Ramesth Construction Pvt. Ltd. v. Eldeco Infrastructure and Properties Ltd

Delhi High Court · 02 Feb 2020 · 2020:DHC:3899
V. Kameswar Rao
OMP(MISC)(COMM)165/2020, LA.6397/2020; OMP(MISC)(COMM)167/2020, LA.6401/2020
2020:DHC:3899
civil appeal_allowed

AI Summary

The Delhi High Court granted a joint petition extending the time for the Arbitral Tribunal to complete arbitration proceedings until December 31, 2020, and allowed procedural exemptions from filing original documents and court fees subject to conditions.

Full Text
Translation output
HIGH COURT OF DELHI
OMP(MISC)(COMM)165/2020,LA.6397/2020
OMP(MISC)(COMM)167/2020,LA.6401/2020
RAMESTH CONSTRUCTION PVT.LTD.
RAMESTH CONSTRUCTION PVT.LTD.
Petitioner
Through: Counsel(appearance notgiven)
VERSUS
ELDECOINFRASTRUCTURE ANDPROPERTIESLTD ELDECOINFRASTRUCTUREPROPERTIES LTD
Respondent
Through: Counsel(appearance notgiven)
CORAM:
HON'BLE MR.JUSTICE V.KAMESWAR RAO
31.07.2020 These matters are being heard through video-conferencing.
I.A.6397/2020 in OMP(MISC¥COMM)165/2020
LA.6401/2020 in OMPIMISCVCOMM)167/2020
These applications have been filed by the petitioner seeking exemption from filing original documents / certified copies / true typed copies ofthe Annexures and courtfee.
For the reasons stated in the applications,the same is allowed and the petitioneris exempted from filing original documents/certified copies/true typed copies ofthe Annexures.
Subject to the applicant / petitioner filing the necessary Court fee
2020:DHC:3899 within 72 hrs from the date of resumption of regular functioning ofme
Court,as mandated interms ofOffice Order dated April04,2020issued by this Court, exemption from filing the requisite court fees is granted.
Applications are disposed of.
OMPfMISOrCOMM)165/2020 OMPnviisofcoMivn 167/2020
These two petitions have been filed by the parties under Section
29(A)(4)ofthe Arbitration and Conciliation Act,1996for extension oftime.
Eventhough the prayer made in the petitions is for grantofextension oftime w.e.f. February 02,2020,learned counsel for the parties state that the period be extendedtill December31,2020.
Noting the submission made by the counsel and these petitions being joint petitions by the parties,the time forthe Arbitral Tribunalto complete the proceedings and render the award is extended till December 31,2020 w.e.f.February 02,2020.
The petitions are disposed of.
JULY31,2020/<3y^ V.KAMESWARRAO,J 2020:DHC:3899