W.P(C) 11540/2021 1
HIGH COURT OF DELHI
JUDGMENT
delivered on: 12.10.2021
W.P.(C) 11540/2021
SYED SAJID ALI ..... Petitioner
versus
BSES YAMUNA POWER LTD & ANR. ..... Respondents
HON’BLE MR. JUSTICE SANJEEV SACHDEVA
Advocates who appeared in this case:
For the Petitioner: Mr. Mahboob Alam Inayati, Advocate.
For the Respondent: Mr. Manish Kumar Srivastava and Mr. Akhil Hasija, Advocates for R-1.
Mr. Rizwan, Advocate for R-2.
CORAM:-
JUDGMENT
SANJEEV SACHDEVA, J. (ORAL)
CM APPL. 35601/2021 (exemption)
Exemption is allowed subject to all just exceptions.

1. The hearing was conducted through video conferencing. W.P(C) 11540/2021 & CM APPL. 35600/2021

2. Petitioner seeks a direction to respondents to provide electricity connection at the premises of the petitioner being House No.2303, Gali Nal Bandan, Turkman, Daryaganj, Central Delhi-110002. 2021:DHC:3276 W.P(C) 11540/2021 2

3. Learned counsel for the petitioner submits that because of financial difficulty faced by the petitioner due to Corona Pandemic, bills could not be cleared. He submits that as per his instructions about Rs. 65,000/- is due and payable.

4. Learned counsel for the petitioner further submits that petitioner is willing to pay the entire dues in four equal monthly instalments.

5. Issue notice. Notice is accepted by learned counsel appearing for respondent No.1 as also by counsel appearing for respondent No.2.

6. Learned counsel appearing for respondent No.1 submits that the due amount is yet to be ascertained. He submits that as per his prima facie instructions a sum of over Rs. 80,000/- is due and payable. He submits that petitioner may visit the office of Mr. Swaroop Mukuty, Business Manager, 33 KV Grid, Kamla Market, Daryaganj, Delhi, officer of respondent No.1 for the purposes of ascertaining the final bill amount.

7. Learned counsel for the petitioner submits that on due amount being ascertained, petitioner shall pay the said amount in four equal monthly instalments.

8. This petition is accordingly disposed of directing that the petitioner to pay the entire outstanding amount as may be indicated to the petitioner by the officer of respondent No.1 in four equal monthly W.P(C) 11540/2021 3 instalments.

9. On petitioner paying the first instalment, petitioner shall also make an application for grant of a fresh connection, which application shall be processed expeditiously and preferably disposed of within a period of three working days and electricity provided, if in order.

10. It is, however, clarified that in case there is a default in payment of any of the instalments by a period more than 5 days, respondents would be at liberty to disconnect the electricity without recourse to this Court.

11. Petition is disposed of in the above terms.

12. Copy of the Order be uploaded on the High Court website and be also forwarded to learned counsels through email.

SANJEEV SACHDEVA, J. OCTOBER 12, 2021 rk