AYG REALITY PRIVATE LIMITED v. NBCC(INDIA) LIMITED AND ANR.

Delhi High Court · 02 Sep 2021 · 2021:DHC:2720
C. Hari Shankar
IA12354/2019 in CS(COMM) 1005/2018
2021:DHC:2720
civil appeal_allowed Significant

AI Summary

The Delhi High Court held that the defects liability period in a construction contract is fixed at twelve months per building from taking over, and the contractor is entitled to release of bank guarantees and security deposits upon expiry of this period and submission of final bills, overruling NBCC's attempts to withhold payments and guarantees beyond the DLP.

Full Text
Translation output
IA12354/2019 in CS(COMM) 1005/2018
HIGH COURT OF DELHI
Reserved on: 13th August, 2020 Pronounced on: 2nd September, 2021
I.A.12354/2019 in CS(COMM)1005/2018
AYG REALITY PRIVATE LIMITED ..... Plaintiff
Through: Mr. Jayant K. Mehta, Senior Adv, Mr. Aman Verma and Mr. Anjuman Tripathy, Advs.
VERSUS
NBCC(INDIA) LIMITED AND ANR. ....Defendants
Through: Mr. Rajinder Wali, Advocate with Mr. Ashish Rana, Adv. for
D-1
CORAM:
HON'BLE MR. JUSTICE C. HARI SHANKAR O R D E R
(Video-Conferencing)
IA 12354/2019 in CS(COMM)1005/2018
JUDGMENT

1. This order disposes of IA 12354/2019, preferred under Order XXXIX Rules 1 and 2 of the Code of Civil Procedure, 1908 (“the CPC”), whereby the plaintiff has sought interim relief. Facts

2. Defendant No. 1 (hereinafter referred to as “NBCC”) invited tenders, for construction of infrastructure at the Subsidiary Training 2021:DHC:2720 Centre for the Border Security Force (BSF) at Chakur, District Latur, Maharashtra. The plaintiff applied, and was awarded the tender, for a total contract value of ₹ 30,06,15,853/–. The project involved for separate “Packages” of work, designated as Package I-A, I-B, II-A and II-B. A tabular representation thereof may be provided thus: Package No. Date of Letter of Acceptance (LOA) Value (₹) Nature of work I-A 16th January, 7,44,27,503/- Construction of the Training A Building, Training B Building, SOS Mess Building and GOS Mess Building I-B 10th January, 7,60,08,843/- Construction of MI Hospital Building, Shopping Complex, Family Welfare Centre and Barracks 2. II-A 10th January, 9,25,19,742/- Construction of Parade Ground, Stadium and Swimming Pool (Swimming Pool was later withdrawn) II-B 10th January, 5,76,59,806/- Construction of Barracks 3, 4, 5 and 6 (Barracks 5 was later The work was required to be completed within Nine months.

3. The plaintiff predicates its case on Clauses 9, 10, 37.[1] and 74 of the General Conditions of Contract (GCC), which governed the contractual relationship between the plaintiff and NBCC. NBCC relies, for its part, on Clauses 37.1, 37.[3] and 67.0 of the GCC. These Clauses read thus: “9.0 PERFORMANCE GUARANTEE Within 10 days (ten) from the date of issue of letter of award or within such extended time as may be granted by NBCC in writing, the contractor shall submit to NBCC a performance bank guarantee in the form appended, from any Nationalized bank, equivalent to 5% (five percent only) of the contract value for the due and proper execution of the contract. This bank guarantee shall remain valid up to 90 (ninety) days after the end of defects liability period. In case the contractor fails to submit the performance guarantee of the requisite amount within the stipulated period or extended period, letter of intent will stand withdrawn and EMD of contractor shall be forfeited.”

10.0 SECURITY DEPOSIT/RETENTION MONEY The security deposit or the retention money shall be deducted from each running bill of the contractor at 5% (five percent only) of the gross value of the Running Account will. The Earnest Money Deposited by the tenderer in the form of D.D. only will be treated as part of the security deposit. The lumpsum (consolidated) EMD amount deposited by the Contractor at the time of registration with NBCC shall not be adjusted for security deposit. The security deposit or retention money shall be refunded to the contractor after expiry of defects liability period (referred to in Clause No. 74) or on payment of the amount of the final bill whichever is later. If the amount of Security Deposit deduction in cash is more than Rs. 10 lakhs (Rupees Ten Lakhs only), the excess amount can be refunded to contractor against submission of Bank Guarantee of equivalent amount from a Nationalized Bank in the prescribed proforma of NBCC.” “37.0 PAYMENTS 37.[1] The bill shall be submitted by contract are each month on or before the date fixed by the Engineer-in-Charge for all works executed in previous months. The contractor shall prepare computerized bills using the program as approved by Engineer-in-Charge as per the prescribed format/pro forma. The Contractor shall submit five numbers of hard copies and one soft copy of floppy/CD for all bills. Subject to clause 37.[3] herein below, the payment due to the contractor shall be made within fifteen days of getting the measurements verified from the Engineer-in-Charge on his subordinate/representative and certification of bill by the Engineer-in-Charge. ***** 37.[3] It is clearly agreed and understood by the Contractor that notwithstanding anything to the contrary that may be stated in the agreement between NBCC and the contractor, the contractor shall become entitled to payment only after NBCC has received the corresponding payment(s) from the client/Owner for the work done by the contractor. Any delay in the release of payment by the client/Owner to NBCC leading to a delay in the release the corresponding payment by NBCC to the contractor shall not entitle the contractor to any compensation/interest from NBCC.” “67.0

SET-OFF OF CONTRACTORS LIABILITIES NBCC shall have the right to deduct or set off the expenses incurred or likely to be incurred by it in rectifying the defects and/or any claim under this agreement against the Contractor from any or against any amount payable to the contractor under this agreement including security deposit and proceeds of performance guarantee.” “74.0

DEFECTS LIABILITY PERIOD The contractor shall be responsible for the rectification of defects in the works for a period of 12 months from the date of taking over of the works by the Owner/Client. Any defects discovered and brought to the notice of the contractor forthwith shall be attended to and rectified by him at his own cost and expense. In case the contractor fails to carry out these rectifications, the same may without prejudice to any other right or remedy available, be got rectified by NBCC at the cost and expense of the contractor.” (Emphasis supplied throughout)

4. The following features are plain, from a reading of the aforeextracted Clauses:

(i) The responsibility of the plaintiff, for rectification of defects, extended only till the expiry of Twelve months from the date of taking over of the works by the “Owner/Client”. “Works” and “Owner/Client” are defined, in sub- clauses (b) and (l) of Clause 1.[4] of the GCC, as under: “(b) WORKS OR WORK The expression works or work shall unless there is something either in the subject or context repugnant to such construction, be construed and taken to mean the works by or by virtue of the contract contracted to be executed whether temporary or permanent, and whether original, altered, substituted or additional.” “(l) OWNER/CLIENT means the Government, Organisation, Ministry, Department, Society, Cooperative etc. who has awarded the work/Project to NBCC and/or appointed NBCC as Implementing/Executing Agency/Project Manager and/or for whom NBCC is acting as an agent and on whose behalf NBCC is entering into the contract and getting the work executed.” The period of Twelve months, for reckoning the Defects Liability Period (“DLP”, in short) has, therefore, to be computed from the date of taking over of the works by the Border Security Force (BSF), who awarded the work to NBCC. Clearly, the existence of defects in the work, or their rectification/curing, by the plaintiff, is not relevant, for assessing the DLP. The DLP extends only till the expiry of Twelve months from the date of taking over of the work by the BSF. Clause 74.0 requires NBCC to communicate, to the plaintiff, defects in the work, if any, within the said period of Twelve months. The liability of the plaintiff to rectify the defects extends only to that effect which are so brought to his notice within the said period of Twelve months. The plaintiff has no liability in respect of any defects in the work, to which its notice is invited after the expiry of Twelve months from the taking over of the work by the BSF. At the same time, intimation, to the plaintiff, of the existence of defects, and their rectification, by the plaintiff, thereof, had no effect on the operation of Clause 74.0, insofar as the Twelve months’ terminus ad quem of the DLP is concerned. Any which way, on the expiry of Twelve months from the date of taking over of the work by the BSF, the DLP comes to an end.

(ii) The expression “works”, as employed in Clause 74.0, is also of no little significance. The submission of Mr. Mehta is that Clause 74.0 is to apply on a building-wise basis, and not on a Package-wise basis, whereas Mr. Wali would contend, per contra, that Clause 74.0 is to be reckoned for each Package, and not for each building. Mr. Mehta has, in this context, placed reliance on a communication, dated 23rd April, 2018, from NBCC to the plaintiff, which sets out the “actual DLP status”, as per the NBCC, building-wise. It is also asserted, in the said communication, inter alia, that “the DLP of SOS Mess completed but as on date you have not installed the solar water heating at SOS building.” The letter contains separate tabular representations, for each Package, on a building-wise basis, explaining why, according to NBCC, the DLP, for the said building, was as yet not concluded. This communication, in my view, prima facie supports the submission of Mr. Mehta that the DLP was required to be computed on a building-wise, rather than a Package-wise, basis. Clauses in contracts, which admit of ambiguity, or suffer from any want of clarity, may be interpreted in the light of the manner in which the clauses are understood by the parties to the contract, as manifested by their actions, as held in Godhra Electricity Co. v. State of Gujarat[1] and Mukul Sharma v. Orion India Pvt Ltd[2].

