Full Text
CIVIL APPEAL NO.1805/2021
MAHARASHTRA STATE ELECTRICITY
DISTRIBUTION COMPANY LIMITED APPELLANT(S)
& ANR. RESPONDENT(S)
JUDGMENT
1. This appeal challenges the order passed by the Appellate Tribunal for Electricity dated 13.11.2020. The operative part of the order reads thus:-
2. Shri Balbir Singh, learned Additional Solicitor General of India (‘ASG” for short) appearing on behalf of the Distribution Company (“DISCOM” for short), submits that though the respondent gets a specific quantity for a particular month out of the Annual Contracted Quantity (ACQ), in the event the same is not utilized for a particular month, it is not carried forward to the next month, thereby giving undue benefit to the generator.
3. Shri Sajan Poovayya, learned Senior Counsel and Mr. Vishrov Mukerjee, learned counsel appearing on behalf of the Generator submit that the said apprehension is totally misconceived as could be seen from the impugned judgment.
4. We find that the apprehension is not well merited. Insofar as direction No.1 is concerned, the same is in tune with the view taken by us in Maharashtra State Electricity Distribution Company Ltd. v. Adani Power Maharashtra Limited and Others[1]. Insofar as, direction No.2 is concerned, the same is also covered by the judgment of this Court in Adani Power Maharashtra Limited (supra) following the law laid down in Energy Watchdog v. Central Electricity Regulatory Commission and Others[2].
5. Insofar as the apprehension with regard to unutilized coal quantity for a particular month being not carried forward to the next month is concerned, the same is also without substance. In this respect, it will be relevant to reproduce paragraph 43 of the impugned judgment, wherein the learned Tribunal has recorded the submission of the respondent/generator, which is extracted below:-
6. The chart itself would show that for the month of February the coal assured was 850 MW, the coal delivered was 800 MW and the actual generation was 700 MW. As such, for the said month the generator had surplus coal for production of 100 MW energy. The same has been carried forward for the month of March. It is clear from the chart that though for the month of March the assured coal was 850 MW, the actual coal delivered was only 600 MW and the generation was 750 MW. If the apprehension of the learned ASG was to be of substance, then the generator could have claimed a shortfall of 150 MW, however, the surplus coal of 100 MW from the month of February has been carried forward and the shortfall claimed is only 50 MW.
7. If this methodology is adopted by the generator, we do not find that the apprehension of the learned Additional Solicitor General of India would be substantiated.
8. The appeal is, accordingly, disposed of.
9. Pending application(s), if any, shall stand disposed of...............................J (B.R. GAVAI)..............................J (VIKRAM NATH) NEW DELHI; MARCH 27, 2023