AI Summary

The Delhi High Court granted a twelve-month extension to the Sole Arbitrator to complete arbitration proceedings and render the award under Section 29A of the Arbitration & Conciliation Act, 1996.

Full Text
Translation output
O.M.P.(MISC.) (COMM) 196/2020
HIGH COURT OF DELHI
O.M.P.(MISC) (COMM.) 196/2020 & I.A. 8048/2020
PRAGATI CONSTRUCTION CONSULTANTS..... Petitioner
Through: Mr. Vivekanand, Adv.
VERSUS
UNION OF INDIA THROUGH ITS GENERAL MANAGER..... Respondent
Through: Mr.Jagjit Singh, Sr.Counsel for Railways with Mr.Preet Singh, Adv.
CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR O R D E R (O R A L)
22.09.2020 (Video-Conferencing)
JUDGMENT

1. This is a petition under Section 29A(4) and (6) of the Arbitration & Conciliation Act, 1996, for extension of time, to complete the proceedings and render award in the proceedings pending before the learned Sole Arbitrator. Mr. Jagjit Singh, learned Counsel appearing for the respondent has no objection.

2. Accordingly, as prayed in the petition, the time available with the learned Sole Arbitrator, to complete the proceedings and render award stands extended by a period of twelve months with effect from 18th July, 2020. 2020:DHC:2831 O.M.P.(MISC.) (COMM) 196/2020

3. The petition stands allowed.

C. HARI SHANKAR, J.

SEPTEMBER 22, 2020