3 to release the PBGs of INR 81.94 Crores issued by it at the request of respondent No.1; o) on 01.08.2018 the petitioner informed respondent No.2 regarding the release of the counter PBG issued by respondent No.1 to the Parsian Bank and even requested the respondent No.2 to take up this matter with the respondent No.3 for release of PBGs; hence this petition with aforesaid prayers.
4. The learned senior counsel for petitioner argues the contract between the petitioner and foreign buyer regarding the supply of steel rails have been fully performed and the work being completed; last shipment having been sent on 11.11.2017. Further, the foreign buyer has issued two certificates; one dated 06.10.2018; and another dated 21.01.2020 qua the satisfactory performance of the rails being in use since the year 2018 and as the work having been satisfactorily executed and there being no dues or claim of the foreign buyer; the contract since having been fully performed to its satisfaction, hence per Clause No.11 of the contract, both the PBGs need to be released in favour of the petitioner.
5. In support of his arguments, the learned senior counsel for the petitioner besides referring to various clauses of the agreement dated 24.09.2014 has also referred to certificates issued by the foreign buyer i.e. Ministry of Roads and Urban Development, Iranian Islamic Republic Railway, Tract and Technical Structures Dep. The certificate dated 21.01.2020, inter alia notes:- This is to certify that JSPL India has produced and supplied 1,49,982MT of Rails to Iranian Islamic Republic Railways. The details of rails supplied are given below: xxx xxxx These rails are used for passenger / mixed traffic carrying railway systems in operation and performance has been found to be satisfactory. and the certificate dated 06.10.2018 issued by abovesaid Department inter alia notes:- This is to certify that JSPL India has produced and supplied 1,49,982MT of Rails to Iranian Islamic Republic Railways. The details of rails supplied are given below: xxx xxx Over 42,000 MT of these Rails have been in use for more than 2 years in passenger / mixed traffic carrying Railway systems in operation and the performance is found to be satisfactory.
6. It was argued as eight months of performance, noted in Clause 11 of the agreement dated 24.09.2014 have since been completed, hence as a matter of right, the PBGs be released to the petitioner.
7. It was also argued any apprehension of respondent No.1 can be safeguarded by way of a Corporate Guarantee already given and also by way of an Indemnity Bond; Undertaking or by any other mode as the Court may deem fit, per Section 9(1)(e) of the Arbitration and Conciliation (Amendment)Act, 2015, which read as under:- ―such other interim measure of protection as may appear to the court to be just and convenient.
8. The petitioner is also inclined to issue the Post Dated Cheques (PDCs) as an alternative for the PBGs and can even undertake in the event of any defect being reported by the foreign buyer, it shall be the sole responsibility of the petitioner to cure such defect and not of the respondent No.1. It is also contended the contract and relationship was between the petitioner and the foreign buyer and that the respondents were only the intermediaries, hence there is no justification in withholding such a huge amount of the petitioner, especially, in this extra ordinary situation with which the country is confronted with and there being huge scarcity of liquidity. The petitioner requires the money to be paid to the workers as their salaries, hence the petition be allowed and the PBGs be directed to be released in favour of the petitioner.
9. Reference was made to Marathon Electric Motors (India) vs North Eastern Electric Power 2011 SCC Online Del 1208 wherein this Court noted:- ―6. There is no dispute about the fact that the law regarding performance guarantee is well-settled in the sense that once the performance guarantee is furnished by a contracting party and the opposite side is fully satisfied regarding performance of the contract, having been successfully executed, the guarantee deserves to be released……………‖
10. Heard.
11. This prayer at this stage, as alleged, must fail because of the following reasons - a) the release of PBGs at this stage would amount to grant of final relief at an interim stage, which cannot be allowed; and b) the petitioner has failed to raise any dispute so as to be referred to arbitration.
12. Admittedly, if the PBGs are allowed to be released in favour petitioner today, it shall be granting of the final relief in the petition under Section 9 of the Act, which would rather make this petition infructuous for the reasons the interim relief has to be in the aid of the final order, but cannot be the final order itself. Secondly, the petition fails to raise any dispute between the parties so as to bring a petition under Section 9 of the Act. Section 9(2) of the Act rather notes as under:- ―9. Interim measures, etc. by Court.— (1)xxx (2) Where, before the commencement of the arbitral proceedings, a Court passes an order for any interim measure of protection under sub-section (1), the arbitral proceedings shall be commenced within a period of ninety days from the date of such order or within such further time as the Court may determine.‖ There is no averment in para No.61 of the petition, disclosing cause of action that the petitioner has any intention to refer the dispute to arbitration. Rather the petitioner itself urges there being no dispute, the contract having been satisfactorily completed, the PBGs need be released.
