Full Text
HIGH COURT OF DELHI
NORTH DELHI METRO MALL PVT. LTD. ..... Petitioner
Through: Mr. Amit Sibal and Mr. Jayant Mehta, Sr. Advocates with Mr. Hardeep Sachdeva, Mr. Kamal Shankar, Mr. Abhishek Awasthi, Mr. Pradyumna Sharma, Mr. Darpan Sachdeva, Advocates.
Through: Mr. Tarun Johri, Advocate for R-1.
Mr. Sandeep Sethi, Sr.
Advocate with Mr. Rahul Malhotra and Mr. Deeptanshu Jain, Advocate for R-2.
Mr. Anupam Srivastava, ASC GNCTD with Mr. Ujjwal Malhotra, Advocate.
JUDGMENT
1. The petitioner says that it was incorporated pursuant to a Concession Agreement dated 25.07.2003 („the Agreement‟) between Delhi Metro Rail Corporation Ltd. („DMRC/ R-1‟) and MGF Developments Ltd. („MGF‟), for development of a shopping mall, multiplex theatre, food court and other entertainment facilities on a plot of land in North Delhi at Khyber Pass, Civil Lines.
2. The land was licensed to the petitioner by DMRC and indeed, DMRC itself is a licensee of L&DO. The allotted land in north Delhi abuts Mall Road, Magazine Road and Timarpur Road. The petitioner‟s land of 5 hectares is in two parts. The northern part – Site B, is referred to as „Island Plot‟ and is located to the north of the Metro Deck abutting Timarpur Road. The petitioner contends that it has enjoyed access from Timarpur Road for Site B/Island Plot since 2005 but is now being illegally, arbitrarily and unreasonably deprived of access from Timarpur Road by a gate put up by R-2.
3. The petition seeks the following reliefs: “…a. Issue a writ of mandamus, or any other appropriate writ, order or direction, directing the Respondents to ensure access from Timarpur Road to the Petitioner's site located in Khyber Pass as described in the Concession Agreement between the Petitioner and Respondent No. 1 dated 25.07.2003; b. Issue a writ of mandamus, or any other appropriate writ, order or direction, directing the Respondents to demolish the gate…”
I. Issue of Maintainability
4. At the outset, R-2/ Parsvnath Developers Limited challenges the maintainability of the writ petition. It contends that: i) disputed questions of fact are best adjudicated in suits or proceedings for specific performance and not in writ petition; ii) the prayers sought cannot be granted because the relief sought is pivoted on the petitioner‟s claim of a right to access from Timarpur Road to the Island Plot which the petitioner claims has been granted to it in an agreement with DMRC; and iii) since the petition seeks adjudication of rights between the parties, which will entail leading of evidence, interpretation of clauses of the agreement, this would be best done in such proceedings of specific performance of the agreement between the petitioner and the DMRC, therefore the writ proceedings is not the correct process.
5. Refuting the said contention, the petitioner relies on the dicta of the Supreme Court in M.P. Power Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd., (2023) 2 SCC 703, which has held, inter alia, as under:
10. The Service Road coming down from Timarpur Road was at one time barricaded by R-2 so as to secure exclusive access to the residential land, to the exclusion of the petitioner from using the loop road. The moment this was brought to the notice of DMRC, it issued letters and directives to R-2 to remove the said barriers, barricades and walls. The relevant letter of DMRC is reproduced hereunder:
11. Pursuant to the aforesaid letters from DMRC, the barricading of the service road was removed so as to provide access to the petitioner as well from Timarpur Road side. DMRC has specifically intimated R-2 that the petitioner‟s only access to the „Island Plot‟ was from Timarpur Road which is separated from the other part of the petitioner‟s plot by Deck of underlying Metro Line to the Depot; that the Building Plan has been sanctioned and development has to be carried out in terms thereof; the said approved Building Plan shows access from Timarpur Road. This letter was never the subject matter of any challenge by R-2 before any authority. This letter was followed by two more communications by DMRC to the petitioner on 14.03.2018 and 06.07.2018. Another letter was issued to R-2 by DMRC on 22.06.2018 specifically calling upon R-2 to demolish the boundary wall constructed by it so that the earlier access available to M/s North Delhi Metro Mall Private Limited – petitioner was restored. The said letter reiterated that all vehicles be cleared before entering Timarpur Road. In other words, the DMRC has all along represented to all parties that North Delhi Metro Mall Private Limited will have access to the „Island Plot‟ from Timarpur Road. In the letter dated 06.07.2018, the DMRC has communicated to R-2 as under:
12. In effect, both concessionaires i.e. the petitioner and R-2 would have access to their respective plots of land from Timarpur Road through the common access road, as shown in the map. A building plan was sanctioned by the Municipal Corporation of Delhi and the same has been annexed to the petition showing petitioner‟s access to the „Island Plot‟ from Timarpur Road. It is reproduced hereunder:
13. The Building Plan was sanctioned by MCD, was drawn up as per the understanding and/or logical interpretation of the agreement. The offending boundary wall constructed by R-2 to impede access and passage to the petitioner from Timarpur Road, was in apparent breach of the understanding and terms of agreement. The wall/obstacle was demolished by DMRC. This demolition is testimony of and acceptance by R-2 that its endeavour to create, treat or represent the common access loop road as its own exclusive access was not in consonance with the scheme/ project under which both the concessionaires had been granted license rights in their respective plots of land. There was no challenge by R-2 to the said demolition by DMRC of wall built by R-2 sometime in November, 2018.
14. The petitioner‟s Concession Agreement with DMRC dated 25.07.2003 was never amended. In any case, it could not have been altered unilaterally as both parties would be required to agree to any amendment in terms of Clause 11.[5] thereof. Their respective rights got crystallized in terms of the same. The subsequent Concession Agreement between DMRC and R-2 was executed on 30.03.2004, i.e. 9 months after the petitioner‟s agreement. This subsequent agreement could not unilaterally override, obliterate or subjugate the rights of the petitioner, which stood created and secured in terms of the earlier agreement. Therefore, if something has been purported to be granted to R-2 by the subsequent agreement, it would be subject to the rights already created in favour of the petitioner. Therefore, since the petitioner has been granted right of access from Timarpur Road, the same could not be taken away unilaterally and no exclusive right could purportedly be conferred upon R-2. Subsequent rights will be subject to the rights earlier created. DMRC will need to so ensure. The learned Senior Advocate for the petitioner relies upon the dicta in S.Kumar versus S.Ramalingam (2020) 16 SCC 553, which inter alia reads as under:
15. The learned counsel for DMRC submits that in two agreements with both the licensees, common service access is shown to both parties from the loop road coming down from Timarpur Road. For the petitioner, the access is limited to service access i.e. fire access, medical services, municipal utilities, as may be.
16. In terms of Serial no. 7 of the legend to the Site Map annexed with the petitioners‟ Concession Agreement dated 25.07.2003, common access to the petitioner is shown from the same looproad from Timarpur Road, both to residential area with service access to commercial area.
17. However, for the sake of convenience and to ensure that the rights of R-2 are unhindered, an access of equivalent width of 9 mtrs. has been arranged and a road has been laid for exclusive use of R-2 from Timarpur Road. This new access is immediately to the left side of the current access. The latter portion will be an exclusive access to the petitioner. This will not create any hindrance or prejudice to either of the parties.
18. It is only upon approval by the DMRC, of the building plan proposed by the petitioner, that it was submitted to the Municipal Corporation of Delhi and was sanctioned. DMRC was aware that the first proposed building plan which showed a 6 mtrs. wide road around the Metro Deck was not a feasible option because a study carried out at the instance of DMRC apropos the load-bearing capacity of the proposed road, had opined the road to be unviable for use. In other words, even light weight motor vehicles would not be able to access the „Island Plot‟ from the southern side, i.e. from the Magazine Road. In the communications to R-2, the petitioner and other authorities, DMRC has consistently maintained that the petitioner had a right of way/access to the „Island Plot‟ from Timarpur Road.
19. Referring to the Building Plan sanctioned by the MCD on 10.01.2008, R-2 contends that the access to „Island Plot‟ is from Magazine Road by a 6mt wide road, which goes around the concrete Metro Deck; cars entering into the petitioner‟s commercial complex are to travel from the Magazine Road towards the „Island Plot‟ for parking of cars in the three basements to be constructed in the „Island Plot‟; the exit gate shown by the petitioner in its Building Plan is a misnomer and a misrepresentation by the petitioner to the Corporation; this exit gate is not in terms of the agreement; it has been placed at the end of the petitioner‟s land and it opens into the loop road going towards Timarpur Road; that the petitioner is seeking access to Timarpur Road from this exit gate, through these proceedings. R-2 submits that the Building Plan was revised in 2013, and modified in 2019, albeit with the permission and approval of DMRC for further construction, above the 3-tire underground parking.
