Full Text
HIGH COURT OF DELHI
Date of Decision: 17th January, 2023
UNION OF INDIA & ANR. ..... Petitioners
Through: Mr. Jitendra Kumar Singh, Advocate with Ms. Anjali Kumari & Mr. Rudresh Tripathi, Advocates.
Through: Mr. G.S. Gangwar, Advocate.
JUDGMENT
By way of the present petition under section 34 of the
Arbitration & Conciliation Act, 1996 („A&C Act‟ for short), the petitioners - Union of India (Northern Railways) - impugn arbitral award dated 09.08.2007 („impugned award‟) rendered by the learned
Sole Arbitrator, thereby deciding the disputes that had arisen between the petitioners and the respondent from a works-contract for 'Indoor
Signalling Works i.c.w. Yard Remodelling at GZB' awarded by the petitioners to the respondent on 07.12.1994. The impugned award variously decides the claims and counter-claims raised by the parties.
2. As recorded in order dated 04.03.2008, the limited challenge raised by the petitioners before this court concerns the award of pendente-lite interest and costs by way of the impugned award. Challenge to Award of Pendente-Lite Interest
3. Mr. Jitendra Kumar Singh, learned counsel appearing for the petitioners submits that in awarding pendente-lite interest on the principal sum awarded, the learned Arbitrator has acted in breach of the provisions of section 28(3) of the A&C Act (as it stood prior to amendment by way of Amendment Act 3 of 2016 which came into effect from 23.10.2015). To be sure, the award itself pre-dates the amendment, and is therefore governed by the pre-amendment provision.
4. Attention in this behalf is drawn to the pre-amendment sections 28(3) and 31(7)(a) of the A&C Act, which read as under:
5. Learned counsel for the petitioners submits that the award of interest by the learned Arbitrator is contrary to the express agreement between the parties, since clause 16(2) of the General Conditions of Contract („GCCs‟) governing the parties recites as under: "Clause 16(2) - No interest will be payable upon the earnest money or the security deposit or amounts payable to the Contractor under the contract, but Government Securities deposited in terms of sub-clause (1) of this clause will be repayable with interest accrued thereon"
6. It is submitted that on the one hand, in the impugned arbitral award the learned Arbitrator has acknowledged that under the terms of the contract entered into between the parties, the contractor, viz the respondent, was debarred from receiving any interest upon any amount payable under the contract, on the other hand, the learned Arbitrator has proceeded to award interest. It is pointed-out that taking due notice of clause 16(2) of the GCCs, in paras 27 and 28 of the award, the learned Arbitrator expressly observes that the contractor is debarred from receiving any interest upon any amount payable under the contract, saying:
7. Yet, contradicting the above inference, the learned Arbitrator proceeds to award pendent-lite interest from the date the cause of action arose till the date of the award, in the following words:
8. In support of his objection to awarding of pendente-lite interest, learned counsel for the petitioners has drawn attention to the judgment of the Supreme Court in Sri Chittaranjan Maity vs. Union of India[1], the relevant paragraphs of which read as under:
“12. Having given our thoughtful consideration to the contractual obligations entered into by the parties through clause 16, we have no reason to doubt, firstly, that the clause related exclusively to earnest money and security deposit. The above Clause did not relate to the other contractual obligations between the parties. A perusal of clause 16(1) further clarifies the position, inasmuch as, even if some payment under the contractual obligation was diverted to make good the security deposit payable, no interest would be payable thereon as well. Therefore, there can be no doubt, that non-payment of interest, contemplated between the parties under clause 16, was exclusively limited to the component of earnest money and the security deposit, which was held by the appellant and nothing else. Even though, there can be no dispute whatsoever, that Clause 16(2) is in parimateria with the clause taken into consideration in Tehri Hydro Development Corpn. Ltd.' case (supra), yet in the case before us, having read the clause in its entirety, we are satisfied, that the parties had agreed, that payment of interest would not be due, only with reference to earnest money and security deposit. Thus viewed, we have no hesitation in concluding, that the determination in the arbitral award, of component of interest, payable by the appellant to the respondent, was in terms of the contractual obligation. Nothing in the contract provided for non-payment of interest on the contractual obligations.”
11. Reliance is also placed by the respondent on the observations of the Supreme Court in Secretary, Irrigation Department, Government of Orissa and Ors. vs. G.C. Roy[4], where it has been observed thus:
12. Insofar as the award of costs is concerned, learned counsel for the petitioners submits that the learned Arbitrator has awarded Rs.[4] lacs as costs of proceedings, despite the fact that the respondent had claimed only Rs.[1] lac towards costs and the petitioners had, in any case, borne their share of the costs of the arbitral proceedings. It is submitted that there is no break-up, quantification, reason or rationale for the amount of costs awarded.
