Full Text
HIGH COURT OF DELHI
FAO(OS) (COMM) 27/2021 & C.M.No.6354/2021
NATIONAL HIGHWAYS AUTHORITY OF INDIA ..... Appellant
Through: Ms.Neetica Sharma, Advocate.
Through: Mr.Raghvendra M. Bajaj with Ms.Yashika Sarvaria and Mr.Samaj
Aggarwal, Advocates for R-1/PNB.
Mr.Samar Singh Kachwaha with Ms.Tara Shahani, Ms.Akanksha
Mohan and Ms.Aanya Saluja, Advocates for R-2.
Date of Decision: 10th August, 2023
HON'BLE MS. JUSTICE MINI PUSHKARNA
JUDGMENT
1. Present appeal has been filed, by the appellant-National Highway Authority of India (in short ‘NHAI’), seeking to set aside the judgment and order dated 04th January, 2021 passed by a learned Single Judge of this Court in OMP (COMM) No.442/2020, whereby the Appellant’s petition under Section 34 of the Arbitration and Conciliation Act, 1996 (for short ‘Act, 1996’) challenging the second Arbitral Award dated 24th March, 2020 was dismissed.
2. Learned counsel for the appellant-NHAI submits that the Arbitral Tribunal in the impugned award has ‘wandered outside the relief sought’ and dealt with the matters pending in the first arbitration inter se between the parties, which amounts to a patent illegality.
3. She further submits that the learned Single Judge has erred in holding that pendency of the first arbitration award would have no bearing on the issue of bank guarantee as the said bank guarantee was never furnished by the concessionaire / Jetpur Somnath Tollways Pvt. Ltd. (‘JSTPL’) to secure the claim of the appellant-NHAI. She contends that there is a clear finding to this effect by another learned Single Judge of this Court in an earlier proceeding filed under Section 9 of the Act, 1996. The relevant portion of the order passed in the earlier petition filed under Section 9 of the Act, 1996 by the learned Single Judge is reproduced hereinbelow:- “106. In view of the above:
(i) JETPUR is directed to furnish an unconditional and irrevocable
Bank Guarantee, in favour of NHAI, undertaking to pay to NHAI an amount not exceeding Rs.348.604 Crores [i.e. 90% of 640.86 = 576.774 (minus) 222.03 {already paid} (minus) 6.14 {agreed to be payable by NHAI} = 348.604]; and
(ii) On deposit of the Bank Guarantee, NHAI shall forthwith OMP
(iii) The encashment of the Bank Guarantee shall be subject to the final award of the Arbitral Tribunal; and
(iv) JETPUR shall keep the bank guarantee alive for upto a period of four months after the making of the final award by the Arbitration Tribunal; and
(v) Parties shall comply with the provisions of Section 9(2) of the Act”
4. She also challenges the directions given by the Arbitral Tribunal to pay pendent lite and future interest @ 9 per cent (simple interest) per annum on the ground that the appellant-NHAI had made the payment in accordance with the order of the Supreme Court dated 05th January, 2018, which had directed the appellant-NHAI to pay a sum of Rs.348.604 crore within a period of six months. She contends that as the appellant-NHAI had made the payment on 29th January, 2018 i.e. within the prescribed time period of six months, the award of interest by the Arbitral Tribunal was patently illegal.
5. Having perused the paper book, this Court finds that both the Arbitral Tribunal as well as the learned Single Judge have rejected the aforesaid submissions advanced by the learned counsel for appellant-NHAI. The relevant portions of the Arbitral Award and the order passed by the learned Single Judge are reproduced hereinbelow:-
(i) The findings by the High Court with regard to encashment of bank guarantee is affirmed. ……
(iv) The amount shall be kept in the Escrow Account as directed by the High Court
(C) With regard to the later part of the aforesaid issue of consequential reliefs and Respondent No.2’s prayer made vide its submission dt. 09.01.2019, there appears to be no reason, in view of the AT’s decision in respect of the first part of the issue, to keep the aforesaid BG by the Respondent No.1 or to keep the same alive by the Respondent No.2 beyond a period of 4 months after making the final award by AT (refer para 106(iv) of Hon’ble High Court’s order dt. 31.07.2017 – Ann C-46, pg. 2445-2480 of CD-11) 68.[7] Issue as framed by AT in its order dt. 01.07.2019 is decided accordingly. 68.[8] The claim is decided in favour of the Claimant and as against the Respondent No.1. The Claimant is entitled and the Respondent No.1 is liable to pay 90% of Debt Due amount towards termination payment. In view of this award, there appears to be no reason to keep the aforesaid BG by the Respondent No.1 or to keep the BG alive by the Respondent No.2…. xxx xxx xxx 76.[3] In this case, the details of Debt Due were furnished by the Claimant to the Respondent No.1 on 16.11.2016. As such, the Claimant has noted the date of cause of action as 17.11.2016. However, the Claimant’s claim for payment of interest on the 100 % Debt Due cannot be entertained as the Claimant in its claim no.(a) itself has prayed for the award of 100 % Debt Due depending on the outcome of another Arbitration. The Claimant, in the legal notice dt.20.04.2017[4] (Ann. C-40, pg.974-980 of CD-4) had also claimed interest on the sum of 90% Debt Due and that too @9.75% only. Thus, award of interest on the amount of 90 % Debt Due i.e. Rs. 576.77 crs. only can be allowed for the pre-date-of-award period. AT is of the opinion that award of interest @9 % p.a. simple shall meet the ends of justice. AT accordingly awards interest for pre-date-of-award period from 05.12.2016 to the date of award @9% p.a. simple only as below.
