Full Text
HIGH COURT OF DELHI
FAO 179/2019, CM APPL. 18730/2019, CM APPL. 39752/2022
NATIONAL HIGHWAY AUTHORITY OF INDIA ..... Appellant
Through: Mr. Sudhir Nandrajog, Sr.
Advocate with Mr. Balendu Shekhar, Mr. Krishna Chaitanya, Mr. Sriansh Prakarsh and Mr. Rajkumar Maurya, Advocates.
Through: Mr. Swastik Singh and Mr. Himanshu Dagar, Advocates.
JUDGMENT
1. By way of present appeal filed under Section 37(1)(c) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as the ‘Act’), the appellant impugns the order dated 15.12.2018 passed in Arbitration Case No. 68/2017 whereby its objections filed under Section 34 of the Act against the Award dated 27.07.2018 were dismissed.
2. The parties are related to each other through a Contract Agreement dated 21.03.2014, whereby the Appellant had engaged the respondent as a Contractor for collection of User Fee at Kharik Toll Plaza at km 333.150 (for length of 69.961 km at Khagaria-Purnia Section of NH-31 in the State of Bihar). The respondent was appointed pursuant to an etender issued by the appellant. The contract period was for one year i.e., from 25.03.2014 to 24.03.2015.
3. The respondent alleged loss of revenue and lodged a claim for damages to the tune of Rs.1,35,26,024/- on account of reduction in the collection of User Fee in the period from 03.07.2014 to 24.11.2014. The respondent also sought return of penalty amount of Rs. 88,93,346.00 levied on it by the appellant. Additionally, interest @ 18% p.a. was claimed on the principal sum awarded alongwith cost of litigation.
4. Vide Award dated 27.07.2016, the Arbitral Tribunal (hereafter, referred to as ‘AT’) awarded the following claims. “7.[5] SUMMARY OF AWARD: Following amounts are awarded against respective Claim: Claim Nos. Amount Claimed (in Rs.) Amount Awarded (in Rs.) Remarks
1. 2. 1,35,26,024.00 88,93,346.00 68,12,000.00 27,08,700.00 Total 2,24,19,370.00 95,20,700.00
3. Interest @ 18% @10 on amounts of Rs.68,12,000.00 w.e.f. 17.05.2015 If payment not paid within 3 months of award then 12 % on amount of Rs.95,20,[7]
00.00 till date of payment
4. 5,00,000.00 Nil
5. Respondent’s Claim
6. 15,00,000 Nil.
5. The Appellant felt aggrieved by the award and filed objections under Section 34 of the Act, inter-alia including the ground that AT has travelled beyond the agreed terms of the Contract Agreement and erred in the interpretation of clause 25. The Objections were dismissed by the Court vide the impugned order.
6. Mr. Sudhir Nandrajog, learned Senior Counsel for the appellant has premised the appellant’s challenge on Clause 9 of the Contract Agreement to contend that the Award suffered from patent illegality as the claim was barred under the aforesaid clause. It was also contended that though the respondent had relied on Clause 25 i.e., Force Majeure Clause in the Contract Agreement to justify its claims however, it did not follow the procedure provided in the said clause, inasmuch as, no prior notice was given to the appellant. Lastly, it was contended that to justify its claims, respondent had to necessarily show losses suffered by it but the material placed on record would rather reveal that against the bid of Rs.14.33 crores, respondent had earned a sum of Rs.17.74 crores. Learned Senior Counsel has placed reliance on the decision of Steel Authroity of India Ltd. v. J.C. Budharaja, Government & Mining Contractor reported as (1999) 8 SCC 122 and State of Chhattisgarh & Anr. v. Sal Udyog Private Limited reported as (2022) 2 SCC 275.
7. Per contra, learned counsel for the respondent disputed the contentions raised on behalf of the appellant. It was submitted that the appellant’s reliance on Clause 9 of the Contract Agreement is misplaced as the respondent had filed its claim solely on the basis of Clause 25. Insofar as contention raised with respect to process under Force Majeure Clause not being followed, it was submitted that no such contention was even raised either before the learned Arbitrator or filed under Section 34 of the Act. It was contended that the relevant data for the months from July to November, 2014 would show that the respondent suffered reduced earnings, and it can’t be said that since the User Fee collection exceeded the bid price, the Respondent did not suffer a loss. In support of his contentions, learned counsel has placed reliance on Haryana Tourism Limited v. Kandhari Beverages Limited reported as (2022) S SCC 237.
8. In rejoinder, learned Senior Counsel for the appellant submitted that the Force Majeure Clause does not provide for filing of claim of damages and the claim, if any, has to be premised on the basis of Clause 9 of the Contract Agreement.
