Full Text
HIGH COURT OF DELHI
Date of Decision: 07th September 2022
AIRPORT AUTHORITY OF INDIA ..... Petitioner
Through: Mr. Kiran Kumar Patra, Advocate.
Through:
JUDGMENT
ANUP JAIRAM BHAMBHANI, J.
By way of the present petition under section 34 of the
Arbitration & Conciliation Act, 1996 (‘A&C Act’ for short), the petitioner/non-claimant impugns arbitral award dated 15.06.2020 rendered by the learned sole arbitrator on disputes that had arisen between the parties from Agreement dated 14.11.2011. The transaction between the parties as comprised in the agreement was for the respondent to undertake the work of ‘External ACP Cladding, Check in Island and Glass Canopy for the New Integrated Passenger
Terminal Building’ at Netaji Subhash Chandra Bose International
Airport, Kolkata.
2022:DHC:3675
2. Although several claims were raised in the arbitral proceedings, the principal points of challenge raised by the petitioner are that by way of the impugned arbitral award dated 15.06.2020, issues Nos.
(iii) and (iv), which related to claims Nos. 1 and 2 have been allowed against the petitioner, which were untenable; and the award is amenable to challenge under section 34 of the A&C Act on those counts, as detailed below.
3. Mr. Kiran Kumar Patra, learned counsel for the petitioner submits that insofar as issue No. (iii)/claim No. 1 towards increased wages for the extended contract period is concerned, the learned sole arbitrator has drawn an inference that is contrary to his own observations in the award. In support of this submission, it is pointed-out that the contract was extended in terms of letter dated 10.01.2014, which recited as under: “REF.1. AGREEMENT NO:AAI/KOL-PORJ/SME(C)/ACP- CANOPY/2011-12/01 DATED.03.10.2011.
2. Your letter No: AAI/JKOL/Proj/ACP-Canopy/Energy(C)/3984 Date.08.01.2014 Reference to captioned above, we hereby state that there shall not be any additional/ extra claim to AAI other than admissible as per contract/ agreement if extension of time is granted to us without any levy.) Further, you are requested to kindly arrange to release all withheld amount against EOT, Land security deposit and any other amount.” (emphasis supplied) It is the petitioner’s submission that the aforesaid letter makes it clear that in consideration of extension of time granted to the respondent to complete the works, the respondent had agreed not to make any additional/extra claims under the contract. However, the petitioner contends that despite having considered letter dated 10.01.2014 addressed by the respondent to the petitioner, the learned sole arbitrator has proceeded to award claim No. 1 as follows: “23. Therefore, when it is a case of payment of increased minimum wages to the labourers, the Claimant is bound to give effect to such welfare scheme and order and pay the increased minimum wages as per the rate fixed. The Claimant had also raised bills in that regard and a compilation of such bills total numbering sixteen are placed on record at pg. 239 of the Statement of the Claim amounting to the claimed amount of Rs.42,54,140.83 which is annexed as Annexure I to the IOC claim Bill dated 28.04.2014. Neither the veracity or validity of the R.A. bills numbering 16 or the claim filed before the Respondent for payment of the amount indicated in the said R.A. bills are challenged before us. The only ground taken is that the claim is time barred and the said amount is not payable since labour/material component is not mentioned in the agreement. The Respondent has nowhere disputed that such payment of increased minimum wages was not made by the Claimant to the labourers.” “24. This argument and defence of the Respondent is belied by the language of Clause 10C of the agreement which provides that in case of wages of labour increases as a direct result of coming into force of any fresh law or statutory rule or order then the amount of the contract shall be varied to the extent of accommodating the increase.”
4. The next challenge to the award is in relation to issue No. (iv)/claim No. 2, which was also decided in favour of the respondent, awarding against the petitioner reimbursement of entry tax of Rs.4,54,339/-, that was paid by the respondent to the West Bengal Government under the West Bengal Tax on Entry of Goods Into Local Areas Act,
2012. It is the petitioner’s contention that the respondent was exempt from payment of entry tax; and even if the respondent had paid such tax, the respondent should have sought refund thereof from the State Authorities. Mr. Patra points-out that this claim is discussed by the learned sole arbitrator in the following words:
5. Mr. Patra contends that it was neither the petitioner’s responsibility, nor was it possible for the petitioner, to seek refund of entry tax paid by the respondent; and that therefore, the claim ought not to have been awarded in favour of the respondent/claimant. Counsel for the petitioner impugns the manner in which this issue has been dealt with by the learned sole arbitrator, who decided it in the following words:
6. Now, in the considered opinion of this court, firstly, the award of claim No. 1 is purely a decision on the merits of the disputes, in which this court would not interfere in a petition under section 34 of the A&C Act. Furthermore, in any event, on a fair and objective reading of letter dated 10.01.2014 issued by the respondent to the petitioner in relation to the extension of time for completion of the works, it is seen that in the said letter the respondent said that “…there shall not be any additional / extra claim to AAI other than admissible as per contract/ agreement if extension of time is granted…”. However, on a plain reading of clause 10C of the General Guidelines for Tender dated 01.09.2011 governing the agreement entered into between the parties on 14.11.2011, it is seen that the said clause specifically covers increase in wages payable by the respondent in the following words: “ If after submission of the tender, the price of any material incorporated in the works (excluding the materials covered under Clause 10CA and not being a material supplied from the Engineer-in-charge’s stores in accordance with Clause 10 thereof) and/or wages of labour increases as a direct result of the coming into force of any fresh law or statutory rule or order (but not due to any changes in sales tax/VAT) beyond the prices/wages prevailing at the time of last stipulated date for receipt of the tenders including extensions, if any, for the work, during contract period including the justified period extended under the provisions of the Clause 5 of the Contract without any action under Clause 2, then the amount of the contract shall accordingly be varied and provided further that any such increase shall be limited to the price/wages prevailing at the time of stipulated date of completion or as prevailing for the period under consideration, whichever is less…” ] It is therefore seen, that claim No. 1 towards increased wages for the extended contract period was expressly admissible as per the contract; and this claim was therefore outside the purview of the waiver of additional/extra claim by the respondent, as referred to in letter dated 10.01.2014.
7. Secondly, as regards the objection raised by the petitioner to the award of claim No. 2, on a plain reading of para 28 of the impugned award it is clear that the said sum of Rs.4,54,339/- was admittedly paid by the respondent to the West Bengal Government towards entry tax; and further, that vide letter dated 4/7.03.2015 the petitioner had itself advised the respondent to claim refund of entry tax paid, since according to the petitioner, the West Bengal Government had subsequently withdrawn the entry tax with retrospective effect.
8. From a perusal of para 29 of the impugned award, it is also seen that the learned sole arbitrator proceeded to decide this claim in a manner which is eminently fair and reasonable, holding that if refund is to be sought from the State Authorities, it should be done by joint efforts of both parties; and that the amount refunded would belong to the petitioner.
9. No other objection has either been raised or pressed, in challenge to the arbitral award.
10. At this point it would not be out of place to revisit the well-worn principles regarding the scope and ambit of objections under section 34 of the A&C Act, with a brief reference to the lucid exposition thereof by the Hon’ble Supreme Court in PSA SICAL Terminals Pvt Ltd vs. Board of Trustees of V.O. Chidambranar Port Trust Tuticorin & Ors.1, reiterating what was said in MMTC Limited vs. Vedanta Limited[2]. Some relevant paras of PSA SICAL are as follows: