Full Text
HIGH COURT OF DELHI
Date of Decision: 03.06.2022
CONTAINER CORPORATION OF INDIA LTD. ..... Appellant
Through: Ms Divya Singh and Mr Paritosh Budhiraja, Advocates.
Through: Mr Sanjeev Puri, Senior Advocate with Mr Prateek
Mishra, Ms Moinmoi Chatterjee and Ms Tweisha Mishra, Advocates for R-1.
HON'BLE MR. JUSTICE AMIT MAHAJAN VIBHU BAKHRU, J. (ORAL)
JUDGMENT
1. The appellant has filed the present appeal impugning an ex parte order dated 12.03.2021 passed by the learned District Judge, inter alia, directing that the status quo be maintained in respect of the Performance Bank Guarantee no. 3178120BG0000192 dated 21.08.2020 and the Security Deposit Bank Guarantee No.3178120BG0000272 dated 06.10.2020 (hereafter ‘the PBG’ and ‘SDBG’ respectively). 2022:DHC:2250-DB
2. Respondent no.1 (M/s Shivakriti International Ltd. – hereafter ‘SIL’) filed a suit, inter alia, praying for a decree of permanent injunction restraining the appellant (hereafter ‘Concor’) from invoking and encashing the PBG and SDBG. SIL further sought a decree of permanent injunction restraining respondent no.2 (State Bank of India) from acting upon any letter received from Concor demanding the invocation of the two bank guarantees in question.
3. The case set up by SIL in its plaint is briefly stated as under: 3.[1] Concor issued a Letter of Acceptance (LoA) dated 06.02.2017 awarding the work pertaining to Signalling and Telecommunication at Khemli Station on Chittorgarh-Udaipur Section of Ajmer Division on North Western Railway. SIL signed the said LoA on 01.03.2017. In terms of the LoA work was to be commenced on or before the 15th day of the issuance of the LoA. 3.[2] On 04.03.2017, SIL furnished a Performance Bank Guarantee issued by State Bank of India for a sum of ₹34,64,482/- being 5% of the contract value. Thereafter, on 23.03.2017, Concor and SIL entered into a formal contract. It was stipulated that the work would be completed within a period of six months from the date of commencement (that is, six months from the 15th day of issuance of LoA). SIL claims that Concor had failed and neglected to perform its obligations under the contract and consequently, the work could not be completed within the stipulated period of time. The time for completing the contract was extended and SIL was constrained to extend the term of the Performance Bank Guarantee. SIL has averred in its plaint that despite all obstacles, it continued to perform its obligations within the limited scope as available. However, it was unable to perform substantial work due to alleged inaction on the part of Concor. SIL set out various reasons resulting in delay in completion of the said works including the delay for a period of almost 6 months on the part of Concor in deciding the supervising agency; design and drawings submitted to the Sr. DTSE Ajmer had not yet been approved; and station building for signalling and telecommunication need had not been handed over as yet. It claims that in the circumstances, it sought a short closure of the contract in question but did not receive any response to the request. It claims that in order to avoid forfeiture of the security deposit and earnest money deposit, SIL sought extension of the contract up to 31.03.2019. The same was granted initially by Concor without levy of liquidated damages.
4. SIL raised Running Bills from time to time. However, there were considerable delays in releasing payment against the said bills. SIL claims that 4th RA Bill for a sum of Rs.55,37,878.83/- was submitted in June 2018 but remained unpaid for several months. In the circumstances, SIL once again sought for short closure of the contract on ‘as is where is basis’, as it was unable to carry out further works.
5. SIL claims that on insistence of Concor, it continued to extend the term of the Performance Bank Guarantee.
6. Ministry of Finance, Government of India had issued a Circular providing relief to contractors by partial release of bank guarantees to the extent of works already completed. SIL states that it sent a letter dated 09.06.2020 seeking relief in terms of the said Circular. Since it had completed work amounting to ₹4,33,16,276/- out of a total contract value of ₹6,92,89,621/-, SIL requested that the amount of Performance Bank Guarantee be reduced in the same proportion. Since the Performance Bank Guarantee was to cover 5% of the contract value, the same was now required to be reduced to 5% of the value of the remaining works (that is, ₹12,98,667/- being 5% of the remaining work of ₹2,59,73,345/-).
7. SIL states that Concor complied with the Circular issued by Ministry of Finance and permitted SIL to replace the Performance Bank Guarantee with the PBG for a reduced amount of ₹12,98,700/-. Concor also agreed to grant further relief by releasing the security deposit (amount withheld by deduction from the Running Bills) against a Bank Guarantee. SIL submitted the SDBG for a sum of ₹34,64,482/- and the security deposit (retention money) withheld by Concor was released.
8. The averments made in the plaint indicate that there were certain disputes between Concor and SIL regarding execution of the balance works as well as on account of delay in completion of the contract. SIL sent a letter dated 03.03.2021 stating that it would not be possible for SIL to complete the balance work at the rates as agreed between the parties.
9. SIL claims that there has been a considerable delay in execution of the contract for reasons attributable to Concor and in view of rise in the prices of material and resources, it is not feasible to complete the works at the rates as initially agreed.
