Full Text
HIGH COURT OF DELHI
Date of Decision: 21.08.2023
PELE KHEZHIE ..... Petitioner
Through: Ms. Amrita Panda and Mr. Aditya Kumar, Advs.
Through: Ms. Rajdipa Behura, Mr. Philomon Kani, Mr. Ashray Behura, Ms. Neha Dobriyal, Ms. Hansika Sahu, Mr. Ashutosh Namdev and Mr. Ashok Kumar Jha, Advs.
PELE KHEZHIE ..... Petitioner
Through: Ms. Amrita Panda and Mr. Aditya Kumar, Advs.
Through: Ms. Rajdipa Behura, Mr. Philomon Kani, Mr. Ashray Behura, Ms. Neha Dobriyal, Ms. Hansika Sahu, Mr. Ashutosh Namdev and Mr. Ashok Kumar Jha, Advs.
JUDGMENT
1. The present petition under Section 11 of the Arbitration and Conciliation Act 1996 (the “A&C Act”) seeks appointment of an independent sole arbitrator to adjudicate the dispute between the parties.
2. The disputes between the parties have arisen in the context of a tender process initiated by the respondent for ―Construction of two lane with paved shoulder of Kohima-Bypass Road connecting NH-39 (New NH-02), NH-150 (New NH-02), NH-61 (New NH- 29) and NH-39 (New NH-02) from Design Km 32.00 to design Km 43.454 [Design Length – 11.454 Km] in the state of Nagaland under SARDP-NE on EPC Mode (Package IV).‖ The bid submitted by the petitioner for the said tender was accepted by the respondent vide Letter of Acceptance dated 14.08.2020. Accordingly, the petitioner and the respondent entered into the Engineering, Procurement and Construction Contract dated 05.09.2020.
3. The stipulated date for completion of the work was 18 months from the appointed date. For slow progress of work and non-completion of milestones by the petitioner, the respondent, vide letter 07.03.2023, declared the petitioner a Non-Performer. Further, vide letter dated 17.04.2023, the respondent sought to levy liquidated damages on the petitioner, and vide letter dated 22.05.2023 issued notice of intention to terminate the Contract. The petitioner contends that the sole reason the progress of work was slow and the milestones were not achieved, was the non-provision of the „Right of Way‟ by the respondent as per its contractual obligations.
4. A petition under Section 9 of the A&C Act has also been filed by the petitioner seeking stay of the respondent‟s letter dated 07.03.2023, restraining the respondent from taking any coercive or precipitative action on the basis of the letter dated 22.05.2023 and seeking status quo in relation to the Performance Bank Guarantees.
5. The Contract Agreement contains a dispute resolution clause in the following terms: ― Article 26 Dispute Resolution 26.[1] Dispute Resolution
(i) Any dispute, difference or controversy of whatever nature howsoever arising under or out of or in relation to this Agreement (including its interpretation) between the Parties, and so notified in writing by either Party to the other Party (the "Dispute‖) shall, in the first instance, be attempted to be resolved amicably in accordance with the conciliation procedure set forth in Clause 26.2.
(ii) The Parties agree to use their best efforts for resolving all Disputes arising under or in respect of this Agreement promptly, equitably and in good faith, and further agree to provide each other with reasonable access during normal business hours to all nonprivileged records, information and data pertaining to any Dispute. 26.[2] Conciliation In the event of any Dispute between the Parties, either Party may call upon the Authority’s Engineer, or such other person as the Parties may mutually agree upon (the "Conciliator") to mediate and assist the Parties in arriving at an amicable settlement thereof. Failing mediation by the Conciliator or without the intervention of the Conciliator, either Party may require such Dispute to be referred to the Chairman of the Authority and the Chairman of the Board of Directors of the Contractor for amicable settlement, and upon such reference, the said persons shall meet no later than 7 (seven) business days from the date of reference to discuss and attempt to amicably resolve the Dispute. If such meeting does not take place within the 30 (thirty) business day period or the Dispute is not amicably settled within 30 (thirty) days of the meeting or the Dispute is not resolved as evidenced by the signing of written terms of settlement within 30 (thirty) days of the notice in writing referred to in Clause 26.1.[1] or such longer period as may be mutually agreed by the Parties, either Party may refer the Dispute to arbitration in accordance with the provisions of Clause 26.[3] but before resorting to such arbitration, the parties agree to explore conciliation by the Conciliation Committees of Independent Experts set up by the Authority in accordance with the procedure decided by the panel of such experts and notified by the Authority on its website including its subsequent amendments. In the event of the conciliation proceedings being successful, the parties to the dispute would sign the written settlement agreement and the conciliators would authenticate the same. Such settlement agreement would then be binding on the parties in terms of Section 73 of the Arbitration Act. In case of failure of the conciliation process even at the level of the Conciliation Committee, either party may refer the Dispute to arbitration in accordance with the provisions of Clause 26.3. 26.[3] Arbitration
(i) Any dispute which remains unresolved between the parties through the mechanisms available/ prescribed in the Agreement, irrespective of any claim value, which has not been agreed upon/ reached settlement by the parties, will be referred to the Arbitral Tribunal as per the Arbitration and Conciliation Act.