20. The learned Senior Advocate for R-2 asserts that the petitioner would have to first show a right of access from Timarpur Road. In terms of clause 4.3.[1] of the contract between the petitioner and the DMRC, there is unlimited access to the licensed land. It does not specify as to whether the unlimited access could include access from Timarpur Road. In additional affidavit, the DMRC reiterated its stand with respect to access as under: “..6. It is submitted that in the aforesaid letters the Respondent No. 1 DMRC, had placed mistaken interpretation on the words, "Service Access" appearing in the plans attached with the Agreement of DMRC with the Petitioner, so as to include, "Construction Access" and thereby DMRC wrote the said letters stating that the Petitioner, will be given access for construction from the said road. DMRC has never assured the Petitioner in Agreement executed with it, that the construction access would be given to the Petitioner from Timarpur Road side.”
21. Mr. Amit Sibal, the learned Senior Advocate for the petitioner refutes the aforesaid contentions apropos DMRC‟s affidavit. He says that DMRC‟s own position as recorded in the order dated 09.06.2020 refutes the aforestated contentions. It reads interalia as under:-
4. The petitioner contends that other communications dated 14.03.2018(Annexure P[9]), 30.10.2018 (Annexure P19), 14.11.2018 [Annexure P21 (Colly)] and 07.02.2020 (Annexure P28), which are also in the same vein, reiterate the same position. In other words, all along the DMRC has held the view that the wall built by respondent no. 2 was illegal and it had to be broken down and that service access, i.e. access by road for vehicular movement, has to be provided to the petitioner by the DMRC from the Timarpur Roadside. The said communications have not been referred to in the counter affidavit and the said affidavit is clearly contrary to the earlier position taken by DMRC in the various letters mentioned hereinabove.
5. In view of the above, Mr. Johri, the learned counsel for DMRC, seeks time to obtain instructions and file a better affidavit, if so instructed, before the next date. Copy of the same shall be furnished to the learned counsels for the parties through e-mail and other viable electronic modes of communication….”
(ii) Service access
22. The legend in the plan annexed to the agreement between the petitioner and DMRC provides service access to the petitioner for commercial development. The term „service access‟ is not described in the contract. In the law relating to municipalities, the expressions „service passage‟ and „service access‟ would have a specific connotation, for example „service passage‟ under the Delhi Municipal Corporation Act, 1957, has been defined as under: “2(22) "house-gully" or "service passage" means a passage or strip of land constructed, set apart or utilised for the purpose of serving as or carrying a drain or affording access to a latrine, urinal, cesspool or other receptacle for filth or other polluted matter, by municipal employees or other persons employed in the cleansing thereof or in the removal of such matter therefrom;
23. Similarly the New Delhi Municipal Council Act, 1994, defines „house-gully‟ as under: “2(18) house-gully" means a passage or strip of land constructed, set apart or utilized for the purpose of serving as or carrying a drain or affording access to a latrine, urinal, cesspool or other receptacle for filth or other polluted matter, by municipal employee or other person employed in the cleansing thereof or in the removal of such matter therefrom;”
24. However, it is noted that in the latter definition the word „service access‟ or „service passage‟ is not used.
25. The petitioner relies on the Unified Building Bye Laws for Delhi, 2016, which defines service road as under: “…4.104 Service Road: A road/lane provided at the rear or side of a plot for service purposes.”
26. Reference is also made to a notification of Ministry of Shipping, Road Transport and Highways dated 05.12.2008. However, this notification is inapplicable to the present case because it is about highways not about city or colony roads.
27. Apropos access, DMRC has maintained its proposal recorded in the order of 18.12.2020. At the site, the proposal has been implemented in its entirety. However, R-2 has opposed the said proposal in its affidavit dated 11.01.2021.
28. The petitioner has not been able to access the island from the side because of repeated obstacles being created by R-2. Nevertheless, those obstacles were removed by DMRC. During the course of the hearing, R-2 asserted that access to the „Island Plot‟ would disturb the access to the residential land because trucks and other emergency vehicles would disturb the peace or otherwise quiet access to residents of the apartment block
29. MTNL occupies land abutting the loop coming down from Timarpur Road. In an effort to find a solution to accommodate the needs of both the sub-licensee(s), i.e. the petitioner and R-2, DMRC in coordination with MTNL has shifted the latter‟s telephone tower and toilet block to another part of MTNL‟s land, so as to make available a 9m wide road for exclusive use by R-2. This new access road is contiguous to the existing access from Timarpur Road.
