Full Text
HIGH COURT OF DELHI
M/S SUPER ADS ..... Plaintiff
Through: Mr.Anant Garg and Ms.Sreejita Mitra, Advs.
Through: Mr.Rajeev Sharma, Sr. Adv. with Ms.Shruti Sharma, Mr.Saket Chandra, Mr.Pranav
Giri, Advs.
JUDGMENT
1. This application has been filed by the defendant nos.[1] and 2 under Section 8 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the „Act‟) praying that the parties be referred to arbitration in terms of Clause 14 of the Agreement dated 04.08.2017, on the basis whereof the plaintiff has filed the present suit.
2. The present suit has been filed by the plaintiff, inter alia, praying for a decree of recovery of a sum of Rs. 6,89,57,768/- (Rupees Six Crores Eighty-Nine Lakhs Fifty-Seven Thousand Seven Hundred and Sixty-Eight only) alongwith interest thereon from the defendants.
3. It is the case of the plaintiff that the plaintiff had applied to the defendant no.1 for producing a Radio-Programme titled “Chaandi Ke Parde Se” to be broadcasted on the radio channels of the defendant no.1. The plaintiff entered into an Agreement dated 04.08.2017 with the defendant no.1 for broadcasting 260 episodes of approximately 30 minutes duration in two installments and for dividing the net revenue in two equal halves between the parties. The plaintiff claims that the payment on its invoices remained pending from the defendants and, therefore, has filed the present suit for recovery.
4. As noted hereinabove, the defendant nos.[1] and 2 have now filed the present application under Section 8 of the Act contending therein that the parties had entered into an Arbitration Agreement, as contained in Clause 14 of the Agreement dated 04.08.2017, and, in view thereof, the present suit is not maintainable and the parties should be referred to arbitration.
5. Clause 14 of the Agreement dated 04.08.2017 is reproduced hereinunder:-
6. The learned senior counsel for the defendant nos.[1] and 2/applicants, placing reliance on the judgment of the Supreme Court in Smt. Rukmanibai Gupta v. Collector, Jabalpur and Others, (1980) 4 SCC 556, submits that Clause 14 of the Agreement is an Arbitration Agreement between the parties and, therefore, the present suit is not maintainable, and the parties should be referred to arbitration.
7. On the other hand, the learned counsel for the plaintiff, placing reliance on the judgments of the Supreme Court in K.K. Modi v. K.N. Modi & Ors., (1998) 3 SCC 573; State of Orissa & Anr. v. Damodar Das, (1996) 2 SCC 216; Bihar State Mineral Development Corporation & Anr. v. Encon Builders (I) (P) Ltd., (2003) 7 SCC 418; and International Amusement Limited v. India Trade Promotion Organisation & Anr., (2015) 12 SCC 677, submits that Clause 14 of the Agreement is not an Arbitration Agreement between the parties, but is only an internal mechanism of dispute resolution.
8. I have considered the submissions made by the learned counsels for the parties.
9. Section 8 of the Act is reproduced hereinbelow:-
10. A reading of the above provision would show that where an action is brought in a matter which is subject to an Arbitration Agreement, the Court shall refer the parties to arbitration unless it finds that, prima facie, no valid Arbitration Agreement exists.
11. Section 7 of the Act defines the expression „Arbitration Agreement‟ as under:-
12. In K.K. Modi (supra), the Court was considering whether Clause 9 of the Memorandum of Understanding dated 24.01.1989 therein constitutes an Arbitration Agreement. Clause 9 of the MoU dated 24.01.1989, which was the subject matter of the dispute in the said judgment, is reproduced hereinbelow:- “Implementation will be done in consultation with the financial institutions. For all disputes, clarifications etc. in respect of implementation of this agreement, the same shall be referred to the Chairman, IFCI or his nominees whose decisions will be final and binding on both the groups.”
13. The Supreme Court in answering the above issue, held as under:-
14. The Supreme Court finally held that Clause 9 of the MoU was not an Arbitration Agreement; it was meant to be an expert‟s decision.
15. In International Amusement Limited (supra), the Supreme Court was considering whether Clause 28 of the Agreement dated 06.11.1995 therein, which is been reproduced hereinbelow, is an Arbitration Agreement between the parties:-
16. The Supreme Court held that the above Clause would not amount to an Arbitration Agreement between the parties. The reasoning of the Supreme Court is reproduced herein below:-
23. It was further held that a clause substantially similar to the clauses referred to in P. Dasaratharama Reddy was interpreted by the three-Judge Bench of this Court in State of U.P. v. Tipper Chand wherein paras 2 and 3 of the said judgment contain the reasons for holding that the clause in the agreement cannot be construed as an arbitration clause.
24. At para 18 in P. Dasaratharama Reddy, the case of State of Maharashtra v. Ranjeet Construction has been discussed wherein a two-Judge Bench of this Court interpreted Clause 30 of the agreement entered into between the parties, which is almost identical to the clauses under consideration, relying upon the judgment in Tipper Chand, and held that Clause 30 cannot be relied upon by the parties for seeking reference of any dispute to an arbitrator arising out of the contract.