(iii) The buildings under the Four Packages were handed/taken over to the BSF, as follows: Package Buildings Actual Date of Handing over Package I-A Training A 01.11.2014 Training B 03.12.2013 SOS 16.11.2016 GOS 19.05.2018 Package I-B MI Hospital 05.08.2014 Shopping Complex 16.11.2016 Family WelfareCentre 26.05.2015 Barrack 2 30.03.2019 Package II-B Barrack 3 30.04.2013 Barrack 4 09.09.2017 Barrack 6 19.06.2017

(iv) The expiry of the DLP does not, however, unfortunately, crystallise any right, in favour of the plaintiff, to the reliefs sought in this application. The plaintiff’s essential claim is to refund of the Security Deposit and return of the One remaining PBG and the SBGs. These are governed by Clauses 9 and 10 of the GCC.

(v) Clause 9.0 requires the petitioner to submit to NBCC, within Ten days of issuance of letter of award of the contract (subject to extension by NBCC), PBG, equivalent to 5% of the total contract value, and further requires the PBG to remain valid till the expiry of Ninety days after the DLP ends. As the PBG, in respect of Package II-A continued to remain alive till it was invoked by NBCC on 30th June, 2018, Clause 9 does not call for application.

(vi) Clause 10.0 specifically envisages refund, of the security deposit, by NBCC to the plaintiff. This, however, is to take place after expiry of the DLP, or on payment of the Final Bill raised by the plaintiff, whichever is later.

(vii) Clause 10.0 has to be read in juxtaposition with Clauses

37.[1] and 37.[3] of the GCC. Clause 37.[1] is made subject to Clause 37.[3] and, to counterbalance, Clause 37.[3] incorporates a non obstante covenant; accordingly it has pre-eminence over all other Clauses in the agreement between the plaintiff and NBCC.

77,486 characters total

(viii) Clause 37.[1] requires payment, due to the plaintiff, to be made by NBCC within Fifteen days of getting the measurements verified from the Engineer-in-Charge or his representative, and certification of the bill by the Engineer-in- Charge. Clause 37.[3] records the agreement and understanding, of the plaintiff, that the plaintiff would be entitled to payment only after NBCC received the corresponding payment from BSF for the concerned work.

(ix) In order to claim entitlement to payment against any bill, therefore, the plaintiff has, contractually, to establish that (a) the measurements have been verified by the Engineer-in-Charge or his subordinate/representative, (b) the bill has been certified by the Engineer-in-Charge and (c) NBCC has received payment of the amount, covered by the bill, from BSF.

(x) The result is that the contractor cannot, merely by virtue of the DLP having expired, or come to an end, seek the return of the SBGs furnished by it.

(xi) The PBGs were to remain alive till the expiry of Ninety days from the end of the DLP. Once the DLP had expired, on a building-wise basis, then, in respect of those buildings which had been taken over by the BSF, Clause 9.0 requires the life of the PBG, to that extent, to continue only for a period of Ninety more days.

5. For the purposes of the present application, and the present order, it is not necessary to enter, in detail, into the allegations and counter allegations in the suit. A brief reference is, however, necessary. The contract was awarded, by NBCC to the plaintiff, in Four Packages – Package I-A, Package I-B, Package II-A and Package II-B. Each Package was covered by a separate Letter of Acceptance (LOA). The LOA, covering Packages I-B, II-A and II-B, were issued on 10th January, 2012, whereas the LOA covering Package I-A was dated 16th January, 2012. Each Package required the plaintiff to construct the buildings/structures covered thereby. This may be presented, in a tabular fashion, thus: Package Date of LOA Value of Package (₹) Buildings covered by Package I-A 16th January, 7,44,27,503/– (1) Training A Building (2) Training B Building (3) SOS Mess Building (4) GOS Mess Building I-B 10th January, 7,60,08,843/– (1) MI Hospital Building (2) Shopping Complex (3) Family Welfare Centre (4) Barrack No. 2 II-A 10th January, 9,25,19,742/– (1) Parade Ground (2) Stadium (3) Swimming Pool (later withdrawn) II-B 10th January, 5,76,59,806/– (1) Barrack No. 3 (2) Barrack No. 4 (3) Barrack No. 5 (later (4) Barrack No. 6

6. As required by the General Conditions of Contract (GCC), applicable to the contract between the plaintiff and NBCC, the following Performance Bank Guarantees (PBGs) and Bank Guarantees towards Security Deposit (SBGs) were furnished by the plaintiff to NBCC, towards Packages I-A, I-B and II-B (the present application does not concern Package II-A): Package B/G No. PBG/SBG B/G Amount (₹) I-A 00061PEBG12000[4] PBG 37,21,400/– 00061PEBG150019 SBG 5,85,927/– 00061PEBG140027 SBG 11,42,000/– 00061PEBG170012 SBG 6,97,000/– I-B 00061PEBG12000[2] PBG 38,00,500/– 00061PEBG150018 SBG 8,67,910/– 00061PEBG140028 SBG 8,42,000/– 00061PEBG170013 SBG 3,91,000/– II-B 00061PEBG12000[3] PBG 28,83,000/– 00061PEBG150020 SBG 10,15,808/– 00061PEBG140030 SBG 19,90,000/– 00061PEBG170015 SBG 4,54,000/–

7. Though, by the time of filing of the present suit, and even at this stage of amendment thereof, some of the Bank Guarantees had been invoked and encashed by NBCC (in respect to Package II-A). The amounts covered by the PBGs issued in respect of Packages I-A (₹ 37,21,400/–) and II-B (₹ 28,83,000/–) were, subsequently, released to the plaintiff on 7th July, 2020. The prayers in the plaint seek return, by NBCC, of the amounts covered by the Bank Guarantees invoked by it, as well as of the Security Deposit furnished by the plaintiff and a restraint against NBCC from invoking any further Bank Guarantees, and the direction, to NBCC, to return all the Bank Guarantees to the plaintiff. The prayer clause in the present IA, preferred under Order XXXIX Rules 1 and 2 of the CPC, reads as under: “In the aforesaid circumstances, the Plaintiff most respectfully prays that:

(i) This Hon’ble Court may be pleased to order and direct the Defendant No. 1 to finalize the final bills raised by the Plaintiff with respect to ‘Package I-A’, ‘Package I-B’ and ‘Package II-B’ vide letters dated 24.07.2019, 26.04.2019 and 10.08.2018 respectively in a specific time frame.

(ii) This Hon’ble Court may be pleased to order and direct the Defendant No.1 to return, release and hand over to the Plaintiff all the 12 (twelve) Bank Guarantees with immediate effect, details of which are as herein below (tabular statement of the Bank Guarantees);

(iii) Alternatively, order and direct the Defendant

No.1 to return, release and hand over to the Plaintiff the 08 (eight) Bank Guarantees with immediate effect with respect to the Bank Guarantees of ‘Package I-A’ and ‘Package II-B’ and to refund/return proportionate Bank Guarantees qua ‘Package I-B’ since the defects liability period of 3 out of the 4 buildings in the said package are over and one building is ready for possession.

(iv) This Hon’ble Court may be pleased to order and direct the Defendant No.1 to return, release, refund and/or pay over the security deposit of an amount of ₹ 65,00,000/- (Rupees Sixty Five Lakhs only) lying with it in cash, back to the Plaintiff without any claim or demand thereunder on any count, whatsoever;

(v) This Hon’ble Court may be pleased to order and direct the Defendant no.1 to return, release, refund and/or pay over to the Plaintiff all the pending deposits and amounts etc. under the Project Contract lying with it and by whatever name called and in whichever form whether lying with the Defendant No.1 or any other person;

(vi) This Hon’ble Court may be pleased to permit the Plaintiff to remove its construction material, tools and equipment lying on the project site;

(vii) Ad-interim reliefs in terms of prayer clause (i)

(viii) Any other such reliefs as this Hon’ble Court may deem fit and proper in the facts and circumstances of the case.”

8. According to the plaint, owing to unavoidable circumstances – for a large part of which the plaintiff blames NBCC – the plaintiff was unable to meet the milestones fixed by NBCC, from time to time. As a result, various communications were addressed, by the plaintiff to NBCC, inter alia on 26th September, 2012, 6th June, 2013, 9th April, 2015, 10th June, 2015, 5th September, 2017, 24th January, 2018, 1st February, 2018, 15th February, 2018, 19th April, 2018, 12th May, 2018 and 26th June, 2018. Ultimately, NBCC granted the plaintiff Nine months extension for completing the project which, according to the plaintiff, was unreasonable.

