Neutral Citation Number 2023/DHC/000369
CM(M) 746/2018 1
HIGH COURT OF DELHI
JUDGMENT
delivered on: 13.01.2023
CM(M) 746/2018 & CM APPL. 26842/2018
PROMILA SUD & ORS ..... Petitioners
versus
NAVEEN ANAND & ANR. ..... Respondents For the Petitioners : Mr. Rajiv Bahl and Mr. S.P. Srivastava, Advocates.
Advocates who appeared in this case:
For the Respondents : Mr. Sonali Malhotra, Advocate
CORAM:
HON'BLE MR. JUSTICE TUSHAR RAO GEDELA
JUDGMENT
TUSHAR RAO GEDELA, J. (ORAL)

1. Ms. Malhotra, learned counsel appears for the respondents and submits that the concession to frame the additional issues are on instructions of her client for the reason that immense delay has occured in disposal of the suit. [ The proceeding has been conducted through Hybrid mode ]

2. Mr. Bahl, learned counsel appearing for the petitioner vehemently objects to the same.

3. With consent of the parties and without prejudice to the rights and contentions and objections of both the parties, the following additional issues are framed:-

(i) Whether the suit is barred by time? OPD

(ii) Whether the defendants have right of pre-emption under

Neutral Citation Number 2023/DHC/000369 CM(M) 746/2018 2 Section 4 of the Partition Act, 1893 read with Section 22 of the Hindu Succession Act, 1956? OPD

4. In view of the aforesaid, no other issue arises nor expressed by the parties.

5. Learned Trial Court to take up these additional issues and additional affidavits, if required, may be called for, by the learned Trial Court, and then proceed in accordance with law.

6. In view of the aforesaid directions, the petition is disposed of with no orders as to costs.

TUSHAR RAO GEDELA, J. JANUARY 13, 2023