25. At para 19 in P. Dasaratharama Reddy Complex case, the case of State of Orissa v. Damodar Das has also been examined, wherein the three-Judge Bench of this Court interpreted Clause 21 of the contract entered into between the parties. In the said case, this Court referred to Clause 25 of the agreement, relied upon the judgment in State of U.P. v. Tipper Chand and held that the said clause cannot be interpreted for resolution of the dispute by an arbitrator, the case fell for consideration of this Court in State of U.P. v. Tipper Chand which was relied upon in the said case is extracted at para 20 of P. Dasaratharama Reddy case as under: (SCC pp.215-16) “20. … (10) … A reading of the above clause in the contract as a conjoint whole, would give us an indication that during the progress of the work or after the completion or the sooner determination thereof of the contract, the Public Health Engineer has been empowered to decide all questions relating to the meaning of the specifications, drawings, instructions hereinbefore mentioned and as to the quality of workmanship or material used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of, or relating to, the contract drawings, specifications, estimates, instructions, orders or those conditions or otherwise concerning the works or the execution or failure to execute the same has been entrusted to the Public Health Engineer and his decision shall be final. In other words, he is nominated only to decide the questions arising in the quality of the work or any other matters enumerated hereinbefore and his decision shall be final and bind the contractor. A clause in the contract cannot be split into two parts so as to consider one part to give rise to difference or dispute and another part relating to execution of work, its workmanship, etc. It is settled now that a clause in the contract must be read as a whole. If the construction suggested by the respondent is given effect then the decision of the Public Health Engineer would become final and it is not even necessary to have it made rule of the court under the Arbitration Act. It would be hazardous to the claim of a contractor to give such instruction and give power to the Public Health Engineer to make any dispute final and binding on the contractor. A careful reading of the clause in the contract would give us an indication that the Public Health Engineer is empowered to decide all the questions enumerated therein other than any disputes or differences that have arisen between the contractor and the Government. But for Clause 25, there is no other contract to refer any dispute or difference to an arbitrator named or otherwise.”
26. Further, at para 21 of P. Dasaratharama Reddy the case of K.K. Modi v. K.N. Modi fell for consideration, wherein this Court interpreted Clause 9 of the memorandum of understanding that was signed by the two groups of Modi family. The relevant portion from the said judgment with regard to interpretation of Clause 9 of the memorandum of understanding between the parties is extracted below: “21. … „9. Implementation will be done in consultation with the financial institutions. For all disputes, clarifications, etc. in respect of implementation of this agreement, the same shall be referred to the Chairman, IFCI or his nominees whose decisions will be final and binding on both the groups.‟”
27. Further, the decision of P. Dasaratharama Reddy at para 30 referred to the case of Mallikarjun v. Gulbarga University wherein it was held that the decision of the Superintending Engineer of Gulbarga Circle was final, conclusive and binding on all parties to the contract upon all questions relating to the meaning of the specifications, designs, etc. whether arising during the progress of the work or after the completion or abandonment thereof in case of dispute arising between the contractor and Gulbarga University. The case of Punjab State v. Dina Nath was also referred supporting the same view in P. Dasaratharama Reddy.
28. In view of the aforesaid decisions and the law laid down by this Court in a catena of cases referred to supra which are reiterated in
17. I must herein also take note of the judgment of Smt. Rukmanibai Gupta (supra), which has been relied upon by the learned counsel for the defendants to contend that Clause 14 of the Agreement dated 04.08.2017 shall amount to an Arbitration Agreement between the parties. In the said case, however, the Court was also influenced by the fact that the appellant therein had herself unreservedly accepted that the Clause 15, which was in dispute therein, spelled out an Arbitration Agreement between the parties.
18. From a reading of the above judgments, it would be evident that to constitute an Arbitration Agreement, the parties must have agreed for the Arbitral Tribunal to determine the rights of the parties in an impartial and judicial manner, with the Tribunal owing an equal obligation of fairness towards both sides. The Tribunal has to act judicially after taking into account relevant evidence and submissions made by the parties before it. One must examine the true intent and purport of the Agreement and though the presence or absence of the words „Arbitrator‟, „Arbitral Tribunal‟, „Arbitration‟ may be persuasive, but are not always conclusive to determine the question whether the Clause amounts to an Arbitration Agreement between the parties. Apart from an Arbitral Tribunal, the parties may have, by consent, empowered a body to also consider the disputes between them in a ministerial and not a judicial manner like an expert (for example in the case of K.K. Modi) or as an in-house dispute resolution mechanism, like in the present case.
19. In my opinion, therefore, Clause 14 of the Agreement dated 04.08.2017 does not amount to an Arbitration Agreement between the parties. It merely provides for an in-house escalation of the disputes to the Director General, All India Radio (DG,AIR), however, it cannot curtail the right of the plaintiff to institute a Civil Suit in case the plaintiff is aggrieved of the decision of the said authority, that is, DG, AIR. The Agreement is executed with the DG, AIR being one of the parties thereto. The parties to the Agreement could never have intended to make one of them to act as an impartial dispute adjudicator/arbitrator.
20. In view of the above, I find no merit in the present application. The same is dismissed.
21. List before the learned Joint Registrar (Judicial) on 12th May, 2023, the date already fixed.
NAVIN CHAWLA, J MARCH 27, 2023