9. The plaint also alleges that there was continuous default, on the part of NBCC, in making prompt payment of the bills raised by the plaintiff and that, in certain cases, payment was delayed by as long as a year. When payment was made, it is alleged that arbitrary deductions were effected from the bills, by NBCC suo motu. This, it is alleged, violated Clause 37.[1] of the GCC, which required payments, against bills raised by the plaintiff, to be cleared within Fifteen days from certification by the Engineer-in-Charge of NBCC. The plaintiff alleges that, in violation of this covenant, NBCC, citing frivolous administrative and technical reasons, failed to clear the plaintiff’s bills in time, and repeatedly sought accommodation, pleading scarcity of funds. This, it is submitted, resulted in unnecessary financial burden on the plaintiff, which also adversely affected progress of the work on the Project. It is also asserted, in the plaint, that meetings were held, between the plaintiff and NBCC on 5th July, 2013 and 16th July, 2013, which were duly minuted, and in which NBCC undertook to conduct joint measurement of the work done by the plaintiff and release the payment within Seven days, as well as to provide maximum assistance to the plaintiff, to complete the Project within time. Even so, it is alleged that, from January to December, 2015, the plaintiff’s payments were not released in time owing to financial difficulties being faced by NBCC. Reliance has been placed, in this regard, on letters dated 9th April, 2015, 1st June, 2015, 9th June, 2015, 10th June, 2015, 11th June, 2015, 2nd July, 2015, 28th August, 2015, 8th October, 2015 and 16th December, 2015, from the plaintiff to NBCC. It was only in early 2016 that, consequent to assurances extended by NBCC, the plaintiff agreed to restart the work. This, it is submitted, was reduced, by the plaintiff, in writing, vide letter dated 16th December, 2015 addressed to NBCC.

10. All these facts, though undoubtedly interesting and informative, do not really advance adjudication of the present application. Prayer (i) in the application refers to letters dated 24th July, 2019, 26th April, 2019 and 10th August, 2018, whereunder final bills, in respect of Packages I-A, I-B and II-B, were raised by the plaintiff. It would be relevant, therefore, to refer to the said communications, and what happened to them, as the plaintiff seeks interlocutory directions to NBCC to finalise the said final bills. For this purpose, a chronological excursion through the communications between the parties, howsoever tedious, is essential.

11. Communications between NBCC and plaintiff: 11.[1] The original time stipulated, for completion of work under the contract, expired on 9th October, 2012. 11.[2] On 5th March, 2013 and 7th May, 2013, NBCC wrote to the plaintiff, requiring it to rectify the defects in Barrack 3 (Package II- B). Thirteen civil works and Nine electrical works, requiring to be done, were enumerated. 11.[3] On 25th April, 2013, NBCC wrote to the plaintiff, drawing its attention to Seventeen works remaining to be done in Training Building-B (Package I-A) and pointing out that the Building was scheduled to be inaugurated by the Home Minister on 11th May,

2013. As such, the plaintiff was directed to complete the work on war footing basis. 11.[4] The plaintiff’s assertion that Barrack 3 (Package II-B) was completed and handed over in September 2012 and that Training Building B was completed on 31st March, 2013, was denied, by NBCC, in its letter dated 31st May, 2013, to the plaintiff. The letter again highlighted the defects in Barrack 3. It was further stated, in the said communication, that, in exercising its right under Clause 72.[1] of the GCC, NBCC had withheld amounts, liable to be recovered from the plaintiff in respect of the works related to Package II-B, as the contract was scheduled to expire on 30th April, 2013, and no completion program had been received from the plaintiff. The letter also referred to defects in Barracks 4, 5 and 6 (Package II-B). It was further alleged that the Family Welfare Centre (Package I-B), the SOS Mess (Package I-A), GOS Mess (Package I- A), MI Hospital (Package I-B) and Shopping Complex (Package I-B) were not complete. Defects, pointed out in respect of Barrack 3, it was reiterated, were yet to be addressed and that the BSF Board had declined to take over the said Building, for that reason. In the circumstances, the plaintiff was directed to show cause as to why sub clauses (ii) to (iv) of Clause 72.[2] of the GCC be not invoked by NBCC. 11.[5] On 6th June, 2013, the plaintiff responded to the aforesaid Show Cause Notice dated 31st May, 2013. Apropos Barrack 3, it was asserted that the building was complete and in occupation by the BSF since September 2012. It was further pointed out that the Building had been inaugurated by the IG, BSF, on 16th January, 2013. The DLP, in respect of Barrack 3, therefore, it was submitted, had commenced in September, 2012. In a somewhat contradictory vein, however, the same communication went on to state that the plaintiff would hand over, to NBCC, Barrack 3 (Package II-B), Training Building-B (Package I-A), Training Building-A (Package I-A), the MI Building (Package I-B) and the Family Welfare Centre (Package I-B) within 4 months, and would complete the RCC work in Barrack- 6 (Package II-B), the SOS Mess (Package I-A), GOS Mess (Package I-A), Barrack-2 (Package I-B) and Barrack-4 (Package II-B) within 4 months, and in the Shopping Centre (Package II-A) and Barrack-5 (Package II-B) within 8 to 10 months. 11.[6] On 6th June, 2013, NBCC wrote to the plaintiff, reiterating its request for completion of Training Building-B (Package I-A). The letter alleged that the plaintiff had not yet completed the first floor of the said Building, but that the Building was inaugurated as per programme on 2nd June, 2013. NBCC further stated that it had taken the initiative to formally hand over the building to the BSF, but that, in order to initiate the proceedings, incomplete work was required to be first completed. Fifteen items of work, requiring attention, were enumerated in the letter. 11.[7] The plaintiff was once again requested by NBCC, vide letter dated 2nd July, 2013, to immediately rectify the defects which remained in Barrack-3 (Package I-B) and Training Building-B (Package I-A). Vide a subsequent communication, dated 25th July, 2013, NBCC informed the plaintiff that defects, in Training Building- B (Package I-A) were persisting, and that the BSF had adversely commented on this aspect during the process of handing over/taking over inspection. 11.[8] The plaintiff responded, vide letter dated 19th September, 2013, stating that the defects, pointed out in Barrack-3 (Package II-B) and Training Building-B (Package I-A) had been rectified. The NBCC was, therefore, requested to expedite the process of handing over/taking over of Barrack-3 (Package II-B) and Training Building- B (Package I-A). 11.[9] On 11th November, 2013, NBCC wrote to the plaintiff, alleging that major rectification work continued to remain unfinished in Barrack-3 (Package II-B) and Training Building-B (Package I-A), as well as in the MI Hospital (Package I-B). In the circumstances, NBCC stated that it was left with no alternative but to impose Liquidated Damages, owing to the delay, attributable to the plaintiff, in completion of the aforesaid buildings. It was stated, in the said letter, that (i) the completion date had been crossed in respect of Training Building-A (Package I-A), the GOS Mess (Package I-A), the SOS Mess (Package I-A), the MI Building (Package I-B), Family Welfare Centre (Package I-B), and Barracks 4 and 6 (Package II-B), but the buildings were still incomplete, and that (ii) the Completion Date was yet to reach in respect of the Shopping Complex (Package I-B), Barrack-2 (Package I-B) and Barrack-5 (Package II-B). The plaintiff was, therefore, requested to submit its final completion programme.

11.10 NBCC further alleged, vide its communication dated 3rd December, 2013, addressed to the plaintiff, that defects continued to remain in Training Building-B (Package I-A) and the MI Building (Package I-B). Further, vide communication dated 20th August, 2014, NBCC alleged that defects were noticed by the BSF, at the time of handing over/taking over of the MI Hospital Building as intimated by the BSF vide letter dated 13th August, 2014. The plaintiff was, therefore, requested to rectify the said defects without delay.

11.11 On 9th October, 2014, NBCC again wrote to the plaintiff, stating that, during handing over/taking over of Training Building-B (Package I-A), Barrack-3 (Package II-B) and the MI Hospital Building (Package I-B), various defects were found, which were required to be rectified at the earliest. This was followed by further communications dated (i) 13th January, 2015, alleging persistence of defects in Training Building-B (Package I-A), the MI Hospital Building (Package I-B), Barrack-3 (Package II-B), (ii) 16th January, 2015, alleging existence of defects in the Shopping Complex (Package I-B) and (iii) 21st February, 2015, alleging existence of defects in Training Building-B (Package I-A) and the Family Welfare Centre (Package I-B).

11.12 The plaintiff wrote, on 9th April, 2015, to NBCC, requesting for extension of time, without liquidated damages, for completion of Package I-B.