10. SIL claims that it is an MSME and has faced terrible financial difficulties during the pandemic; work at its project had come to a standstill and there was no inflow of any revenue. SIL claims that if in these circumstances, the bank guarantees in question are encashed, it would be unable to recover from the adverse impact and that may result in its closure.
11. SIL claims that the given circumstances give rise to special equities in its favour for interdicting Concor to encash the bank guarantees.
12. It is settled law that unconditional bank guarantees cannot be interdicted except in exceptional cases of egregious fraud and special equities. In Svenska Handelsbanken v. M/s Indian Charge Chrome and Ors.: (1994) 1 SCC 502, the Supreme Court held as under: “… in case of confirmed bank guarantees/irrevocable letters of credit, it cannot be interfered with unless there is fraud and irretrievable injustice involved in the case and fraud has to be an established fraud…. … irretrievable injustice which was made the basis for grant of injunction really was on the ground that the guarantee was not encashable on its terms…. … there should be prima facie case of fraud and special equities in the form of preventing irretrievable injustice between the parties. Mere irretrievable injustice without prima facie case of established fraud is of no consequence in restraining the encashment of bank guarantee.”
13. In Larsen & Toubro Limited v. Maharashtra State Electricity Board and Others: (1995) 6 SCC 68, the Supreme Court reiterated the law relating to the bank guarantees. The relevant extract of the said judgement is set out below:
14. In Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. And Anr.: AIR 1997 SC 2477, the Supreme Court observed as under:
15. A similar view was also expressed by the Supreme Court in Himadri Chemicals Industries Ltd. v. Coal Tar Refining Company: (2007) 8 SCC 110. The Supreme Court referred to the earlier decisions and summarized the principles regarding interdiction of a bank guarantee as under:
17. A plain reading of the above clearly indicates that there is no allegation that the contract between the parties is vitiated by fraud. The only allegation is that invocation of the bank guarantee would result in a fraud. This is not a ground for interdicting an unconditional bank guarantee. In absence of SIL establishing any fraud of an egregious nature, the question of interdicting an unconditional bank guarantee does not arise.
18. Financial difficulties due to the outbreak of Covid-19 do not give rise to any special equities to interdict an unconditional bank guarantee. More importantly, special equities are not an independent ground for seeking interdiction of the bank guarantee. In Consortium of Deepak Cable India Limited & Abir Infrastructure Private Limited (Dcil-Aipl) Thr Abir v. Teestavalley Power Transmission Limited: 2014 SCC Online Del 4741, this Court had held as under: -
19. The learned District Judge had not indicated any reasons for granting the extraordinary ad interim relief of interdicting the unconditional bank guarantees. The learned District Judge had merely noted the contentions advanced on behalf of SIL. However, as noted above, the averments made in the plaint only indicate certain contractual disputes and it is settled law that unconditional bank guarantees cannot be interdicted on the ground that disputes have arisen between the parties.
20. In view of the above, the impugned order is unsustainable and is liable to be set aside.
21. Mr Puri, learned senior counsel appearing for the respondent had raised an additional ground. He submitted that the Letter of Invocation submitted by Concor was not in terms of the bank guarantees in question. He had handed over a copy of the letter dated 15.03.2021 sent by Concor to SBI invoking the PBG. By the said letter, Concor had requested SBI to invoke the PBG “due to default by the supplier under the contract”.
22. This contention was not advanced before the learned District Judge. However, it is merited. Paragraph 2 of the said PBG reads as under:
2. We State Bank of India, do hereby undertake to pay the amounts due and payable under this guarantee without any demur, merely on a demand from the CONCOR stating that the amount claimed is due by way of loss or damage caused to or would be caused to or suffered by the CONCOR by reason or breach by the said contractor(s) of any of the terms and conditions contained in the said agreement or by reason of the contractor(s) failure to perform the said agreement. Any such demand made on the bank shall be conclusive as regards the amount due and payable by the Bank under this guarantee. However, our liability under this guarantee shall be restricted to an amount not exceeding Rs. 12,98,700/- (Rupees: Twelve Lakh Ninety Eight/. Thousand Seven Hundred only). [underlined for emphasis]
23. The PBG can be invoked only by a letter in terms of paragraph 2 of the PBG. Since the letter dated 15.03.2021 is not in terms of the PBG, SBI cannot encash the PBG pursuant thereto.
24. Having stated the above, it is also necessary to clarify that Concor is not precluded from issuing a fresh letter invoking the Bank Guarantees.
25. At the conclusion, Mr Puri requested that the Bank Guarantees may not be invoked, and SIL will voluntarily deposit the amount with the Court.
26. In view of the above, the impugned order is set aside. However, considering the statement made by Mr Puri, it is directed that the Bank Guarantees will not be invoked if SIL deposits the entire amount with the Registry of this Court within a period of one week from today. The disbursal of the amount so deposited shall be in accordance with further orders that may be passed by the learned trial court.
27. Concor is at liberty to approach the learned trial court for appropriate orders for release of the amounts as may be deposited by SIL.
28. The appeal is disposed of in the aforesaid terms.
29. All pending applications are also disposed of.
VIBHU BAKHRU, J AMIT MAHAJAN, J JUNE 3, 2022 RK