Full Text
HIGH COURT OF DELHI
Date of Decision: 6th January, 2023
AMIT BROTHERS ..... Petitioner
Through: Mr Ankit Gupta, Advocate (M- 9999568812)
Through: Mr. Rakesh Kumar, CGSC with Mr. Sunil, Advocate (M-9811549455)
JUDGMENT
1. This hearing has been done through hybrid mode.
2. The present petition has been filed by the Petitioner - M/s Amit Brothers challenging the impugned letter dated 18th November, 2022 issued by the Commander Works Engineer, Air Force Tughlakabad - Respondent No. 2.
3. The background of this petition is that a work order dated 5th April, 2021 was awarded to the Petitioner for repair of certain road, road furniture, kerb stone, paths and culvert in the area of 13 BRD, 16 BRD, 27 ED and 31 MCU AT AF STN Palam under GE(P) AF GURGAON (hereinafter `the Works’).
4. The total value of the work order was Rs.54,29,840.00/-. The conditions of the contract were attached with the work order. The work order had to be executed by 6th October, 2021. However, the Petitioner did not commence the work and raised various grievances including nonallocation of godown etc., by the Respondents. Finally vide letter dated 18th November 2022, the performance guarantees to the tune of Rs. 1,63,000/have been forfeited and further sum of 2% to the tune of Rs.1,08,597/- has been demanded from the Petitioner. Until then, even the participation of the Petitioner in the bids of the Respondent has been withheld. The said letter is challenged in this writ petition.
5. Ld. counsel for the Petitioner Mr. Gupta submits that there were various justifiable causes including the Covid-19 pandemic, ban by the NGT, monsoons and escalation in prices, etc. due to which the work could not be commenced. He further submits that the debarring is illegal and contrary to law.
6. On the other hand, ld. Counsel for the Respondent, Mr. Rakesh Kumar, CGSC submits that the Petitioner has been consistently in default. The work has not even started despite almost two years having passed. He further submits that the Petitioner has also invoked the arbitration clause by seeking appointment of an arbitrator.
7. Heard. The Court has perused the correspondence on record and it is clear that after the initial work order was given on 5th April, 2021 which was to conclude by 6th October, 2021, the Petitioner kept raising one excuse or the other to even commence the work. Initially the COVID-19 pandemic was cited as the reason for non-commencement of work. In July, 2021, a grievance was raised by the Petitioner that there was a ban on running diesel generator, hot mix plant in Delhi NCR and due to the start of rainy season, it is not possible for the Petitioner to complete the work by 6th October, 2021. The letter dated 27th July, 2021 addressed by the Petitioner, reads as under:- “1. Ref. show Cause notice given by you, dated 20 July 2021. (which we have not Received till date but detailed reply on getting information)
2. It is requested that the contract for the above work was done by you with our Firm on 26 February 2021. Unfortunately at the time of the contract, there was a ban on running diesel generator /hot mix plant in Delhi NCR as per the order of Environmental Protection and Pollution Control Authority. Due to which the work could not be start at present the rainy season is going on in Delhi and around Delhi, due to which the work is not possible at present because the completion time of the work is 06th October 2021. We assure you that the work will be completed on time is decided by you.”
8. The Respondents vide letter dated 15th December, 2021 notified the Petitioner that even as of December, the work had not started and the same is not satisfactory. The Petitioner was asked to show cause as to why further issuance of tenders to the Petitioner should not be banned till completion of the subject work. In response to the same, vide letter dated 20th December, 2021, the Petitioner sought additional time to complete the work by 30th June, 2022 and continued to blame various factors such as monsoons, hot plants being closed due to NGT orders, etc.
9. The Respondents, finally vide communication dated 22nd January, 2022 rebutted all the issues raised by the Petitioner and served a final notice to commence the work by 7th February, 2022 failing which action for cancellation would be taken. It is an admitted position that even then the Petitioner did not commence the work.
10. On 10th March, 2022, the Respondent again informed the Petitioner that it is clear that the Petitioner is not in a position to execute the work on ground and that action in accordance with the contract would be taken. The said letter dated 10th March, 2022 reads as under:- “1. Reference the following:- (a) Your letter No Nil dated 27 Feb 2022. (b) This office letter No 85129/33/E[8] dt 22 Jan 2022.
(c) This office letter No 85129/36/E[8] dt 03 Feb 2022.
(d) Your letter No Nil dated 20 Jan 2022.
2. It is stated that as per your letter ref at Para 1 (a), you had promise the dept to start the work by last week of Feb or 1st week of Mar 2022. However, till date your firm have not commence the work on ground. The user is pressing very much difficulties for nonexecution of work by your firm. Further, your firm vide letter ref Para 1(a) again put forth another lame excuse for not commencing the work, which is not tenable and acceptable at all and denied in toto. Also, your contention of heavy rainfall is not agreed as from past 02 to 03 months there is no rain in near by area(s). The decision of matter of price escalation had already been conveyed vide this office letter ref at Para 1 (b).
3. In view of above, it is felt that your firm is not in position to execute the work on ground. The time given as well as promised by you had also expired. Therefore, the accepting officer had not left with any choice except to take action as per expressed and agreed conditions of contract.
4. Kind ack the receipt.”
11. Subsequent to these communications having been issued by the Respondents, the Petitioner vide communication letter dated 25th April, 2022, sought for closure of the contract under condition 59 of IAFW -2249. This was rejected by the Respondents vide letter dated 9th may, 2022.
12. On 18th November, 2022, the Respondents terminated the contract and forfeited the performance guarantee for a sum of Rs.1,63,000/-. In addition, 2% amount of the contract i.e., Rs.1,08,597/- was also demanded and in the meantime, the Respondents barred the Petitioner for consideration for any bids.
13. It is clear from the correspondence that the Respondents have been reasonable and gave repeated opportunities to the Petitioner to commence the work and to conclude the same. However, it appears that the Petitioner never intended to commence the work inasmuch as the reasons for noncommencement kept varying from letter to letter. The excuses began with non-allocation of a godown, thereafter monsoon rains, NGT ban of diesel generators, escalation of prices, etc. Each of these issues has been adverted to by the Respondents in the letter dated 22nd January, 2022 which reads as under:-
14. Even thereafter, time was given for commencement of the work by February 2022, which the Petitioner did not avail of. The said communication dated 3rd February 2022, is set out below:
15. The work order is admittedly governed by the general conditions of contract prescribed by the Military Engineer Service, 2019. The same includes an Arbitration Clause which reads as under:-
17. It is submitted by the ld. Counsel for the Respondents that the request for appointment of the Arbitrator is under process.
18. Under such circumstances and the facts of this case, where the Petitioner has clearly not even commenced the work for about a period of more than two years, considerable damage has been caused to the Respondents as the work has been delayed and the opportunity cost also exists considering that these are public roads. The stand of the Respondent seeking demand of 2% balance of Rs.1,08,597/- cannot be faulted and the communications dated 18th November 2022 and 6th December 2022 are not liable to be interfered with. However, if the Petitioner wishes to make the said payment and seek lifting of the ban imposed, it is free to do so. Upon the Petitioner making the said payment of Rs.1,08,597/- to the Respondent, there shall be no impediment, under the subject contract, for the Petitioner to participate in other bids.
19. The petition is, accordingly, dismissed. All pending applications are also disposed of.
20. Parties are relegated to the Arbitral Tribunal which may be constituted in accordance with law. The deposit shall also be subject to the outcome of the arbitral proceedings. The present order shall not be considered as the opinion on the merits of the matter.
PRATHIBA M. SINGH JUDGE JANUARY 6, 2023 MR/hh