11.13 On 8th May, 2015, the plaintiff wrote to NBCC, asserting that, out of Fourteen buildings, it had completed Six and handed over the buildings to NBCC. The plaintiff also requested for escalation, for the period by which completion of work under the contract had got extended beyond the originally stipulated period of Nine months. This was followed by a communication dated 1st June, 2015, in which the plaintiff asserted that Barrack-3 (Package II-B), Training Building-A (Package I-A), Training Building-B (Package I-A), the MI Hospital (Package I-B), the Family Welfare Centre (Package I-B) and the Shopping Complex (Package I-B) had been completed and handed over and that the SOS Building (Package I-A), GOS Building (Package I-A) and Barracks 2 (Package I-B), 4, 5 and 6 (Package II- B) were nearing completion. Escalation, beyond the originally stipulated period of 9 months, was again sought, and also extension of time without liquidated damages.

11.14 On 2nd June, 2015, NBCC wrote to the plaintiff, alleging that the plaintiff had failed to adhere to the stipulated milestones in the contract and that much of the work continued to be defective or incomplete. It was also asserted, in the said communication, that almost all payments to the plaintiff stood paid.

11.15 On 10th June, 2015, the plaintiff again wrote to NBCC, reiterating that Six out of the Fourteen buildings contracted, i.e. Barrack-3 (Package III-B), Training Building-A (Package I-A), Training Building-B (Package I-A), the MI Hospital (Package I-B), Family Welfare Centre (Package I-B) and Shopping Complex (Package I-B) had been completed and handed over, and that the remaining Eight buildings were in the process of completion. The plaintiff also blamed NBCC for delay in progress of the work, attributing it to an availability of cash flow and free funds. In order to complete the remaining work, the plaintiff sought extension of time without liquidated damages, escalation and payment of its pending bills. The request for payment of its pending bills was reiterated by the plaintiff, vide its letter dated 2nd July, 2015, to NBCC.

11.16 On 3rd October, 2015, NBCC again wrote to the plaintiff, assuring the plaintiff that there was no fund problem and that “as the work progress, you will be paid immediately”. The following assurance was contained in the said communication: “Please recall our discussion held on 26-8-2015 with undersigned in SBG office, Mumbai, and it was informed that there is no fund problem, and as the work progress, you will be paid immediately. In spite of various incomplete items/non executed items included in bill passed, payment of Package I/Part B has been released to you, on your firm assurance that you will resume the work immediately and further payment on expeditious completion of incomplete items etc progressively. You are advised to start the work immediately to enable us to release payment as work progress.”

11.17 Again, on 5th December, 2015, NBCC wrote to the plaintiff, alleging that defects continued to persist in the MI Hospital Building, Family Welfare Centre and Shopping Complex, in Package I-B. This was followed by communications dated 10th June, 2016, 1st July, 2016, 2nd July, 2016th and 16th July, 2016, from NBCC to the plaintiff, alleging persistence of defects in the MI Hospital Building (Package I- B), GOS Mess (Package I-A), SOS Mess (Package I-A), Family Welfare Centre (Package I-B), Training Building-A and Training Building-B (Package I-A).

11.18 On 28th July, 2016, BSF wrote to NBCC, stating that the Barracks (Packages I-B and II-B), GOS Mess (Package I-A) and SOS Mess (Package I-A) were yet to be completed. This message was forwarded by NBCC to the plaintiff on 1st August, 2016.

11.19 Persistence of the defects in the SOS Mess (Package I-A) and Shopping Complex (Package I-B) was again alleged, by NBCC, in its subsequent communication dated 20th January, 2017, to the plaintiff, based on complaints received from the BSF in that regard.

11.20 On 12th February, 2017, the plaintiff forwarded, to NBCC, the deviation statements in respect of Packages I-A, I-B and II-A.

11.21 On 23rd March, 2017, BSF wrote to NBCC, informing that, during the inspection prior to handing over/taking over, Barrack-6 (Package II-B) was inspected by the BSF, and several shortcomings, in civil and electrical works, were noticed, which were also shown to the representative of the plaintiff, present at the site. The letter attached a list of the shortcomings, Twenty Six in number, with a request that all shortcomings be rectified at the earliest. This was reiterated by the BSF, in its subsequent communication dated 21st April, 2017, which was forwarded by NBCC to the plaintiff on 25th April, 2017.

11.22 On 19th June, 2017, BSF wrote to the NBCC, again intimating the NBCC that, on inspection, seepage was found in Training Building-A (Package I-A), the SOS Mess (Package I-A), as well as in Training Building-B (Package I-A) and Barracks 2 (Package I-B), 3 (Package II-B) and 6 (Package II-B). This, it was pointed out, was required to be rectified. The complaint was forwarded by NBCC to the plaintiff on 21st June, 2017.

11.23 On 7th August, 2017, BSF again wrote to NBCC, drawing its attention to defects which persisted in Barrack-6 (Package II-B), and calling for their rectification. This was communicated by NBCC to the plaintiff on 12th August, 2017.

11.24 On 13th September, 2017, BSF again wrote to NBCC, alleging that shortcomings were still found pending in Barracks 4 and 6 (Package II-B), before handing over/taking over. It was requested that this pending work be completed at the earliest. The request was communicated by NBCC to the plaintiff under cover of letter dated 22nd September, 2017.

11.25 On 28th September, 2017, NBCC wrote to the plaintiff, alleging that the plaintiff’s claims for excess work having been undertaken by it were not reflected from the position on the ground. Defects in the SOS Mess (Package I-A) were also referred to. It was further alleged that work was still incomplete in Barrack-5 (Package II-B).

11.26 On 6th October, 2017, the plaintiff wrote to NBCC, stating, inter alia, that the 26th RA Bill raised by the plaintiff on 24th August, 2017 for Package I-A was still awaiting payment, those certified by NBCC for ₹ 9,54,287/–. Prompt payment was requested.

11.27 Vide communications dated 7th November, 2017, NBCC alleged that work relating to Packages I-A and II-B was still incomplete, despite the expiry of the last date stipulated in that regard. Provisional extension of time was granted, therefore, to 30th November, 2017, reserving the right of NBCC to recover liquidated damages as per the GCC. The plaintiff was directed to intimate the proposed programme for completion of the remaining work.

11.28 On 22nd December, 2017, BSF again wrote to NBCC, communicating the shortcomings/defects which still persisted in Barrack-6 (Package II-B). This was forwarded by NBCC to the plaintiff on 2nd January, 2018, with the request that the defects be rectified. On the same day, i.e. 2nd January, 2018, NBCC forwarded, to the plaintiff, defects noticed by the BSF in respect of Barrack-4 (Package II-B), with a request that they be attended to, immediately.

11.29 On 24th January, 2018, the plaintiff wrote to NBCC, asserting that the work relating to Packages I-A and II-B had been completed, and the work relating to Package I-B was also completed except one building, i.e. Barrack-2, which would be completed shortly. The attention of NBCC was drawn to the pending payments of the plaintiff, with a request that the payments be expeditiously released, extension of time be granted without liquidated damages and the deviation file submitted by the plaintiff be approved.

11.30 NBCC, vide its response, dated 25th January, 2018, to the aforesaid letter dated 24th January, 2018, of the plaintiff, denied the submission, of the plaintiff, that work relating to Packages I-A and II- B was completed, or that the work relating to Package I-B was completed, except for Barrack 2. Rather, submitted NBCC,

(i) in respect of Package I-A,

(a) despite repeated communications, the defects in Training Building-A and Training Building-B were yet to be rectified by the plaintiff; (b) solar water heating system was not yet installed in the SOS Mess, though the building had been handed over on 16th November, 2016, due to which reason “this board proceeding has not been concluded for starting the defect liability period” and

(c) work was still in progress in the GOS Mess;

(ii) in respect of Package I-B,

(a) defects, pointed out in respect of the Shopping Complex, MI Hospital and the Family Welfare Centre, were yet to be rectified, and (b) work, in respect of Barrack-2, was not progressing well since long, and

(iii) in respect of Package II-B,

(a) Barracks 3, 4 and 6 had been handed over on 30th April, 2013, 9th September, 2017 and 19th June, 2017, but rectification therein were yet to be carried out, and (b) Barrack 5 had been withdrawn from the scope of work of the plaintiff, and would be executed otherwise, at the risk and cost of the plaintiff. No payments of the plaintiff, it was asserted, had been unjustifiably withheld by NBCC.

11.31 The plaintiff rejoined to the aforesaid communication, dated 25th January, 2018, of NBCC, vide letter dated 10th February, 2018, reasserting that

(i) in Package I-A,

(a) Training Building-A, Training Building-B, the SOS Mess and the GOS Mess were handed over, to NBCC, on 20th September, 2014, 2nd June, 2013, 8th February, 2017 and 24th January, 2018, respectively, (b) resultantly, the DLP, in respect of Training Buildings-A and B, and the SOS Mess, stood completed, whereas the DLP, in respect of the GOS Mess was still continuing,

(ii) in Package I-B, the MI Hospital, Shopping Complex and

Family Welfare Centre had been handed over on 15th December, 2013, 21st February, 2015 and 21st January, 2015, respectively, and the DLP, in respect of all 3 buildings, already stood completed, and

(iii) in Package II-B,

(a) Barracks-3, 4 and 6 had been handed over on 30th April, 2017, 9th September, 2017 and 1019 June, 2017, respectively, and (b) consequently, the DLP, in respect of Barrack 3 stood completed, whereas the DLP in respect of Barracks 4 and 6 was still continuing. The plaintiff further submitted that payment of its bills was being unjustifiably delayed.