30. The expense of construction of a new toilet block and shifting of the MTNL tower was borne by the petitioner. The new road of 6m was also laid during these proceedings, at the expense of the petitioner, with the full knowledge and cooperation of DMRC and MTNL. Now, 15m wide access is available from Timarpur Road which could provide a 9m access to the residents of Parsvnath/R-2 from the left side as shown in the map below and the 6m wide road could well be made available exclusively for the petitioner‟s island plot. There could be a clear demarcation of the two respective access points from Timarpur Road.
III. DMRC- Lessee or Licensee?
31. The petitioner contends that the L&DO is yet to lease out the property to DMRC. Therefore, the latter can at best be treated as a licensee. DMRC cannot transfer anything more to a third party, except a sub-license. R-2 insists that it had a registered lease agreement in its favour. The petitioner says, and rightfully so, that „lease agreement‟ would be an incorrect nomenclature because if the DMRC is not a lessee, it cannot create a lease or transfer deed in favour of R-2. DMRC is only a licensee of L&DO. While the agreement between DMRC and R-2 may be titled as Transfer Deed, it cannot transfer any right in the property except to put R-2 and likewise the petitioner as sublicensee and nothing more. Therefore, the nomenclature of the document called „transfer deed‟ is misleading and could not be read as anything more than a License Deed.
32. The petitioner contends that the government‟s allotment letter dated 15.11.1999 clearly stipulates as under: “...2. viii. The plot will initially be on license under an agreement and upon successful fulfilment of the terms of the contract lease will be given. The lease will, however, commence from the date of allotment...”
33. Indeed, R-2 and DMRC themselves acknowledge the L&DO‟s letter of 15.11.1999 and are deemed to have knowledge of its contents. It is recorded in their agreement dated 30.03.2004 as under: “...B. DMRC has been allotted land admeasuring about 37.80 ha located at Khyber Pass, Delhi, as more specifically described in Paragraph 1 of Annexure A and marked out in the plan set out in Annexure B („Allotted Land‟) by the Land and Development Officer, Ministry of Urban Development, Govt. Of India („L&DO‟) vide allotment letter No.L-II-I (1252)/99/888 dated November 15, 1999 for the construction of Khyber Pass Depot. In terms of the Allotment Letter to DMRC, a lease deed is required to be executed for grant of leasehold rights in favour of DMRC and the execution of such lease deed is presently pending...”
34. As contemplated in the letter of allotment dated 15.11.1999, two documents were to be executed, one was Memorandum of Agreement („MOA‟) another was a lease deed. The former was executed on 11.07.2014. It stipulates as under:
“XIX. Nothing in this Agreement shall be construed as a demised in law of the said premises or any part thereof so as to give Delhi Metro Rail Corporation (DMRC) Ltd any interest therein until and unless the said Perpetual Lease shall be executed and registered but Delhi Metro Rail Corporation (DMRC) Ltd shall only have the permission of the President to enter upon and occupy the said premises for the purpose of performance of this Agreement....
XXX. It is expressly agreed and declared by Delhi
Metro Rail Corporation (DMRC) Ltd that before execution the Perpetual Lease as required by the President, Delhi Metro Rail Corporation (DMRC) Ltd is and shall be a bare licensee in respect of the said premises. Provided that if at any time any breach of such undertaking is discovered by the president, regardless of the execution of the said Perpetual Lease, Delhi Metro Rail Corporation (DMRC) Ltd, shall be liable to pay penalty to the President by way of compensation for such contravention. The amount of terms of such penalty by way of compensation shall be fixed by the President and the same shall be binding on Delhi Metro Rail Corporation (DMRC) Ltd.
XXXI. Delhi Metro Rail Corporation (DMRC) Ltd shall not be entitled to require and title to be shown to the said piece of land to be demised as aforesaid or any proof of the right of the President to grant this bare licence or the said premises.”
35. The lease deed has yet not been executed. In effect, the DMRC has till date not become the lessee of the President of India. The aforesaid clauses clearly declare that the DMRC is a bare licensee.