13. It is further submitted on behalf of the petitioners, that the award of costs is also contrary to the provisions of section 31(8) of the A&C Act, as it stood prior to amendment by Amendment Act 3 of 2016 which came into effect from 23.10.2015. The pre-amendment provision read as under: “(8) Unless otherwise agreed by the parties,— (a) the costs of an arbitration shall be fixed by the arbitral tribunal; (b) the arbitral tribunal shall specify—
(i) the party entitled to costs,
(ii) the party who shall pay the costs,
(iii) the amount of costs or method of determining that amount, and
(iv) the manner in which the costs shall be paid.
(i) the fees and expenses of the arbitrators and witnesses,
(ii) legal fees and expenses,
(iii) any administration fees of the institution supervising the arbitration, and
(iv) any other expenses incurred in connection with the arbitral proceedings and the arbitral award.”
14. Responding to the challenge to award of costs, learned counsel for the respondent argues that the claim of Rs.[1] lac made by the respondent towards costs, was only on tentative basis; whereas, the learned Arbitrator has quantified arbitrator‟s fee vide order dated 22.03.2007 at Rs. 4,40,000/- for 20 hearings and has further directed payment of half-share by each party.
15. Counsel argues that since the petitioners had failed to deposit their share of the arbitrator‟s fee despite reminders by the Arbitrator, this compelled the learned Arbitrator on 26.05.2007 to direct the petitioners to pay the fee due within 02 weeks, failing which the respondent was directed to pay the same, observing that the same would be treated as part of the costs. However, since the petitioners failed to deposit their share of the arbitrator‟s fee, the respondent deposited Rs.1,16,000/-, which led to the learned Arbitrator awarding costs in the sum of Rs.[4] lacs in the respondent’s favour.
16. It is further argued, that there is no bar in GCCs of 1989; nor is there any other provision that the arbitral fee and costs are to be borne in equal share by the parties; nor was there any provision in the contract that barred the arbitrator from fixing costs of proceedings in his discretion in favour of the successful party.
17. In support of this submission, the respondent places reliance on the decision of this court in Union of India vs. Om Vajrakaya Construction Company[5] where this court held as under:
33. Unlike the power of the Arbitral Tribunal to award interest under Section 31(7)(a) of the A&C Act, which is subject to the contract between the parties, there are no such fetters on the discretion of the Arbitral Tribunal to award costs under Section 31A of the A&C Act. The only exception being any agreement between the parties regarding costs which is entered into after the disputes have arisen. On partial setting-aside of an award
18. In the course of hearing the parties, a preliminary query was raised as to whether, in exercise of its jurisdiction under section 34 of the A&C Act, this court can partly set-aside an arbitral award. Learned counsel for the parties answered the query in the affirmative, to say that in any case, the challenge was only to the arbitrator‟s decision on two aspects; and the parties have accepted and acted-upon the rest of the award. That being said however, this court finds it necessary to refer to the decision of the Supreme Court in The Project Director, National Highway No. 45 E and 220, National Highways Authority of India vs. M. Hakeem and Another[6], in which case it was held that the court's power under section 34 of the A&C Act does not include the power to „modify‟ an award. The question then arises whether partial setting-aside of an award would amount to 'modification' thereof. It would be beneficial at this point to extract para 42 of M. Hakeem which reads as under:
19. Upon a closer reading of M. Hakeem (supra) however, it transpires that the said case concerned a claim for payment of compensation for land acquisition and the District Court, in exercise of its powers under section 34 of the A&C Act, had increased the quantum of compensation awarded by the competent authority. M. Hakeem (supra) therefore, was not a case where some of several claims made before the arbitral tribunal were set-aside.
20. In order to better appreciate and apply M Hakeem (supra), and to understand the correct meaning of what amounts to „modification‟ of an arbitral award, it is necessary to refer to the following decisions:
20.1. In J.G. Engineers Pvt. Ltd. vs. Union of India and Anr.,[7] which involved multiple claims dealt with and decided by the arbitrator, this is what the Supreme Court had to say: “25. It is now well settled that if an award deals with and decides several claims separately and distinctly, even if the court finds that the award in regard to some items is bad, the court will segregate the award on items which did not suffer from any infirmity and uphold the award to that extent. …”
20.2. Then again, in R.S. Jiwani (M/S.) Mumbai vs. Ircon International Ltd., Mumbai[8] a Full Bench of the Bombay High Court has dealt with the concept of severability of the decisions on various claims/counter-claims comprised in an award and has held as follows:
20.3. The judgment in R.S. Jiwani (supra) has been relied upon recently in a judgment of the Bombay High Court in National Highways Authority of India Through its Project Director and Another vs. Additional Commissioner and Others[9].