11.32 NBCC again wrote to the plaintiff on 7th March, 2018, alleging that rectification of the enlisted defects, in the SOS Mess (Package I- A) was still incomplete, and requesting the plaintiff to remedy the situation at the earliest.

11.33 Vide letter dated 10th March, 2018, NBCC responded to the communication dated 10th February, 2018 supra of the plaintiff, to the following effect, in respect of the various Packages of work:

(i) in Package I-A, though all 4 buildings had been handed over on the dates indicated by the plaintiff, (a) the DLP, for Training Building-A, Training Building-B and the SOS Mess, was “not concluded as on date due to non-completion of rectification of defects”, and (b) the work in respect of the GOS Mess was still incomplete on the date of handing over,

(ii) in Package I-B,

(a) though the MI Hospital Building, Shopping Complex and Family Welfare Centre had been handed over on the dates indicated by the plaintiff, the DLP, in respect thereof, was “not concluded as on date due to non-completion of rectification of defects”, and (b) work, in respect of Barrack-2, was not progressing well, and

(iii) in Package II-B, too, though all 3 buildings (Barracks 3, 4 and 6) had been handed over on the dates indicated by the plaintiff, (a) the DLP, in respect of Barrack-3, was “not concluded as on date due to non-completion of rectification of defects”, and (b) the DLP, in respect of Barracks-4 and 6 was yet to commence, as “rectification of defects/balance works had not yet been completed”.

11.34 On 19th April, 2018, the plaintiff again wrote to NBCC, inter alia reiterating its earlier stand regarding handing over of the buildings and status of completion of DLP, in respect of Packages I-A, I-B and II-B. NBCC was once again requested to release the pending payments of the plaintiff. NBCC, in its response dated 23rd April, 2018, also reiterated its stand, as already conveyed to the plaintiff on 10th March, 2018. The plaintiff, too, in its communication dated 12th May, 2018, addressed by way of response thereto, reiterated its stand.

11.35 In the interregnum, on 8th May, 2018, the BSF wrote to NBCC, alleging that defects continued to persist in the SOS Building (Package I-A), and requesting that they be rectified so that the BSF could recheck the defect/shortcomings “to complete the handing taking over process”. The said letter was forwarded by NBCC to the plaintiff on 11th May, 2018, requesting that necessary remedial action be taken.

11.36 On 15th May, 2018, NBCC wrote to the plaintiff, advising the plaintiff to submit the Final Bill for Package IA in accordance with Clause 43.[6] of the GCC. Para-3 of the communication further stated that, though Clause 37.[3] of the GCC required payments to be made, by NBCC to the plaintiff only on receipt of corresponding payment from BSF, NBCC was releasing payment in the interests of work to expedite the progress of work at site.

11.37 On 16th May, 2018, NBCC wrote to the plaintiff, granting extension of time for completion of the work relating to Packages I-A and II-B, as sought by the plaintiff, till 30th June, 2018, subject to levy of liquidated damages.

11.38 Four Show Cause Notices were issued by the NBCC to the plaintiff on 20th June, 2018, under sub- clauses (i) to (xi) of Clause 72.[2] of the GCC, one for each Package, threatening the plaintiff with cancellation of the contract for any Package in respect of which the plaintiff failed to remedy the defaults, within 7 days.

11.39 The plaintiff responded on 26th June, 2018, reiterating the submissions already advanced by it earlier.

11.40 On 30th June, 2018, NBCC wrote to the Bank and invoked the Performance Bank Guarantee provided by the plaintiff in respect of Package II-A.

11.41 On 3rd July, 2018, NBCC again wrote to the plaintiff, alleging that work remained incomplete in Packages I-A, I-B and II-B. The plaintiff was, therefore, advised to “act as per the GCC and complete the work immediately”.

11.42 BSF wrote to NBCC on 17th July, 2018, again alleging that, at the time of handing and taking over of the works performed by the plaintiff, defects were found to be persisting, and had not been rectified even 30 days after they had been brought to the notice of the plaintiff. In the circumstances, NBCC was requested to expedite rectification thereof. The letter was communicated, by NBCC to the plaintiff on 19th July, 2018.

11.43 The plaintiff forwarded its Final Bill, for Package I-A, under cover of letter dated 24th July, 2018, for a net payable amount of ₹ 1,43,18,300/-. The appeal was accompanied by its abstract, a bill for escalation and measurements of the work done.

11.44 The Final Bill, for Package II-B, for a net payable amount of ₹ 1,64,03,331/- was forwarded by the plaintiff to NBCC under cover of letter dated 10th August, 2018, along with its abstract, a bill for escalation, measurements of the work done and a “50% Excess Quantity claim statement”.

11.45 BSF again wrote to NBCC on 21st August, 2018, intimating that “some defects were found by BOO during handing taking” and that, despite 30 days having passed since then, the defects were yet to be rectified. NBCC was, therefore, requested to take necessary action at the earliest, to ensure that the defects were set right. Attached, to the letter, was a list of defects/discrepancies/balance work as on 30th July, 2018, which included (a) 5 civil and 3 electrical works in Training Building- A, (b) 10 civil works in Training Building-B, (c) 16 civil and 13 electrical works, and 9 works relating to firefighting, in the SOS Mess and 53 works in the GOS Mess, (a) 8 civil works, 1 electrical work and 10 works relating to firefighting in the MI Hospital Building, (b) 12 civil works, 7 electrical works and 5 works relating to firefighting in the Shopping Complex and (c) 5 civil works, 5 electrical works and 9 works relating to firefighting in the Family Welfare Centre, and (a) 13 civil works in Barrack-3, (b) 27 civil works, 11 electrical works and one item of work relating to firefighting, in Barrack-4 and (c) 20 civil works and 10 electrical works in Barrack-

6. The communication was forwarded to the plaintiff on the very same day, i.e. 21st August, 2018.

11.46 By a separate communication of the same date, i.e. 21st August, 2018, NBCC rejected the 23rd RA Bill submitted by the plaintiff in respect of Package I-B. The plaintiff responded on 29th August, 2018, requesting NBCC to grant extension of time, to the plaintiff, in respect of Packages I-A and II-B till the date when the buildings in the said packages were handed over to NBCC, and to grant extension of time, without Liquidated Damages, up to 31st December, 2018, for Package I-B (in respect of Barrack-2). In response, NBCC, vide letter dated 12th September, 2019, granted extension of time, for Package I-B, till 30th September, 2018, without prejudice to the right of NBCC to recover liquidated damages as per the GCC.

11.47 Vide letter dated 24th September, 2018, NBCC intimated the plaintiff that work, in respect of Package I-B still remained to be completed. On 27th September, 2018, the plaintiff applied to NBCC for extension of time, to complete Package I-B, till 31st December, 2018, without liquidated damages.

11.48 Vide letter dated 24th October, 2018, the plaintiff sought that the time for completion of Package I-A be extended till 31st May, 2018, when the buildings relating to the said Package were handed over by the petitioner to NBCC. A similar request was made, vide letter dated 27th October, 2018, in respect of Package II-B, for extension of time till 30th June, 2018.

11.49 NBCC informed the plaintiff, vide letter dated 5th February, 2019, that the Final Bill relating to Package I-A had duly been checked with the representative of the plaintiff, and requested the plaintiff, therefore, to submit the deviation statement in respect of the said Package, so that the Final Bill could be processed at the earliest. The plaintiff submitted the said Deviation Statement, under cover of letter dated 22nd February, 2019. It was requested, therefore, that the Final Bill for Package I-A be processed and payment released.

11.50 On 30th March, 2019, NBCC wrote to BSF, informing the BSF that Barrack-2 (Package I-B) was ready for handing over, and requesting that Board be constituted for verifying inventories and taking over of the building. As subsequent communications would reveal, this has, however, not taken place till date.

11.51 Vide letter dated 18th April, 2019, addressed to NBCC, the plaintiff asserted that, except for Barrack-2, which was ready for being taken over by the BSF, all other buildings had been handed over and DLP, in respect thereof, completed. The dates of handing over, in the said communication, stated to be (a) 20th September, 2013 for Training Building-A, (b) 2nd June, 2013 for Training Building-B, (c) 8 February, 2017 for the SOS Mess and (d) 24th January, 2018 for the GOS Mess, (a) 15th December, 2013, for the MI Hospital Building, (b) 21st February, 2015, for the Shopping Complex and (c) 21st January, 2015 for the Family Welfare Centre, and (a) 30th April, 2013, for Barrack-3, (b) 9th September, 2017, for Barrack-4 and (c) 19th June, 2017, for Barrack-6. It was also pointed out, in the said communication, that the Final Bills for Packages I-A and II-B, submitted by the plaintiff, were awaiting clearance. The plaintiff also requested that the Three Performance Bank Guarantees and Nine Security Bank Guarantees, furnished by it, be released, along with the Security Deposit of ₹ 65 lakhs.

