Full Text
HIGH COURT OF DELHI
Decided on 21st January, 2021
SAINI ELECTRICAL WORKS ..... Petitioner
Through Mr. Anil Sehrawat, Adv.
Through Mr. Devesh Singh, ASC (Civil) with Ms. Sukriti Ghai and Mr. Manas Bhatnagar, Advs. for
GNCTD
21.01.2021 (Video-Conferencing)
C .HARI SHANKAR, J.
JUDGMENT
1. On the attention of Mr. Sehrawat, learned counsel for the petitioner, being drawn to the fact that the protocol prescribed in Clause 25 of the Agreement between the parties has not been strictly complied with and that, therefore, invocation of Section 11(6) of the Arbitration and Conciliation Act, 1996 at this stage may not be permissible, Mr. Sehrawat seeks leave to withdraw this petition, with liberty to re-approach the Court after following the protocol prescribed in Clause 25 of the Agreement. 2021:DHC:229
2. Leave and liberty is granted as prayed for.
3. The petition is dismissed as withdrawn.
C. HARI SHANKAR, J