36. Pursuant to the aforesaid, in its communication to the petitioner, DMRC has assured the petitioner as under:
37. DMRC fully supports the position of the petitioner and it has admitted that the nomenclatures in the agreement would be misleading because it is only a licensee and not a lessee. Therefore, it could not give or transfer anything to R-2 or any party other than a sub-licence. DMRC says that it has permitted the petitioner and R-2 to construct commercial and residential complexes respectively in terms of the allotment letter and MOA. However, the fact remains that in terms of the MOA, DMRC is nothing more than a licensee. Till such time that the lease deed is executed in favour of DMRC, it does not become a lessee of the President of India and cannot, therefore, issue a sub-lease or purport any document or agreement to be considered or interpreted as a lease document.
38. Referring to the petitioner‟s rejoinder, (page 609, para 19), R-2 contends that the land handed over by the L&DO to the DMRC is in the nature of a lease because immovable structures have to be constructed thereupon for 99 years or otherwise for at least 50 years. Referring to the paras 23,25, 26 and 32 of the dicta of the Supreme Court in Pradip Oil Corporation (2011) 5 SCC 270, he submits that the lands with the parties would be construed as leased land and not as a mere licensed land.
39. R-2 further contends that once the grant has been issued in favour of DMRC, that itself is an absolute act of transferring/vesting rights in the person/entity who is the recipient of the grant; therefore whether the document is stamped or not stamped would make no difference. For the moment, accepting the argument that DMRC is the recipient of the grant, for the latter to grant any rights in favour of a subsequent entity or another entity, the same would have to be recorded through stamped documents, which has been done in the case of R-2 but not so with the petitioner. This argument is flawed because if the grant is absolute, irrespective of whether the document is stamped or registered, then R-2‟s rights, as may be, would be subject to rights/granted already created by DMRC in favour of the petitioner, earlier in time on 25.07.2003.
IV. Public Law Element
40. The petitioner claims public law element in the project: the nonconstruction of the Mall is because of non-access from the Timarpur Road side, and this is resulting in a financial loss to the exchequer. The approved structure was to be constructed as soon as possible, so that the same could be monetized; the developed structure has to be returned to the DMRC after 50 years from 2009. Presently, the land has remained unutilized since 2003, i.e. for the past two decades.
41. The Agreement stipulates that the DMRC is to receive an annual fixed license fee as under: “5.1.[4] Concession Fee of Rs. 5,10,00,000/- (Rupees Five crores and ten lakhs only) payable per annum, after moratorium of two years from the date of signing of concession agreement, and every year thereafter till the expiry of the concession period. This Concession Fee shall be escalated at 20% every three years. The first escalation will be effective after five years from the date of signing of Concession Agreement. DMRC recognizes only the Concessionaire for making all payments in this regard. Direct payment by the suballottees to DMRC is not permissible under this Agreement.”
42. In addition to the above, the DMRC is to receive 5% of annual cash flow as under: “5.1.[3] Five percent (5%) of Annual Cash Inflows (Non-Negotiable) as per the audited annual accounts, payable every year till the expiry of concession period. The Annual Cash inflows in this case shall include all receipts from shorts & long-term lease of space, refundable & non-refundable security deposits, securitised lease rentals, all upfront payments and all forms of O&M fees charged from tenants, sub-lessees or occupants. The maintenance fees charged by the Concessionaire or any third party appointed by Concessionaire or any society promoted by Concessionaire or formed by the tenants/ sub-lessees/ occupiers of the shopping malls, if any, shall also be construed as part of the cash inflows of the Concessionaire. In case the Concessionaire collects the lease payments from his sub-lessees as lumpsum at the at the time of allotment or in installments, such payments shall be treated as part of Concessionaire‟s cash inflows for the year in which they are accruing to him.”
43. R-2 says that a lis between the petitioner and DMRC is to be referred to arbitration in terms of Article 9.[2] of their agreement. He further submits that road access to the residential area is a complete access whereas the service access to the commercial area is a qualified access and this qualified access is yet to be defined. There is a private contract with DMRC, albeit related to public land, nevertheless there is no public law element in it. Therefore, writ proceeding is not appropriate.
44. R-2 refers to its Registered agreement with DMRC whereby residential land of 6.[8] hectares (67903.22 sq. mts) forming part of a larger land admeasuring 37.80 hectares allotted to DMRC, was allocated to/demised by way of lease-hold right for a period of 99 years to R-2/Parsvnath, with a clear access from Timarpur Road, as shown in the plan marked as Part-B forming Annexure-1 to the agreement. R-2 says that the road is a part of grant. It does not indicate any access to the petitioner from the said access road.