11.52 Under cover of letter dated 23rd April, 2019, the plaintiff submitted, to NBCC, the Final Deviation Statement for Package I-A, for approval, with the request that the statement be approved on priority basis.

11.53 Vide letter dated 26th April, 2019, the plaintiff submitted, to NBCC, the Final Bill for Package I-B, for ₹ 1,17,17,328/-.

11.54 Package I-B, however, faced a further hurdle, as BSF wrote, to NBCC, on 3rd May, 2019, that as defects were found in Barrack-2, it could not be handed over/taking over. NBCC was, therefore, requested to ensure that the defects be remedied at the earliest. As a consequence, NBCC, under cover of letter dated 28th May, 2019, returned, to the plaintiff, the Final Bill submitted by it in respect of Package I-B, requiring the plaintiff to complete the work relating to the said Package and re-submit the bill.

11.55 Vide letter dated 29th July, 2019, the defendant informed the plaintiff that the Final Bills, submitted by the plaintiff in respect of Package II-B, had been duly checked with the representative of the plaintiff. The plaintiff was, therefore, directed to submit the Deviation Statement, etc., in respect thereof.

11.56 On 16th April, 2019, BSF wrote to the NBCC, stating that defects still remained in the GOS Mess (Package I-A).

11.57 Vide letter dated 30th August, 2019, NBCC informed the plaintiff that the Final Deviation statement, as well as the statement of extra/substituted items, submitted by the plaintiff in respect of Package I-A, stood approved and that, therefore, the amended value for Package I-A was ₹ 75,885,922/–.

11.58 On 30th November, 2019, NBCC informed the plaintiff that, as the final Deviation Statement and statement of substituted items in respect of Packages I-B and II-B were still awaited from the plaintiff, NBCC had prepared the Final Bill for all the packages. According to the said Final Bill, the total value of Packages I-A, I-B and II-B was ₹

757.86 lakhs, ₹ 701.39 lakhs ₹ 896.66 lakhs. The plaintiff was requested to acknowledge the communication and provide its acquiescence to the finalisation of the Bills by NBCC within 15 days, failing which, it was stated, the bills would be adjusted at the aforesaid amounts without further communication. The plaintiff was also requested to complete the work relating to Barrack-2 (Package I-B) without further delay, as, otherwise, BSF would not accept the Final Bill for the said Package.

11.59 The plaintiff responded on 18th December, 2019, objecting to the Final Bills as computed by NBCC, clearly stating that they were unacceptable. The plaintiff, therefore, requested that the bills be not submitted to BSF. The plaintiff verified the measurements sent by NBCC. It was also pointed out by the plaintiff, in the said letter, that Barrack-2 had been completed by or on 30th March, 2019 and inaugurated by the BSF on 23rd July, 2019. The plaintiff undertook to rectify defects in Barrack-2, as pointed out during the DLP.

11.60 Reiterating this position, the plaintiff wrote, again, to NBCC on 8th January, 2020, asserting that the DLP was complete in respect of all structures, except Barrack-2 (Package I-B). It was again reiterated that Final Bills to be submitted by the plaintiff.

11.61 On 22nd January, 2020, NBCC wrote to the plaintiff, alleging that the defects, pointed out in the MI Hospital, Shopping Complex and Family Welfare Centre (all of Package I-B) were still not rectified. The plaintiff was, therefore, requested to provide a programme for rectification of the said defects and also to complete Barrack-2, so that the building could be taken over by the BSF.

11.62 On 6th March, 2020, BSF wrote to NBCC, clarifying that any proposal for extension of time was to be obtained from NBCC only on completion of the work, and not where the work was in progress. BSF authorised NBCC, vide the said communication, to withhold, from the bills of the plaintiff in cases where scheduled time had been extended, 10% of the sanctioned amount.

11.63 The plaintiff wrote, on 22nd May, 2020, to NBCC, drawing the attention of NBCC to Office Memorandum dated 13th May, 2020, issued by the Ministry of Finance (MOF), requiring Governmental and public Sector undertakings to return the value of security/Bank Guarantees to the contractors. The plaintiff asserted that it had completed the work assigned to it, submitted the Final Bills and that the DLP was also complete. In the circumstances, the plaintiff requested NBCC to released, forthwith, all the bank Guarantees as well as the security deposit furnished by the plaintiff.

11.64 This was followed by a communication, dated 15th June, 2020, from the plaintiff to NBCC, stating that, pursuant to the meeting between the plaintiff and NBCC on 13th March 2020, the plaintiff had signed the measurements and quantities as verified for Package I-A vide letter dated 30th November, 2019. It was, therefore, requested that the amounts as per the said bill be released to the plaintiff, including escalation. A similar request, for Package I-B, was sent by the plaintiff to NBCC on 20th June, 2020.

11.65 On 6th July, 2020, NBCC wrote to its Bank to discharge the PBGs submitted by the plaintiff for Packages I-A and II-B.

11.66 The plaintiff again wrote to NBCC on 10th July, 2020, vis-à-vis Package I-B. It was asserted, in the said communication, that the plaintiff had completed Barrack-2, which was handed over to NBCC on 30th March, 2019, inaugurated on 23rd July, 2019 and was being used by the BSF. It was further pointed out that the Final Bill for Package I-B had also been submitted by the plaintiff on 30th April,

2019. Rectification, in respect of the said Package, too, it was asserted, had been completed.

11.67 On 21st July, 2020, NBCC wrote to the plaintiff, apropos the Final Bill raised by the plaintiff for Package I-A. The letter alleged that defects, observed in Package I-A during the DLP had not yet been rectified. It was further alleged that the Final Bill had not been submitted in time. NBCC further drew attention to the GCC, which required security deposit to be released only after the DLP was completed and the final bill was adjusted, whichever was later. The plaintiff was, therefore, requested to process the Final Bill for Package I-A and resend it as soon as possible. Additionally, the plaintiff was requested to submit the Final Bill for Package II-B without further delay.

11.68 On 25th July, 2020, NBCC again wrote to the petitioner, drawing the attention of the petitioner to defects observed in Package II-B during the taking over of the works and during the DLP. The petitioner was directed to rectify the defects on or before 5th August,

2020. Similar correspondences were sent by NBCC to the plaintiff, on the same day, i.e. 25th July, 2020, with respect to Packages I-A and I-B, in the latter case specifically with respect to defects in Barrack-2. With respect to Package I-B, the letter asserted that, as Barrack-2 had not been taken over, DLP, in respect thereof, has yet to start. The Upshot

12. The entitlement of the plaintiff, to the interlocutory prayers in this application, has to be decided on the basis of the position as it emerges from the above communications, vis-à-vis the clauses in the GCC.

13. The communications between the plaintiff and NBCC make it clear that, as on date, all buildings in Packages I-A, I-B and II-B, except Barrack-5 in Package II-B and Barrack-2 in Package I-B, stand handed over to NBCC. Barrack-5 in Package II-B was withdrawn, from the contract, by NBCC, and, in respect of Barrack-2 in Package I-B, defects still remain to be rectified.

14. Completion of DLP 14.[1] Clause 74.0 of the GCC requires the plaintiff to be responsible for rectification of defects only for a period of 12 months from the date of taking over of the works by the owner/client. The communications on record make it clear that plaintiff and NBCC have both been reckoning the DLP building-wise, and not package-wise. I am unable, therefore, to agree with the submission of Mr. Wali, learned Counsel for NBCC, that the DLP was required to be assessed package-wise. 14.[2] Clause 74.0 fixes the DLP as twelve months from the date of taking over of the works by NBCC/BSF. The communications cited hereinabove make it clear that all buildings have been taken over, in all Packages, except those which were withdrawn from the contract and Barrack-2. More than twelve months have also elapsed, since the date of such taking over. Clause 74.0 does not permit extending the DLP beyond twelve months, merely because defects are found in the buildings after they are taken over. The import of Clause 74.0 is clear and unequivocal. It is not open to the NBCC to, indefinitely, continue to point out defects in the buildings as handed over by the plaintiff, even after the buildings are taken over by the BSF. That liberty enures, in favour of NBCC, only for a period of twelve months, and no more. The attendant liability on the plaintiff is to ensure that defects, pointed out within the said period of twelve months, are remedied and rectified. The DLP does not stand extended till the defects are remedied or rectified to the satisfaction of the NBCC or the BSF. Clause 74.0 also provides for the consequence, in the event of default, on the part of the plaintiff, in carrying out the rectifications, as pointed out during the DLP, which is that NBCC may have the defects rectified otherwise, at the cost and expense of the plaintiff. The stand of NBCC, as manifested from various communications addressed to the plaintiff, that, as the defects, pointed out in the buildings handed over by the plaintiff were yet to be completely rectified, the DLP would not come to an end, is contrary to Clause 74.0 and cannot be accepted. To reiterate, therefore, the DLP, in respect of all buildings except Barrack-2 (Package I-B), has come to an end.

