Full Text
HIGH COURT OF DELHI
Date of Decision: July 04, 2023
UNION OF INDIA..... Appellant
Through: Mr. Sushil Kumar Pandey, Advocate.
Through: Ms. Anusuya Salwan, Mr. Bankim Garg, Ms. Simran Sakuria, Mr. Rachit Wadhwa, Ms. Sopika Singh and Ms. Nitika Salwan, Advocate.
HON'BLE MR. JUSTICE ANOOP KUMAR MENDIRATTA V. KAMESWAR RAO (Oral)
Exemption allowed, subject to all just exceptions.
Application stands disposed of.
JUDGMENT
1. The challenge in this appeal under Section 37 of the Arbitration and Conciliation Act, 1996 is to an order dated February 22, 2023 passed by the learned Single Judge in O.M.P. (COMM.) 335/2022 whereby the learned Single Judge has set aside the arbitral award dated March 12, 2022 to the extent of findings of the learned Arbitrator qua claim No. 6, which is a claim made by the respondent for granting the benefit of bonus because the delay in completing the work was attributable to the appellant herein. The relevant findings of the learned Single Judge in this regard are in paragraphs 24 to 33 24, 26, 27 & 28 of the impugned order which read as under:-
28. Further, the observation in Paragon Constructions (India) Pvt. Ltd. (Supra) is also found relevant to be referred to pertaining to the question before this Court:-
8. Claim Nos 3 and 4 pertain to interest and costs of proceedings and conclusion in respect of that would also follow suit. The award is, therefore, set aside and the parties are directed to go in for arbitration afresh, For this purpose, in terms of clause 25 of the agreement between the parties, the Chief Engineer CPWD incharge of the works or if there be no Chief Engineer, the Administrative head of CPWD shall appoint another sole arbitrator to adjudicate the disputes between the parties. The said appointment be made within a period of four weeks.
29. Therefore, the analysis given by the Arbitrator is not substantiated by the single-sentenced assertion. The Arbitrator merely made a presumption and decided that the petitioner was not entitled to the bonus/incentive.
30. Reason is the soul of justice. As discussed in the foregoing paragraphs, one of the essential requirements while making an Award is furnishing reasons for the decision taken. While passing the Award with respect to Claim No. 6, the Arbitrator failed to furnish any reason for holding that the petitioner was not entitled to the bonus/incentives.
31. The learned Arbitrator need not have given elaborate, comprehensive or extensive decision regarding Claim No. 6 but the mere recording of reasons for the findings made was an· indispensable requirement to be met. Fulfilling the requirements under Section 31 (3) of the Arbitration Act, is not a mere formality, but this provision makes way for a fair, reasonable and equitable opportunity to have the objective knowledge of the reasons why a claim is not decided in their favour. Accordingly, this Court finds that the principles laid down by the Hon'ble Supreme Court favour the case of the petitioner qua the requirement of passing a reasoned order being indispensable.
32. In light of the facts, circumstances, contentions raised in the pleadings, argument made on behalf of the 'parties, the observations of the Hon'ble Supreme Court, the provisions, of the Arbitration Act and the discussion in the foregoing paragraphs, ·this Court finds merit in the petition and is inclined to allow the, same.
33. Accordingly, the instant petition is allowed and the Arbitral Award dated 12th March 2022 is set aside to the extent of the finding of the Arbitrator qua Claim No. 6.”
2. The submission of Mr. Sushil Kumar Pandey, learned counsel for the appellant is by drawing our attention to page 696 of the paper book to contend that the learned Arbitrator has categorically held that no one party to the agreement was at fault in causing the delay in executing the contract. He states, the learned Single Judge could not have interfered with such findings particularly in view of the provisions of Section 34 (2) of the Arbitration and Conciliation Act, 1996. In this regard, he has drawn our attention to grounds ‘B’ & ‘C’ of the appeal.
3. We are not in agreement with the submission made by Mr. Pandey which is by overlooking the conclusive finding of the learned Arbitrator in paragraph 8.2.6.11 page 697 which is reproduced as under:- “8.2.6.11.. Having regard to relevant facts as discussed above, I am of view that respondent has committed a serious breach which is of the most fundamental nature and which goes to very root of contract. Thus, the respondent is entirely responsible for the prolongation of contract.”
4. On a perusal of the conclusion, it is clear that the learned Arbitrator has held that it is the respondent, that is the appellant herein who is entirely responsible for prolongation of the contract. If that be so, the reliance placed by Mr. Pandey is clearly untenable/misplaced.
5. In this background, the learned Single Judge has in paragraph 26 held that given such a finding, the learned Arbitrator should have elaborated on the claim made by the respondent herein with regard to bonus and incentive. In fact, the learned Single Judge has relied upon the judgment of a Coordinate Division Bench of this Court in Union of India Vs. M/s N.N. Buildcon Pvt. Ltd. 2015 SCC OnLine Del 11647, more particularly in paragraph 3 which also relates to the claim of bonus because of the delay in completion of work. The finding of the learned Single Judge is that the analysis given by the learned Arbitrator has not been substantiated. According to the learned Single Judge, the Arbitrator has merely made a presumption and decided that the respondent herein was not entitled to bonus and incentive without furnishing any reason. It is in the above background that the learned Single Judge has set aside the award drawn by the learned Arbitrator, in respect of claim No. 6 with which we agree.
6. The appeal is accordingly dismissed. No costs.
V. KAMESWAR RAO, J
ANOOP KUMAR MENDIRATTA, J JULY 4, 2023