13. In Sundaram Finance Limited vs. NEPC India Limited (1999) 2 SCC 479 the Court noted:-
In order to give full effect to the words "before or during arbitral proceedings" occurring in Section 9 it would not be necessary that a notice invoking the arbitration clause must be issued to the opposite party before an application under Section 9 can be filed. The issuance of a notice may, in a given case, be sufficient to establish the manifest intention to have the dispute referred to arbitral tribunal, but a situation may so demand that a party may choose to apply under Section 9 for an interim measure even before issuing a notice contemplated by Section 21 of the said Act. If an application is so made the Court will first have to be satisfied that there exists a valid arbitration agreement and the applicant intends to take the dispute to arbitration. Once it is so satisfied the Court will have the jurisdiction to pass orders under Section 9 giving such interim protection as the facts and circumstances warrant. While passing such an order and in order to ensure that effective steps are taken to commence the arbitral proceedings, the Court while exercising jurisdiction under Section 9 can pass conditional order to put the applicant to such terms as it may deem fit with a view to see that effective steps are taken by the applicant for commencing the arbitral proceedings. What is apparent, however, is that the Court is not debarred from dealing with an application under Section 9 merely because no notice has been issued under Section 21 of the 1996 Act."
14. In Minochar vs Deenyar Sheiar Jehani 2015(2) R.A.J.46 (Bombay) the Court noted:-
15. Thus, the above law clarifies an interim relief is an aid to final relief and the applicant must demonstrate its intention to refer the matter to arbitration by raising a dispute before Section 9 petition could be entertained.
16. Further, I may say the record does not show if respondent No.1 had any intention to invoke the PBGs, rather they have been requesting the petitioner to extend the same till the guarantee period is over. The averments made in paragraphs No. FF and GG of the petition though urges for stay against the respondent No.1 qua encashment of PBGs, but the petitioner has not made out any case of irrepairable loss or fraud of any egregious nature. The law relating to the encashment of BGs has been clarified in Himadari Chemical Industries Limited vs Coal Tar Refining Company (2007) 8 SCC 110 which notes as under:- ―14. From the discussions made hereinabove relating to the principles for grant or refusal to grant of injunction to restrain enforcement of a Bank Guarantee or a Letter of Credit, we find that the following principles should be noted in the matter of injunction to restrain the encashment of a Bank Guarantee or a Letter of Credit:-
(i) While dealing with an application for injunction in the course of commercial dealings, and when an unconditional Bank Guarantee or Letter of Credit is given or accepted, the Beneficiary is entitled to realize such a Bank Guarantee or a Letter of Credit in terms thereof irrespective of any pending disputes relating to the terms of the contract.
(ii) The Bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer.
(iii) The Courts should be slow in granting an order of injunction to restrain the realization of a Bank Guarantee or a Letter of Credit.
(iv) Since a Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, the existence of any dispute between the parties to the contract is not a ground for issuing an order of injunction to restrain enforcement of Bank Guarantees or Letters of Credit.
(v) Fraud of an egregious nature which would vitiate the very foundation of such a Bank Guarantee or Letter of Credit and the beneficiary seeks to take advantage of the situation.
(vi) Allowing encashment of an unconditional Bank Guarantee or a
17. Nevertheless, as stated above, and even per submissions of the learned counsel for the respondent No.1, it has no intention to encash the bank guarantees rather those have been extended at least seven times before. I may here refer to a letter dated 09.04.2020 issued by respondent No.1 which notes of earlier letters whereby PBGs were extended at least six times. The respondent No.1 in this letter has sought extension of PBGs till November 2021. Its relevant portion notes:- ―The said Agreement between STC and JSPL was to cover the entire period for supply as well as a further guarantee period of 4 years from the date of bill of lading. As per the supplies effected, the guarantee period, in terms of the contract would expire in November, 2021. As per the terms of the Agreement, JSPL is under obligation to keep STC indemnified during the said guarantee period of 4 years with respect to any manufacturing defect and any claim being made by the foreign buyers of STC with respect to any defects as enumerated in Clause 13 of the said Agreement, which defines the guarantee period.‖
18. Now, coming to the terms and conditions of the PBG dated 03.03.2016, having its validity till 03.06.2018, it inter alia notes:-
2. xxx ….. do hereby undertake to pay the amounts due and payable under this guarantee without any demur, merely on a demand from BENEFICIARY stating that the amount claimed is due by way of loss or damage caused to or breach by the said JSPL or any of the terms and conditions contained in the said Agreement or by reason of the JSPL‘s failure to perform the said Agreement. Any such demand made on BG ISSUING BANK shall be conclusive as regards the amount due and payable by BG ISSUING BANK under this guarantee. However, our liability under this guarantee shall be restricted to an amount not exceeding Rs.81,94,00,000/. 4: WE, BG ISSUING BANK ……… or until the Beneficiary certifies that the terms and conditions of the said Agreement have been fully and properly carried out by the said JSPL and accordingly discharged this guarantee. Unless a demand or claim under this guarantee is made on us in writing on or before the 03.06.2018, we shall be discharged from all liabilities under this guarantee thereafter.‖ para No.4 above is clear to an extent that it could be enforceable at the option of respondent No.1 stated therein. Further, in para No.9 it notes:- ―9. …… Notwithstanding anything contained herein: i) We, BG ISSUING BANK undertakes and agree with the Beneficiary that in case there is occurrence of an event which entitles the Beneficiary a right to raise a demand in terms of associate agreement STL/JSPL/EXPORT/2014-2015/1 dated 24th September 2014 and its amendment on dated 20th November 2014 and June 23, 2015 above, ……..‖ thus, the PBG has to be kept in full force till the conditions in the agreement dated 24.09.2014 are satisfied.
19. Before dwelling further, let us examine various clauses of the Associateship Agreement dated 24.09.2014 executed between the petitioner and respondent No.1. The same are as under:-