45. R-2 paid a consideration of Rs.194 crores for the said allotment and expended Rs.10.67 crores on stamp duty; that corresponding concession fee or the cost of transfer is absent in the case of the petitioner; there is no Transfer Deed apropos the petitioner; the nature of the two transactions were entirely different and DMRC cannot purport to equate the two transactions, one by a registered document and the other by a non-registered document.
46. Referring to various judgments, R-2 contends that public law element is the only mitigating factor on the basis of which the writ petition could be maintained apropos a dispute involving a contract or enforcement of rights apropos the contract. Otherwise all judgements referred to have held that the remedy would be in civil proceedings.
47. The petitioner submits that in the last two decades the petitioner has paid DMRC monies in the range of about Rs 186 crores, which is almost equal to what DMRC has received from R-2 as a one-time license amount for the residential land; 5% of the revenue inflow is payable to DMRC as per the audited accounts of the Annual Cash Inflow, payable till the expiry of every concession period; the concession fee is to increase every three years by 20% and upon expiry of the tenure, the allotted land alongwith the buildings would return to the DMRC.
48. R-2 says that it has been permitted to construct 400 apartments of which 200 have been constructed. Ordinarily each family has about 2 cars. Therefore, once 400 apartments are occupied approximately 800 cars will be there in the residential complex and the latter has provision for parking of 1000 cars.
49. Referring to paragraph 39 (10.6) of Shapoorji Pallonji and Co. Pvt. Ltd. versus Rattan India Power Ltd. Anr 2021 SCC OnLine Del 3688, R-2 submits that the lis of this nature is to be addressed only in arbitral proceedings.
50. What emerges from the preceding arguments is that on the basis of an advertisement which showed a loop of a road coming down from Timarpur Road providing access both to the commercial „Island Plot‟ of the petitioner as well as to the residential plot of R-2, the petitioner had entered into the contract on the basis of the said representation, being fully confident that it would have at least service access to the island plot from Timarpur Road.
51. The correspondence between the petitioner, DMRC and R-2 shows the understanding of the petitioner and DMRC in this regard. It is upon DMRC‟s strict interpretation of the terms of the agreement with the petitioner, that the obstacle erected by way of construction of a wall by R-2 was removed, so as to facilitate service access to the petitioner to the „Island Plot‟ from Timarpur Road. R-2‟s agreement with DMRC was created and registered on a much later date. The rights of the petitioner to have service access from Timarpur Road were secured much earlier in time. It could not be over-ridden or superseded by a subsequent agreement between DMRC and R-2. R-2 cannot claim exclusive right of access from Timarpur Road because service access from the common road has already been granted and assured to the petitioner. This advertisement to public at large, in particular to the parties concerned, cannot be overridden by a subsequent agreement between DMRC and R- 2, much to the detriment and without notice to the petitioner.
52. As noted hereinabove, R-2 also has a main access from Magazine Road and the access from the Timarpur Road is a service access. DMRC has tried to find a fair balance by prudently carving out an exclusive contiguous access for R-2 and/or the owners of the flats developed by R-2. DMRC has coordinated with various agencies including GNCTD, MTNL, Ministry of Telecom, etc. in creating a road of equal width immediately adjacent to the current road being used by R-2 and/or residents etc. for access to R-2‟s area. DMRC had to shift the telephone tower as well as toilets, etc. to secure this additional access, which as per the photographs filed looks as under:
53. DMRC is a state entity. According to the court, the arrangement by DMRC is fair and just both to R-2 as well as the petitioner. The latter‟s rights were created earlier in time, therefore, the petitioner‟s right to service access from Timarpur Road has to be secured and due arrangement for the same has been made by DMRC. In view of the above, DMRC is directed to ensure that petitioner has unhindered service access to its „Island Plot‟ from Timarpur Road in terms of the service access as depicted in and represented to the petitioner in the Tender Notice dated 15-12-2002 as well as in terms of clause 4.3.[1] of the Agreement. It will be open to R-2 to create and appropriate for itself an exclusive access of equal width from Timarpur Road for its residential area, as proposed by DMRC. The latter has already cleared the path and laid the road for R-2, as noted hereinabove.
54. The petition is allowed and disposed-off in terms of the above. Pending applications, if any, stand also disposed-off.