15. Re. Clause 37.[3] of the GCC Clause 37.[3] of the GCC provides that plaintiff would be entitled to payment, from NBCC, only after NBCC receives the corresponding payment from BSF, for the work done by the plaintiff. The very enforceability of such a clause, which makes payment to the plaintiff, of the work done by the plaintiff, contingent on payment being made by BSF to NBCC, with no stipulation as to time, may itself be questionable under the Indian Contract Act, 1872. In the present case, however, it would not be open to NBCC to seek shelter behind Clause 37.3, as NBCC itself novated the said clause, vide its communications dated 3rd October, 2015 and 15th May, 2018 supra. In its letter dated 3rd October, 2015, NBCC clearly undertook to pay, “immediately”, to the plaintiff, payments against works executed by it, as the works progress. The concluding sentence of the said communication further advised the plaintiff to commence work immediately, so as to enable NBCC “to release payment as work progresses”. In its subsequent communication dated 15th May, 2018, NBCC expressly noted that, despite Clause 37.[3] of the GCC, it “was releasing payment in the interest of work to expedite the progress of work at site”. Prima facie, in my view, NBCC cannot seek to oppose the application of the plaintiff on the basis of Clause 37.[3] of the GCC.

16. Clause 67.0 of the GCC NBCC also relies on Clause 67.0 of the GCC, which confers, on NBCC, the right to deduct or set off expenses incurred or likely to be incurred in rectifying defects or any claim under the GCC against the plaintiff against any amount payable to the plaintiff, from, inter alia, “security deposit and proceeds of performance guarantee”. This clause applies, at best, only to the security deposit, or payment, to the plaintiff, of the “proceeds of performance guarantee”, and does not impact, in any way, the entitlement of the plaintiff to release of the Bank Guarantees provided by it as security. Even otherwise, what the Clause permits NBCC to set off, are the expenses incurred or likely to be incurred in rectifying defects. The actual expenses which NBCC would have to incur, or would be likely to incur, for rectifying any defects which remained after completion of the work by the plaintiff, would be a matter of evidence and trial. NBCC has not, either in oral arguments during hearing, or in its written submissions, specifically identified any expenses which NBCC would have to incur, to rectify defects, or provided any prima facie material on the basis of which this Court could come to a conclusion, at this stage, that set off, or deduction, of such amounts, from the dues of the plaintiff, could be justified under Clause 67.0. The reliance, by the plaintiff, on Clause

67.0 is also, therefore, in my view, at least at this stage, misguided.

17. Which takes us to the prayers in this application.

18. Re. Prayer (i) 18.[1] Prayer (i) seeks a direction to NBCC to finalise the Final Bills submitted by the plaintiff in respect of Packages I-A, I-B and II-B. 18.[2] Unlike conclusion of the DLP, payment of the bills raised by the plaintiff is, contractually, to be effected on a bill-wise, and package-wise, rather than building-wise, basis. This position also emerges from the communications between the parties, to which detailed reference has already been made. NBCC had, vide its letter dated 30th November, 2019, communicated, to the plaintiff, the amount which, according to NBCC, was payable to the plaintiff in respect of the three Packages. The plaintiff initially objected to the said computation, vide its reply dated 18th December, 2019. Thereafter, however, consequent on the meeting between the plaintiff and NBCC on 13th March, 2020, the plaintiff had signed the measurements and quantities as verified by NBCC for Package I-A in its letter dated 30th November, 2019. The plaintiff, therefore, requested NBCC to finalise the bill and release the amounts payable to the plaintiff. To my mind, no further impediment, to the finalisation of the Final Bill of the plaintiff, in respect of Package I-A, remains. A clear case is made out, therefore, for a direction to NBCC to finalise the Final Bill in respect of Package I-A. 18.[3] The position, in respect of the other two Packages under consideration, is, however, different. The communications between the parties indicate that, till date, Barrack-2 remains unfinished, for which reason BSF has not taken over the said building either. As the Final Bill has to be settled package-wise, no direction for finalising of the Final Bill in respect of Package I-B can be issued, so long as Barrack-2 is not completed to the satisfaction of NBCC. 18.[4] The Final Bill in respect of Package II-B, as computed by NBCC and communicated vide its letter dated 30th November, 2019, has also been disputed by the plaintiff, in its reply dated 18th December, 2019. The record does not refer to any further communications from the plaintiff to NBCC, apropos the computation, by NBCC, of the amount payable to the plaintiff thereunder. It would be for the plaintiff, therefore, now, to propose, to NBCC, the amount which, according to the plaintiff, constitutes its entitlement for the work done in respect of Package I-B. Thereafter, the plaintiff and NBCC would have to work out the amount payable. It is only after this exercise is undertaken that finalisation of the Final Bill, in respect of Package I-B, is possible. 18.[5] Resultantly, no direction, for finalisation of the Final Bills, in respect of Packages I-B and II-B can be issued at this stage.

19. Re. Prayers (ii) and (iii) 19.[1] Two of the three Performance Bank Guarantees stand released by NBCC. The Performance Bank Guarantee relating to Package I-B is yet to be released. Clause 9.0 of the GCC required the Performance Bank Guarantee to be kept alive only for a period of 90 days after the end of the DLP. There is no stipulation, in the GCC, requiring the continuance of the Performance Bank Guarantee even after the expiry of the period of 90 days after conclusion of the DLP, or till all defects, in respect of any particular Package, are remedied to the satisfaction of NBCC or BSF. Indeed, the said stipulation would be manifestly unreasonable, as NBCC and BSF could continue to point out defects and, thereby, indefinitely protract the release of the Performance Bank Guarantee. Clause 9.0 of the GCC requires the Performance Bank Guarantee to be 5% of the contract value. In my prima facie opinion, NBCC would be entitled to continuance of the Performance Bank Guarantee, furnished by the plaintiff in respect of Package I-B, at best to the extent of 5% of the value of Barrack-2. 19.[2] Mr. Mehta had sought to contend that no building-wise computation of value, for the contract, existed and that the values had been worked out on a package-wise basis. Be that as it may, the value of the contract has been worked out by NBCC in the first instance. NBCC is, therefore, aware of the value to be apportioned to individual buildings in any Package. Balancing of equities, in respect of the Performance Bank Guarantee furnished by the plaintiff for Package I- B would, therefore, in my opinion, require NBCC to indicate the value attributable to Barrack-2. The value of the Performance Bank Guarantee, furnished by the plaintiff in respect of Package I-B, would stand reduced to 5% of such value. 19.[3] In the event NBCC is unwilling to apportion any specific value to Barrack-2, then, given the fact that the DLP stands concluded in respect of all buildings in the said Package except Barrack-2, the Performance Bank Guarantee furnished by the plaintiff would have to be released. In that event, the right of NBCC, to claim the differential from the plaintiff would stand reserved. 19.[4] The position, in relation to the Bank Guarantees furnished towards security is, however, somewhat different. 19.[5] Mr. Mehta has impressed, on this Court, the fact that Clause

10.0 of the GCC requires the Security Deposit – which, in his submission, would include the Bank Guarantees furnished towards security – to be returned only after expiry of the DLP, on payment of the Final Bill to the plaintiff, whichever is later. Till payment of the Final Bill, in respect of any Package, remains to be made, therefore, Mr. Mehta would submit that there can be no question of release, to the plaintiff, of the Bank Guarantee furnished by way of security for that Package. 19.[6] I am not willing, at least prima facie, to accord, to Clause 10.0, as rigid interpretation as Mr. Mehta would lend to it. 19.[7] Clause 10.0 of the GCC cannot, in my prima facie opinion, be so interpreted as to allow NBCC to delay payment of the Final Bill, qua any particular Package, without due justification and, thereafter, take advantage of the “whichever is later” caveat incorporated into the said Clause. Where all buildings, for any particular Package have been handed over by the plaintiff, and DLP also stands completed, release of the Bank Guarantee provided by the plaintiff by way of security for that Package cannot be allowed to remain pending indefinitely, till payment is made, to the plaintiff, against the relevant Final Bill. 19.[8] At the same time, Clause 10.0 makes refund of the security deposit conditional, not on finalisation of the Final Bill for any particular Package, but on payment thereof. This is a contractual covenant which the parties have executed with open eyes, and the plaintiff, as much as NBCC, must remain bound thereby. It is not possible for this Court, therefore, to direct release of the Security Bank Guarantee, for any particular Package, unmindful of the fact of payment, by NBCC, of the said Final Bill, to the plaintiff. 19.[9] The sequitur would be that where, for any reason, the stage of payment of the Final Bill, for any particular Package, has not reached, there can be no direction, interlocutory or otherwise, to NBCC, to release the Security Bank Guarantee furnished by the plaintiff in respect of that Package.