(ii) Deleted
(ill) The Arbitral Tribunal shall make a reasoned award (the "Award").
Any Award made in any arbitration held pursuant to this Article 26 shall be final and binding on the Parties as from the date it is made, and the Contractor and the Authority agree and undertake to carry out such Award without delay.
(iv) The Contractor and the Authority agree that an Award may be enforced against the Contractor and/or the Authority, as the case may be, and their respective assets wherever situated.
(v) This Agreement and the rights and obligations of the Parties shall remain in full force and effect, pending the Award in any arbitration proceedings hereunder. Further, the parties unconditionally acknowledge and agree that notwithstanding any dispute between them, each Party shall proceed with the performance of its respective obligations, pending resolution of Dispute in accordance with this Article.
(vi) In the event the Party against whom the Award has been granted challenges the Award for any reason in a court of law, it shall make an interim payment to the other Party for an amount equal to 75% (seventy five per cent) of the Award, pending final settlement of the Dispute. The aforesaid amount shall be paid forthwith upon furnishing an irrevocable Bank Guarantee for a sum equal to 120 % (one hundred and twenty per cent) of the aforesaid amount. Upon final settlement of the Dispute, the aforesaid interim payment shall be adjusted and any balance amount due to be paid or returned, as the case may be, shall be paid or returned with interest calculated at the rate of 10% (ten per cent) per annum from the date of interim payment to the date of final settlement of such balance.‖
6. The petitioner invoked the aforesaid arbitration clause vide letter dated 24.07.2023. However, no reply thereto was sent by the respondent.
7. Learned counsel for the respondent does not dispute the existence of the arbitration agreement between the parties. However, she submits that the present petition is premature on two counts (i) before resorting to arbitration, the petitioner has not taken recourse to conciliation as contemplated under Article 26.[2] of the Contract; it is submitted that use of the word “shall” in Article 26.[1] of the Contract clearly demonstrates that referring the disputes to conciliation is mandatory prior to invocation of arbitration and (ii) no disputes have arisen between the parties as the respondent has only issued a notice of intention to terminate and has not yet terminated the contract.
8. Per contra, the learned counsel for the petitioner submitted that the process of conciliation as contemplated in Article 26.[2] is directory in nature. She further submits that disputes have arisen between the parties and the same is evident from the fact that the respondent has issued a notice of intention to terminate dated 22.05.2023; the subsistence of serious disputes is further evident from the letters of the respondent wherein it had declared the petitioner as a „non-performer‟ and has sought to impose liquidated damages on the petitioner.
9. Having perused the record and having heard learned counsel for the parties, I am unable to agree with the objections raised by learned counsel for the respondent.
10. In the context of a similar arbitration clause, this Court in Ranjit Construction Co. v. Gujarat State Road & Building Department[1] considered the judgments in the case of Oasis Projects Ltd. v. National Highway & Infrastructure Development Corpn. Ltd.2, Kunwar Narayana v. Ozone Overseas Pvt. Ltd.3, Demarara Distilleries Pvt. Ltd. v. Demerara Distilleries Ltd.4, Ravindra Kumar Verma v. BPTP Ltd[5] and Subhash Infraengineers (P) Ltd. v. NTPC Ltd.6, has held as under:-