9. Before proceeding to discuss the rival contentions and analyzing the same, I deem it apposite to reproduce the relevant clauses of the Contract Agreement which are as under:-
10. As per the Contract Agreement, the contract period was from 25.03.2014 to 24.03.2015 however, the claim pertains to the period from 03.07.2014 to 24.11.2014. In the claim petition, the Contractor claimed that due to heavy rains and floods, there was restriction/partial closure of Bhaina river bridge for heavy vehicles at Km 155.00 on NH- 80 (Bhagalpur-Kahalgaon Section) with effect from 03.07.2014. Cracks were found in Baijini bridge near Bhaijini Fulwaria village at Km 7.00 on SH 19 (Bhaijini-Fulwaria Section) with effect from 26.07.2014, where vehicles of all kinds were stopped. Around 07.08.2014, the Paras Banni bridge on SH 25 also got damaged due to rains and floods thereby adversely affecting the use of toll plaza by vehicles.
11. It was claimed that due to the damages to the Bhaina river bridge, the passage of traffic at the toll plaza reduced significantly resulting in loss to the tune of Rs.1.25 lacs per day. Vide letter dated 22.07.2014, the Contractor sought reduction of weekly collection remittances that it was supposed to make to the Appellant. A similar request was made for additional rebate of Rs.[1] lac per day with respect to Bhaijini-Fulwaria bridge as well as for the Paras Banni bridge. The Contractor sent request letters to NHAI on 22.07.2014, 30.07.2014, 02.08.2014, 07.08.2014, 15.09.2014, 19.11.2014 and 01.12.2014.
12. The Project Director, NHAI vide letter dated 05.09.2014 recommended reduction of weekly remittance from Rs.28,82,352/- to Rs.22,33,840/- with effect from 26.07.2014. The said recommendation was claimed to be based on a survey conducted by a third party for the period from 09.08.2014 to 16.08.2014. The recommendation was rejected by the Regional Officer of NHAI on the ground that Force Majeure clause was not applicable as there was no suspension of traffic under Clause 25 of the Agreement and also for the reason that the bridges affected were not in the same section as the toll plaza. On 02.03.2015, Regional Officer of the NHAI submitted its opinion that Contractor’s claim was not tenable. The recommendation of the Project Director was also rejected by the 3 CGM Committee of NHAI.
13. AT, while relying on the map placed on record, opined that to reach toll plaza at NH 31, vehicles coming from NH 80 and SH 19 had no other route but to pass the toll plaza. The road which is the only connecting road between NH 80 and NH 31 turns towards left as well as right side when it joins NH 31 and on the left side, Kharik toll plaza is located.
14. The issue that arose for consideration before the AT was whether the aforesaid events would fall under Clause 9 or 25(b) of the Contract Agreement as admittedly, the events do not fall within the purview of Clause 25(a). Clause 9(b) prohibits the Contractor from making any claim on account of reduction in traffic on the ground of diversion of traffic as per Clause 9(a) which casts an obligation on the Contractor to survey the section of national highway or the said bridge or surrounding area and taking into consideration all such access or diversion of traffic due to deterioration of road condition or closure of road for maintenance work, whether existing or likely to come in future.
15. AT interpreted the Contract Agreement and concluded that the events highlighted by the Contractor were squarely covered by Clause 25(b) of the Contract Agreement.
16. This Court has to see whether the conclusion so arrived suffers from patent illegality. The supreme Court in Sal Udyog (Supra) reiterated its earlier observations in Delhi Airport Metro Express (P) Ltd.v DMRC reported as (2022) 1 SCC 131 while referring to the facets of patent illegality, held as under:
18. Pertinently, Clause 25(b) (ii) came to be interpreted by this Court in National Highway Authority of India v. TGV Projects & Investment Pvt. Ltd., Neutral Citation No. 2018:DHC:3477, wherein the Court has held that the clause contemplates complete blockade of “the road” affected by floods and not a mere reduction in traffic on account of a remote event of flood occurring, thereby affecting the flow of traffic leading to the contract road. The aforesaid view was upheld by the Division Bench and the SLP bearing No.21830/2019 was also dismissed.
19. Accordingly, the interpretation of Clause 25(b) (ii) adopted by the AT appears to be contrary to the intent of the parties that is reflected in the plain words of Clause 25(b) i.e., complete blockade. The AT erred in misapplying rules of interpretation by abandoning the plain language used in Clause 25(b) to fit in “partial reduction of traffic” in the Clause 25(b), as a Force Majeure event. There is no reason cited by the AT, or is otherwise apparent from the facts and records, if the parties had intended to include “partial reduction in traffic” in Clause 25(b).
20. For the reasons stated above, the Award in question is vulnerable to challenge on the ground that the award is contrary to the contractual provisions and thus squarely falls within the scope of Section 34 (2)(b)(ii) of the Act.
21. In terms of Clause 19 of the Contract Agreement, NHAI was well within its right to levy penalty (which to my mind are liquidated damages) @ 0.2% per day for initial one month of delay in depositing remittances and 0.5% for further delay beyond one month. The AT’s decision to direct refund to the Contractor is contrary to the Clause 9 and was premised on the misunderstanding that the partial reduction in traffic was a Force Majeure event, and hence untenable. As a sequitur, the award of interest also is set aside. Consequently, the appeal is allowed and the award dated 27.07.2018 is set aside. The parties are left to bear their own costs.
22. Pending applications stand disposed of.
JUDGE JUNE 02, 2023