77 With regard to post-award period, Sec.31(7)(b) of the Act, 1996 provides that unless the award otherwise directs the sum directed to be paid by an arbitral award shall carry interest @2% p.a. higher than the current rate of interest prevalent on the date of award for the period from the date of the award to the date of payment. The Claimant has claimed this interest @18% p.a. However, this interest has to be granted keeping in view the aforesaid statutory provision. These days the current rate of interest is around @7% p.a. on bank deposits accordingly, AT holds that the Claimant is entitled for the grant of future interest @9% p.a. simple in accordance with amended section 31(7)(b) of the Act. Accordingly, AT awards interest on the aforesaid amount of Rs.42.96 Cr @9% p.a. (simple) for the period from the date of award till the date of actual payment to the Claimant. This amount of interest for post-award period shall be paid in addition to the aforesaid total sum of Rs.42.96 Cr.”
6. It is settled law that once an Arbitral Award has been confirmed in an application filed under Section 34 of the Act, 1996 the appellate Court must be extremely cautious in disturbing concurrent findings of the fact and law as they are ordinarily not amenable to interference under Section 37 of the Act, 1996 (See: Mangalwar Filing Station vs. Indian Oil Corporation Limited & Ors., 2021 SCC OnLine Del 3646, MMTC Ltd. vs. Vedanta Ltd., (2019) 4 SCC 163).
7. Consequently, the scope of interference in an appeal under Section 37 of the Act, 1996 is extremely limited.
8. In any event, this Court is of the view that the Arbitral Tribunal in the present case has neither ‘wandered outside the relief sought for’ nor dealt with the matters pending in the first arbitration.
9. From what has been placed on record, it is apparent that the matter in issue in the first arbitration inter se between the parties is whether the termination of the contract was on account of default of the appellant-NHAI and if so, whether the concessionaire / respondent no.2 is entitled to compensation and damages. Needless to state that it is the appellant-NHAI’s case that the termination was not on account of its default but on account of concessionaire’s / respondent no.2’s default. Though the Arbitral Tribunal in the first award has held that the termination was on account of default of the appellant-NHAI, yet even if the petition filed by the appellant-NHAI under Section 34 of the Act, 1996 were to be allowed, then also the present award would not be interfered with, as according to Clause 37.3.[1] even if the termination takes place on account of concessionaire’s default, the appellant-NHAI has to pay an amount equivalent to 90% of the debt due less insurance cover to the Punjab National Bank (in short ‘PNB’).
10. Further, the appellant-NHAI’s reliance on the order passed by the learned Single Judge as well as by the Apex Court under Section 9 of the Act, 1996 proceedings is misconceived, as the Arbitral Tribunal has rightly pointed out that furnishing of the bank guarantee was subject to the final award to be passed.
11. It is also pertinent to mention that the scope of Section 9 petition is quite different at the pre-award stage from the post-award stage. While under Section 9 (i) of the Act, 1996 the intent of the proceeding is to safeguard the subject matter of the dispute in the course of arbitral proceedings, under Section 9 (ii) (after an award is made) the intent is to protect / secure the property / goods for the benefit of the parties which seeks enforcement as it is a step in aid of enforcement. (See: Dirk India Private Limited vs. Maharashtra State Electricity Generation Company Limited, 2013 SCC OnLine Bom 481, Nussli Switzerland Ltd. vs. Organizing Committee Commonwealth Games, 2014 SCC OnLine Del 4834).
12. Consequently, even if the appellant-NHAI were to succeed in the first arbitration proceedings inter se between the parties, then also the amount awarded in the impugned award would have to be paid by the appellant- NHAI to PNB.
13. As far as the award of interest is concerned, this Court finds that the Arbitral Tribunal has awarded interest @ 9% per annum being 2% above the prevalent ordinary rate of interest on the date of passing of the impugned arbitral award. Accordingly, the said direction is in consonance with the provisions contained in Act, 1996.
14. Consequently, the present appeal being bereft of merit is dismissed along with pending application and the interim order dated 26th August, 2021 is vacated. MANMOHAN, J MINI PUSHKARNA, J AUGUST 10, 2023 KA/AS