20.4. A similar view emerges in a decision of a Division Bench of the Kerala High Court in Navayuga Engineering Company Limited vs. Union of India Represented by the Chief 2022 SCC OnLine Bom 1688 Engineer10, where the Division Bench, while distinguishing M Hakeem (supra) observes as follows: “12. According to us the dictum in Hakeem's case (supra) can be distinguished on facts. As stated earlier, the District Court in the proceedings under Section 34 found that the amount of compensation granted to the land owners under the National Highway Act by the authorities under the Act was abysmally low and therefore enhanced the compensation to Rs. 645/- per sq.mtr. in the place of Rs. 46.55/- to Rs. 83.15/- per sq.mtr. This is the modification that has been interdicted by the Apex Court. However, the situation in the case on hand is different. A total of 31 claims amounting to Rs. 16,04,07,582/- was made by the appellant/claimant before the Arbitrator. An award of Rs. 3,93,24,065/- with interest was granted by the Arbitrator. The court below in the proceeding under Section 34 initiated by the respondent/UoI, confirmed the award on some claims and set aside the award on certain other claims. The claims are independent and separate. This is not a case in which the award of compensation under any particular head was revised/changed or altered, but a case in which the portion of the award relating to certain independent claims were set aside. *****
14. As in the aforesaid decision, in the case on hand also, the award has dealt with and decided several claims separately and distinctly. Therefore, if the court finds the award with regard to some claims to be bad, the court can segregate the award on items which did not suffer from any infirmity and uphold the award to that extent. If such an interpretation is not given, it would result in gross injustice and absurd results because the court would have to set aside that portion of the award also which suffers from no infirmity. This certainly cannot be what was contemplated by the Legislature. No reference has been made to J.G. Engineers Pvt. Ltd. (supra) in Hakeem's case nor has it been distinguished or overruled. The decision in J.G. Engineers Pvt. Ltd. is apparently not under Article 142 of the Constitution also. That being the 2021 SCC OnLine Ker 5197 position, we find that the doctrine of severability can be applied to proceedings under Section 34 also because as held in R.S. Jiwani (supra), if a person can challenge an award in part, certainly the court can also set aside an award in part. That being the position, we negative the argument advanced on behalf of the appellant that the impugned order is liable to be set aside on the said preliminary ground alone.”
20.5. To be sure, it is also necessary for this court to point-out that the apparently contrary view taken by a Division Bench of this court in MBL Infrastructures Ltd. vs. Telecommunication Consultants of India 11, is distinguishable on facts, inasmuch as while holding that an arbitral award can only be set-aside as a whole, the court was dealing with a case where the learned single Judge had proceeded to correct errors and thereby modify the arbitral award, which the Division Bench held was beyond the scope of the powers of the court under section 34 of the A&C Act. In that case, the Division Bench found fault with the learned single Judge having modified and corrected the amounts awarded under individual heads of claims and counterclaims, which, there is no dispute, the court cannot do in exercise of powers under section 34. However, the Division Bench was not seized of and did not express any opinion on the question of what the correct course of action would be if one or more claims in their entirety are set-aside - but not 2022 SCC OnLine Del 4613 modified - by the court in exercise of its jurisdiction under section 34 of the A&C Act.
21. It is important to appreciate that the A&C Act does not define an „award‟, except to say in section 2(1)(c) that „arbitral award‟ includes an interim award. But typically, an arbitral award includes decisions on multiple claims and counter-claims raised by the disputing parties; and thus the award commonly comprises a bouquet of decisions of the arbitrator on separate claims and counter-claims.
22. Furthermore, in line with what is mandated in section 5 of the A&C Act, the settled position of law is that judicial intervention in arbitral proceedings and in an arbitral award is to be „minimal‟. What sense would it then make, to say that if an arbitral award is challenged under section 34, it is the bounden duty of the court to either uphold the arbitrator‟s decisions „wholesale‟ on all claims/counter claims; or set them aside „wholesale‟ on all claims/counter-claims ? What if an arbitral award is challenged only in relation to decisions on certain claims/counter-claims (as is the case in the present matter); or, upon a consideration of the challenge made, the court finds no fallacy in the decision of the arbitrator on some of the claims/counter-claims; and is of the view that the decision on other claims /counter-claims requires to be set-aside ? In such circumstances, would the court necessarily have to wield the axe even on decisions with which it does not find any fault ?
