Full Text
Date of Decision: 20.07.2023
GANNON DUNKERLEY AND COMPANY LTD ..... Appellant
Through: Mr. Arjun Syal & Mr. Rohit Kumar, Advs.
Through:
HON'BLE MR. JUSTICE AMIT MAHAJAN VIBHU BAKHRU, J.
JUDGMENT
1. The appellant (hereafter ‘Gannon’) has filed the present intracourt appeal impugning an order dated 05.06.2023 passed by the learned Single Judge, whereby the petition filed by Gannon under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter ‘the A&C Act’) being OMP (I) COMM. No.193/2023 was rejected.
2. Gannon had filed the aforesaid petition, inter alia, praying for directions restraining the respondent No. 1 (hereafter ‘Doosan Power’) from invoking, encashing or taking any coercive steps in respect of the Performance Bank Guarantee being Bank Guarantee No.003GM07180750006 dated 16.03.2018 for an amount of RAWAL ₹5,55,15,625/- (hereafter referred as ‘the PBG’) issued by respondent no.2 (hereafter ‘Yes Bank’).
3. Gannon had furnished the PBG in connection with a sub-contract agreement for civil, structural and architectural works including Power Block Building, GIS Building and BOP Building which is a part of the 2x660MW Super Critical Thermal Power Station being developed by Doosan Power at Jawaharpur on Engineering, Procurement, Construction (EPC) basis. The contract between Gannon and Doosan Power is hereafter referred to as the Contract.
4. It is Gannon’s case that it had fulfilled its obligations and mobilized the manpower and resources as required for performing the Contract but Doosan Power had failed to fulfil its reciprocal obligations in handing over the encumbrance-free site within time. Admittedly, there were delays in execution of the contract. It is the Gannon’s case that that same was for reasons attributable to Doosan Power including delay in handing over site; delay in release of drawings and the approval of designs; and frequent changes of drawings. Doosan Power disputes the same.
5. It is material to note that it is not Gannon’s case that there has been any egregious fraud which vitiates the Contract entered with Doosan Power. It is also apparent that the disputes between the parties essentially relate to execution of the performance of obligations under the Contract.
6. The PBG submitted by Gannon is an unconditional one. The law RAWAL relating to interdicting unconditional bank guarantees is now well settled.
7. In Svenska Handelsbanken v. M/s Indian Charge Chrome & Ors. (1994) 1 SCC 502, the Supreme Court held as under:- “...in case of confirmed bank guarantees/ irrevocable letters of credit, it cannot be interfered with unless there is fraud and irretrievable injustice involved in the case and fraud has to be an established fraud... …irretrievable injustice which was made the basis for grant of injunction really was on the ground that the guarantee was not encashable on its terms…...there should be prima facie case of fraud and special equities in the form of preventing irretrievable injustice between the parties. Mere irretrievable injustice without prima facie case of established fraud is of no consequence in restraining the encashment of bank guarantee.””
8. In Larsen & Tourbo Limited v. Maharashtra State Electricity Board & Others: (1995) 6 SCC 68, the Supreme Court observed as under:-
9. In Himadari Chemicals Industries Ltd. v. Coal Tar Refining Company: 2007 (8) SCC 110, the Supreme Court referred to the earlier decisions and summarized the principles regarding interdiction of a bank guarantee as under: “14. From the discussions made hereinabove relating to the principles for grant or refusal to grant of injunction to restrain enforcement of a Bank Guarantee or a Letter of Credit, we find that the following principles should be noted in the matter of injunction to restrain the encashment of a Bank Guarantee or a Letter of Credit:- RAWAL
(i) While dealing with an application for injunction in the course of commercial dealings, and when an unconditional Bank Guarantee or Letter of Credit is given or accepted, the Beneficiary is entitled to realize such a Bank Guarantee or a Letter of Credit in terms thereof irrespective of any pending disputes relating to the terms of the contract.
(ii) The Bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer.
(iii) The Courts should be slow in granting an order of injunction to restrain the realization of a Bank Guarantee or a Letter of Credit.
(iv) Since a Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, the existence of any dispute between the parties to the contract is not a ground for issuing an order of injunction to restrain enforcement of Bank Guarantees or Letters of Credit.
(v) Fraud of an egregious nature which would vitiate the very foundation of such a Bank Guarantee or Letter of Credit and the beneficiary seeks to take advantage of the situation.
(vi) Allowing encashment of an unconditional Bank
10. In Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering Works (P) Ltd. & Anr.: AIR 1997 SC 2477, the Supreme Court held as under: RAWAL
11. In BSES Ltd. v Fenner India Ltd.: 2006 2 SCC 728, the Supreme Court reiterated the law relating to interdiction of unconditional bank guarantees in the following words:
12. In view of the settled law, the relief as sought by Gannon cannot be granted. The case set up Gannon is neither of an egregious fraud nor of any irretrievable harm or injustice.
13. In our view, the learned Single Judge has rightly rejected the petition under Section 9 for seeking interdiction of the PBG.
14. The present appeal is unmerited and accordingly dismissed.
VIBHU BAKHRU, J AMIT MAHAJAN, J JULY 20, 2023 RAWAL