SH Varun Gupta v. Union of India through CPWD & Ors.

Delhi High Court · 27 Feb 2023 · 2023:DHC:1458
Chandra Dhari Singh
ARB.P. 1458/2022
2023:DHC:1458
civil appeal_allowed

AI Summary

The Delhi High Court appointed a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to adjudicate disputes arising from a terminated construction contract, facilitating arbitration as agreed by the parties.

Full Text
Translation output
NEUTRAL CITATION NO. 2023/DHC/001458
ARB.P. 1458/2022
HIGH COURT OF DELHI
Date of Order : 27th February, 2023
ARB.P. 1458/2022
SH VARUN GUPTA ..... Petitioner
Through: Mr. Ganesh Khanna, Advocate
VERSUS
UNION OF INDIA THROUGH CPWD & ORS. ..... Respondents
Through: Mr. Bhagvan Swarup Shukla, CGSC with Ms. Sunita Shukla and
Mr. Vikrant along with Mr. Sarvan Kumar, GP
CORAM:
HON'BLE MR. JUSTICE CHANDRA DHARI SINGH O R D E R
CHANDRA DHARI SINGH, J (Oral)
JUDGMENT

1. The present petition has been filed on behalf of the petitioner under Section 11(6) of the Arbitration and Conciliation Act, 1996 seeking appointment of sole arbitrator for redressal of disputes arising between the parties qua the General Conditions of Contract (GCC) executed on 3rd December, 2015.

2. Learned counsel appearing on behalf of the petitioner submitted that the petitioner herein was awarded the work namely "Face Lifting, Renovation and Upgradation of Bank of Baroda, New Delhi DG 2014-15 (SH: Removing of stone slab from cladding providing and fixing aluminium windows and exterior finishing") bearing agreement NO. 62/EE/CD/2015-16, with the date of initiation as 13th December, 2015 and stipulated date of completion as 12th June, 2016.

3. It has been submitted on behalf of the petitioner that the work was carried out in accordance with the terms of the contract with the intention of completing it within the specified time frame. However, due to the presence of several obstacles on site and the unavailability of the site, the work could not be completed within the specified time frame. The Department allegedly neglected to give the petitioner with the site and drawings in a timely manner. It is further submitted that the said hindrances were time and again brought to the notice of department via various communications, however, no action had been taken by the department to resolve the same.

4. It has been submitted that on 21st August, 2017, the petitioner herein filed a revised programme chart indicating therein the challenges and impediments on site and that with elimination of such impediments, the petitioner herein would finally be able to finish the work by 31st January, 2018.

5. It has been submitted on behalf of the petitioner that the Department did not remove the hindrances despite having been intimated. To the contrary, on 2nd May, 2018, by letter no. 54(BOB)/AB/C- Div/2018-19/1239, the Department terminated the contract without providing any justification. It is further submitted that such arbitrary and malafide determination of contract caused the petitioner enormous loss and the petitioner herein sent a demand notice to the Executive Engineer on 11th October, 2018 to settle the claims that arose due to malafide determination of contract but no action was taken within the prescribed time period. It has been submitted that owing to the Executive Engineer's refusal to reply to the demand letter and settlement of the claims, the petitioner contacted the Supervising Engineer on 11th March, 2018, who also remained non-responsive to the request made by the petitioner.

6. Learned counsel for the petitioner submitted that being aggrieved by the actions of the respondent, the petitioner was constrained to invoke the arbitration clause i.e., Clause 25 of the GCC vide Invocation-cum- Demand Notice dated 10th February, 2019 requesting the Chief Engineer to appoint an independent arbitrator for adjudication of the disputes between the parties.

7. Learned counsel appearing on behalf of the respondents vehemently opposed the averments made in the instant petition however has fairly conceded that the disputes between the parties are arbitral in nature and has no objection if the disputes are referred to a Sole Arbitrator.

8. Heard the learned counsel for the parties and perused the record.

9. As agreed on behalf of the parties, this Court finds it evident to refer the disagreements between the parties to an Arbitral Tribunal by appointing a Sole Arbitrator to adjudicate the disputes with respect to the GCC executed on 3rd December, 2015. Hence, the following order: ORDER

(i) Justice Kailash Gambhir (Former Judge, Delhi High

Court) is appointed as a sole arbitrator to adjudicate the disputes between the parties which have arisen under the Contract dated 3rd December, 2015;

(ii) The learned sole arbitrator, before entering the arbitration reference, shall ensure the compliance of Section 12(1) of the Arbitration and Conciliation Act, 1996;

(iii) The fee of the appointed sole arbitrator shall be in accordance with the schedule of fees prescribed under the Delhi International Arbitration Centre (Internal Management) Rules, 2012 and Delhi International Arbitration Centre (Administrative Cost and Arbitrators’ Fees) Rules, 2018 as amended vide notification dated 15th November, 2022;

(iv) At the first instance, the parties shall appear before the learned sole arbitrator within 10 days from today on a date which may be mutually fixed by the learned sole arbitrator;

(v) All contentions of the parties are expressly kept open.

5,040 characters total

10. A copy of the order be forwarded to the learned sole arbitrator on the following address: Justice Kailash Gambhir (Former Judge Delhi High Court) W-67, III Floor, Greater Kailash-I, New Delhi-110048 Mobile No. +91-9871300033 Email id: kailashgambhir1953@gmail.com

11. The petition is disposed of in the aforesaid terms along with pending applications, if any.

12. The order be uploaded on the website forthwith.