23. Upon a combined and meaningful reading of the provisions of the A&C Act and the aforesaid judicial precedents, in the opinion of this court, the following position emerges: 23.[1] A court exercising power under section 34 of the A&C Act cannot „modify‟ an arbitral award; 23.[2] The arbitrator‟s decision on each claim and counter-claim, taken individually, is final. „Modification‟ means to substitute the court‟s own decision for the decision made by the arbitrator on any given claim or counter-claim; which the court cannot do; 23.[3] If objections are filed under section 34, impugning the arbitrator‟s decision only on some of the claims or counterclaims, it is not necessary for the court to set-aside the entire arbitral award viz. the decision on all claims and counterclaims. This follows from the limited ambit of the court‟s powers under section 34. Besides, the decision on a section 34 petition cannot go beyond the scope of the challenge itself; 23.[4] When the arbitrator‟s decisions on multiple claims and counterclaims are severable and not inter-dependent, the court is empowered under section 34 to set-aside or uphold the arbitrator‟s decisions on individual and severable claims or counter-claims; without having to set-aside the entire arbitral award. That would not amount to modification of the arbitral award; 23.[5] The above is also in-line with the overarching principle that the scope of interference by the court under the A&C Act in arbitral proceedings and arbitral awards, is to be minimal. The statute does not command the court to go for the overkill. To adapt a phrase famously used by Justice Felix Frankfurter, while exercising power under section 34, it is not necessary to burn the house to roast the pig! Conclusions
24. In the opinion of this court, there is merit in the challenge made by the petitioners to the arbitral award on both counts, viz. as regards the award of pendente-lite interest as also the award of the costs in favour of the respondent.
25. Insofar as the award of pendente-lite interest is concerned, upon a plain reading of section 28(3) as it stood before it was amended w.e.f. 23.10.2015, it is apparent that the mandate of the law was that “... the arbitral tribunal shall decide (the disputes) in accordance with the terms of the contract...”, meaning thereby that in the present case, the learned Arbitrator had mandatorily to go by the provisions of clause 16(2) of the GCCs of 1989 which governed the contractual relationship between the parties. This clause specifically provided that no interest was to be payable to the respondent, not only upon the earnest money or the security deposit but also on “amounts payable to the Contractor under the contract”. In fact, the learned Arbitrator has acknowledged the applicability of this clause in his own award, but has yet proceeded, to award interest pendente-lite for the period from July 2001 to July 2007, which was impermissible under clause 16(2). The learned Arbitrator himself observes that he had no jurisdiction to “...ignore any contractual provision and award amounts dehors the contract” and that the “... claim of interest is not admissible in view of said contractual provision”; but then goes-on to award interest for an even longer period though at a lesser rate, against the terms of the contract. This, the learned Arbitrator could not have done.
26. The argument made on behalf of the respondent that clause 16(2) only applies to earnest money, security deposit or amounts diverted from such earnest money or security deposit holds no water, inasmuch as the clause, in so many words, applies to “... amounts payable to the Contractor under the contract”. The amounts awarded by the learned Arbitrator after adjudicating the disputes between the parties were obviously amounts claimed by the respondent/contractor to be due from the petitioners under the contract. If under the contractual terms, the contractor was not entitled to interest on such payments, that position would not change merely because amounts were awarded after adjudication by the learned Arbitrator.
27. In interpreting clause 16(2) of the GCCs, this court is also guided by the decision of the Supreme Court in Union of India vs. Manraj Enterprises12, wherein the Supreme Court has interpreted an in parimateria clause as under:
28. Insofar as the award of arbitral costs is concerned, apart from the fact that the respondent had claimed costs only of Rs.[1] lac, the fact that the learned Arbitrator offers no break-up, quantification, reason or rationale for award of costs of Rs.[4] lacs against the petitioners cannot be ignored. It is clear from a bare reading of pre-amendment section 31(8) of the A&C Act, that even under that provision, costs are meant to be „reasonable costs‟ relating to fee and expenses of arbitrator and witnesses; legal fee and expenses; administration fee of institution supervising the arbitration and any other expenses incurred in connection with the arbitration proceedings and the arbitral award. Absent any heads under which costs have been quantified or awarded, and absent any reasoning therefor, the award of costs of Rs.[4] lacs must be held to be arbitrary. It may be observed here that the mandate contained in section 31(3), that an arbitral award shall state the reasons on which it is based, must pervade all and every aspect of the award, including award of costs. Awarding costs by a stroke of the pen, without stating reasons therefor, would fly in the face of section 31(3), apart from being opposed to well accepted canons of fairness and justice.
29. On this point, the argument made on behalf of respondent, that the learned Arbitrator has awarded costs based on the number of hearings; or that the petitioners‟ default in depositing its share of Rs.1,16,000/of the arbitrator’s fee impelled the learned Arbitrator to award costs, also does not address the complete lack of quantification of costs awarded against the petitioners.
30. Accordingly, in the opinion of this court, the award of costs in the sum of Rs.[4] lacs is arbitrary, unreasoned and therefore untenable in law.
31. In this view of the matter, the court is persuaded to accept the present limited challenge to arbitral award dated 09.08.2007.
32. Accordingly, the impugned arbitral award is set-aside limited to the award of pendente-lite interest and costs.
33. The petition is disposed-of in the above terms.
34. Pending applications, if any, also stand disposed of.
ANUP JAIRAM BHAMBHANI, J. January 17, 2023