The Delhi High Court dismissed a petition seeking to stop alleged unauthorized construction on the ground that a sanctioned plan existed and no illegal construction was apparent on inspection.

Full Text
Translation output
W.P(C) 5108/2021 Page 1
HIGH COURT OF DELHI
JUDGMENT
delivered on: 03.05.2021
W.P.(C) 5108/2021 & CM APPL.15654/2021
SATISH KUMAR ….. Petitioner
versus
COMMISSIONER, SOUTH DELHI MUNICIPAL CORPORATION
AND OTHERS …..Respondents
For the Petitioner: Mr. M.S.Bammi with Mr. Arjun Goel, Advocates.
Advocates who appeared in this case:
For the Respondent: Mr. Sanjeev Sabharwal, Standing Counsel, SDMC/R-1 & 2.
Mr. Kushagra Pandey, Panel Counsel (Civil), GNCTD, R-3/SHO, P.S.Hari Nagar.
CORAM:-
HON’BLE MR. JUSTICE SANJEEV SACHDEVA
JUDGMENT

1. The hearing was conducted through video conferencing.

SANJEEV SACHDEVA, J. (ORAL)

2. Petitioner seeks a direction to respondent Corporation as well as the SHO, Police Station Hari Nagar to stop respondent No.4 from continuing with the illegal and unauthorised construction in property bearing No.WZ-VB-137, Gali No.6, Virender Nagar, New Delhi. Further direction is sought to respondent Nos.[1] & 2 to demolish the unauthorised construction and respondent No.3 to provide assistance in demolition of the construction. 2021:DHC:1491 W.P(C) 5108/2021 Page 2

3. Learned counsel appearing for respondent Nos.[1] & 2 – Corporation vehemently opposes the issuance of notice. He submits that the petition has been filed without verifying true facts and by making false allegations. He submits that construction plan has been sanctioned under the saral scheme.

4. It is submitted that in the present time of pandemic subject petition has been filed alleging illegal unauthorised construction and the officers of the respondent Corporation have had to verify the factual matrix of the matter.

5. He submits that since there is a sanctioned plan, no action can be taken against the subject property at this stage. It is only after completion of the construction, when completion certificate is applied that the Corporation officers are obliged to inspect the property and to verify the construction, unless illegal unauthorised construction is apparent on the face of it.

6. Learned counsel submits that on inspection of the property there was no illegal unauthorised construction apparent on the face of it. He submits that action in accordance with law would be taken at the appropriate stage, if required.

7. The statement is taken on record.

8. In view of the fact that subject petition has been filed without verification of correct facts and by alleging that there is no sanction plan, when there is one, I deem it expedient to dismiss the petition by W.P(C) 5108/2021 Page 3 imposing cost of Rs.5000/- on the petitioner.

9. The petition is accordingly dismissed, with costs of Rs. 5,000/-.