19.10 Where, however, the Final Bill, in respect of any particular Package, is ripe for payment, in my opinion, release of the Security Bank Guarantee, furnished by the plaintiff in respect of that particular Package, cannot be delayed indefinitely merely by inaction, on the part of NBCC, in making payment, to the plaintiff, of the Final Bill raised in respect thereof.

19.11 Only thus, in my prima facie view, can the equities be balanced at this stage.

19.12 I have already held, hereinabove, that the Final Bills, raised by the plaintiff, in respect of Packages I-B and II-B, are not ripe for finalisation. The only Final Bill which can be finalised at this stage is the Final Bill pertaining to Package I-A, and necessary directions in that regard have, therefore, already been incorporated in this order. Consequent on finalisation, the only intervening act, which requires to be performed, before the Security Bank Guarantee, in respect of Package I-A, can be released to the plaintiff, is payment of the Final Bill. There is, however, no prayer, in this application, for a direction to NBCC to make payment, forthwith, to the plaintiff, against any of the Final Bills raised by it. Directing release of the Security Bank Guarantee, prior to making of payment, by NBCC, against the Final Bills raised in respect of any particular Package would, however, transgress Clause 10.0 of the GCC.

19.13 In order to ensure that equities are balanced, I am of the view that NBCC requires to be directed to, consequent on finalisation of the Final Bill for Package I-A, deposit, with the Registrar General of this Court, the amount found payable to the plaintiff against the said Final Bill. Release of the Security Bank Guarantee is not specifically dependent on the amount found to be payable to the plaintiff, against any Final Bills raised by it, though Clause 10.0 does use the expression “payment of the amount of the final bill”. The letter, dated 30th November, 2019, from NBCC to the plaintiff, computed the total amount payable, against Package I-A, as ₹ 757.86 lakhs. This figure stands accepted by the plaintiff, consequent on the meeting between the plaintiff and NBCC on 13th March, 2020 and the subsequent communication dated 15th June, 2020, from the plaintiff to NBCC. In any event, NBCC has acknowledged that the plaintiff is entitled to further payment against the Final Bill raised in respect of Package I-A. The balance payment requires, in my view, at this stage, to be deposited, by NBCC, with the Registrar General of this Court, subject to further proceedings in the suit.

19.14 Once payment, against the Final Bill raised by the plaintiff in respect of Package I-A thus stands “made” by NBCC, Clause 10.0 of the GCC would justify a direction to NBCC to release, to the plaintiff, the Bank Guarantees furnished by the Plaintiff by way of security for the said Package.

19.15 The prayer, in the application, for interlocutory directions to NBCC to release, to the plaintiff, the Bank Guarantees furnished by them as security, in my opinion, be, at this stage, allowed only to this limited extent, and no more.

19.16 Directions for release, to the plaintiff, of the entire security deposit of ₹ 65 lakhs, made by it, cannot be issued at this juncture, even while the work, in respect of Package I-B, remains to be completed, and the amount payable to the plaintiff against the Final Bill for Package II-B, remains to be finalised. Security Deposit has been furnished for the entire contract as a whole, and not packagewise. The maximum to which the plaintiff would be entitled, in the matter of release of the Security Deposit, in view of the above reasoning, would be for an amount proportionate to the quantum found payable to the plaintiff, against the Final Bills raised by the plaintiff in respect of Package I-A. At the same time, there is no provision, in the GCC, for “piecemeal” or “package-wise” release of the Security Deposit. I am not, therefore, inclined to direct, at this stage, release, to the plaintiff, of the Security Deposit furnished by it. The right of the plaintiff, for directions in that regard at a later more appropriate stage would, however, stand reserved. Conclusions and Order

20. Resultantly, the following directions are issued: (1) DLP is to be reckoned on a building-wise, rather than a Package-wise, basis. (2) The DLP stands completed in respect of all buildings in Packages I-A, I-B and II-B except Barrack-2 in Package I-B. (3) Clause 9.0 of the contract between the plaintiff and NBCC requires Performance Bank Guarantee to be furnished equivalent to 5% of the contract value. Separate Performance Bank Guarantees have been furnished in respect of each Package. The Performance Bank Guarantees in respect of Packages I-A and II-B already stand released by NBCC. The only justification, therefore, for non-release of the Performance Bank Guarantee in respect of Package I-B, is the work remaining to be completed in respect of Barrack 2. This, however, in my view, cannot justify withholding of the entire Performance Bank Guarantee. The Performance Bank Guarantee furnished in respect of Package I-B has, therefore, in my opinion, to be reduced to 5% of the value of the Package, as attributable to Barrack 2. The contract value of each package has been worked out by NBCC. NBCC is, therefore, directed to file, under cover of an affidavit, the contract value applicable to Barrack 2, within a period of two weeks. The value of the Performance Bank Guarantee No. 00061PEBG12000[2], furnished by the plaintiff in respect of Package I-B, would stand reduced to 5% of the said contract value, attributable to Barrack

2. (4) In the event the NBCC is unable, or unwilling, to apportion or attribute a particular value to Barrack 2, out of the total contract value in respect of Package I-B, I am of the opinion that, possibly, a direction to release the Performance Bank Guarantee furnished by the plaintiff in respect of the said Package, may be justified, as it would not be in the interests of justice to withhold the entire Performance Bank Guarantee merely because of work remaining to be done in respect of Barrack 2. I refrain, however, from expressing any final opinion in that regard at this stage, and the decision on this aspect would be taken after compliance, by NBCC, with the direction contained in (3) supra. (5) The above directions are justified, even though Barrack 2 remains unfinished, as the value of the Performance Bank Guarantee is based on the contract value of the concerned Package, and not on the amount payable to the plaintiff against the bill, or the Final Bill, raised by it. (6) So long as Barrack 2 remains unfinished, no direction for finalisation of the Final Bill, submitted by the plaintiff in respect of Package I-B, can be issued, as the bill is required to be finalised on package-wise, and not on a building-wise, basis. Consequently, no interim directions, for release of Bank Guarantees No. 00061PEBG150018, 00061PEBG140028 and 00061PEBG170013, can be passed at this stage, in view of Clause 10.0 of the contract between the parties, which makes refund of security deposit conditional on payment of the final bill. (7) In respect of Package I-A, however, there is no justification for further delay, on the part of NBCC, in finalising the Final Bill, duly signed by the plaintiff and received by NBCC on 3rd July, 2020. The NBCC is, accordingly, directed to finalise the Final Bill relating to Package I-A within 30 days. (8) Clause 10.0 makes the release of security deposit conditional, however, not to finalisation of the final bill in respect of any package, but to payment of the final bill. At this stage, however, instead of directing release of payment of the Final Bill to the plaintiff – in respect whereof no prayer is contained in the application either – NBCC is directed to deposit, with the Registrar General of this Court, the amount found payable to the plaintiff, consequent to finalisation of the Final Bill in respect of Package I-A, within 15 days of such finalisation. Bank Guarantees No 00061PEBG150019, 00061PEBG140027 and 00061PEBG170012, furnished by the plaintiff towards security in respect of Package I-A would be released, in full, within a week thereof. Compliance report, in respect of these directions, would be filed by the NBCC, before this Court. (9) In respect of Package II-B, the Final Bill, as computed by NBCC and forwarded to the plaintiff, has been disputed by the plaintiff. In this view of the matter, no directions, for release of any Security Bank Guarantee, furnished by the plaintiff in respect of Package II-B, can be issued at this stage. Performance Bank Guarantee, furnished by the plaintiff in respect of Package II-B, already stands released. (10) As the plaintiff has chosen to dispute the amount payable to it against the final bills raised by it in respect of Package II- B, with a specific request not to forward the Final Bill to the BSF, the ball, in respect of Package II-B is, so to speak, in the court of the plaintiff. It would be for the plaintiff and NBCC to work out, between themselves, the amount payable to the plaintiff against Package II-B. Liberty would, therefore, stand reserved to the plaintiff to move this Court, in respect of any interlocutory directions, in respect of Package II-B, at a later, and appropriate, stage. (11) No direction for release of the Bank Guarantees furnished by the plaintiff as security towards Package II-B can, therefore, be passed at this stage. Liberty would, however, stand reserved to the plaintiff to move the Court, in that regard, at any later, and more appropriate, stage.

21. The time for compliance, by NBCC, with the above directions, would stand reckoned from the date of uploading, on the website of this Court, of this order or of communication by the Registry, to NBCC, by email, of a copy thereof, whichever is earlier.

22. Observations and findings, in this order, are only intended for disposal of the present application, and would not influence the Court, in further progress of the proceedings in the suit.

C. HARI SHANKAR, J.

SEPTEMBER 2, 2021