Full Text
HIGH COURT OF DELHI
JUDGMENT
STEEL AUTHORITY OF INDIA LTD ..... Petitioner
Through: Mr. Saurabh Seth, Ms. Sonia Dube, Ms. Kanchan Yadav and Ms. Saumya Sharma, Advs.
Through: Mr. Amit Agarwal, Mr. Shwetabh Sinha, Mr. Sidhant Pandita & Ms. Vatsala Pandey, Advs.
1. The present petition under Section 27 of the Arbitration and Conciliation Act, 1996 (the „A&C Act‟) has been filed on behalf of the petitioner seeking the following reliefs: “a) The person described in paragraph 14 above be directed to appear before the Arbitral Tribunal and adduce evidence directly before the Hon'ble Arbitral Tribunal of the Indian Council of Arbitration; (b) The Department of this Hon'ble Court be directed to issue appropriate notice and summons to the person named and described in paragraph 14 hereinabove to adduce evidence as witness before the Hon'ble Arbitral Tribunal of the Indian Council of Arbitration on the issues framed by the Arbitral Tribunal;”
2. Briefly stated, the facts are that the petitioner had chartered a vessel by the name „MV PEACE GEM‟ for the carriage of the petitioner's cargo from the port of DTA Terminal New Port News, on the East Coast of the United States of America to the destination ports of Vizag (Visakhapatnam) and Haldia in India. The respondent is purportedly the owner of the said Vessel. Disputes having arisen between the parties, the respondent (claimant in the arbitration) has made a reference to Arbitration under the Rules of the Indian Council of Arbitration, New Delhi, in accordance with the relevant terms of the subject Charter Party Agreement.
3. The respondent has a monetary claim against the petitioner on account of alleged demurrage for the said Vessel while the Vessel was at Haldia Port, India, between 07.05.2019 and 20.05.2019. The petitioner in the arbitration has denied this claim on the ground, inter-alia, that the said Vessel was suffering from infrastructural damages and was unfit to be called to berth, inasmuch as the River Pilots of the Haldia Dock Complex had refused to board the said Vessel until 20.05.2019 on account of the pilot ladder on the starboard side of the Vessel having been damaged and rendered non-functional and unserviceable.
4. On the said aspect, one of the issues framed by the Arbitral Tribunal is as under: “5. Whether the vessel can berth and also discharge goods with a damaged starboard combined pilot ladder?”
5. It is averred in the petition that the concerned officer of the Kolkata Port Trust had issued an e-mail to the petitioner on 19.05.2022, confirming that the River Pilots had refused to board the said Vessel when the Vessel was called to berth, on the ground that the combined pilot ladder on the starboard-side of the Vessel was not functional and therefore the Vessel was not capable of being boarded.
6. An application was filed by the petitioner before the Arbitral Tribunal, seeking its approval for moving the court for seeking the court‟s assistance for taking evidence of the concerned officer of the Kolkata Port Trust. Vide order dated 13.04.2023, the Arbitral Tribunal allowed the said application, as under: “ORDER The Respondent had filed an Application dated 27.03.2023 (“the Application”) in the hearing held on 27.03.2023 seeking approval/permission of the Tribunal under Section 27 of the Arbitration and Conciliation Act, 1996 for producing a witness from S P Mookerjee Port, Kolkata for deposing in the present proceedings in respect of vessel MV Peace Gem more particularly, in respect of the damaged pilot combination ladder on her starboard site at that time of her call for berthing at Haldia Dock Complex in May, 2019. The Claimant has filed a Reply dated 03.04.2023 praying for rejection of this application on the grounds stated therein. Having deliberated upon and considered the Application and the Reply thereto, the Tribunal is of the considered view that the role of the Tribunal under Section 27 of the Arbitration & Conciliation Act, 1996 is limited and at this stage, Tribunal is not required to go into relevance or materially of the evidence sought to be produced. Both the parties in arbitration proceedings are to be given full opportunity to present their case. In the last hearing held on 27.03.2023 and 28.03.2023, it was agreed by the parties that the Respondent in the meantime will produce its other witness(es) for which, dates are already fixed on 26th and 27th April, 2023. In view of the foregoing, the Application filed by the Respondent is allowed and permission is given to the Respondent to file the necessary application expeditiously in the appropriate court for its assistance in taking evidence from S P Mookerjee Port, Kolkata. Meanwhile the Respondent will produce its other witness(es) on April 26-27 dates already fixed. Ashok Sharma Presiding Arbitrator on behalf of the Tribunal”
7. The details of the person to be summoned as witness and description of documents to be produced, are described in paragraph 15 of the petition; the same is reproduced hereunder: Submissions of the Parties
8. Learned counsel for the petitioner has submitted that during the stage of Admission/Denial of documents in the subject arbitral proceedings, the respondent has denied the aforesaid e-mail dated 19.05.2022. It is submitted that the petitioner is not the author or issuer of the said email, and therefore cannot prove its contents or veracity. It is submitted that unless the witness of the Kolkata Port, who is an independent third party to the arbitration proceedings, is permitted to depose and get his testimony recorded and considered by the Arbitral Tribunal, the petitioner shall be gravely deprived of valuable legal rights, and its bona fide defence in the subject arbitral proceedings. It is submitted that perusal of the order dated 13.04.2023 clearly shows application of mind and prima facie examination of the matter by the Arbitral Tribunal from the following words in the said order – “Both the parties in arbitration proceedings are to be given full opportunity to present their case”. It is submitted that the Arbitral Tribunal was not required to give elaborate reasons before allowing the application filed under Section 27 of the A&C Act. It is also submitted that the Arbitral Tribunal by virtue of Section 19 of the A&C Act was entitled to conduct the proceedings in a manner it considered appropriate, and thus deferring of the decision on relevance or materiality of the evidence sought to be produced by the petitioner was within the domain of the Arbitral Tribunal.
9. Per contra, learned counsel for the respondent has submitted that the Court is not to issue orders under Section 27 of the A&C Act where the Arbitral Tribunal has proceeded on a misconception of law, or where the Arbitral Tribunal‟s order exhibits a complete non-application of mind. It is submitted that the Arbitral Tribunal is required to pass a reasoned order (even if brief and prima facie) and cannot act mechanically. It is further submitted that, in any case, there is no material before the Court to determine the relevancy of the evidence requested by the petitioner. To determine whether a particular witness or material is relevant or simply an abuse of process, it is necessary to examine the pleadings of the parties and the material/evidence already available. None of this has been placed on record. It is also submitted that the email dated 19.05.2022 is completely irrelevant to the issue of whether the vessel can berth and discharge goods with a damaged starboard combined pilot ladder.
10. Learned counsel for the respondent has also submitted that the Court's power under Section 27 is discretionary, as evidenced by the use of the word “may” in the said provision. It is submitted that the Court should not exercise its discretion in favour of the petitioner in this case, given the petitioner's conduct in not even paying the arbitral fees and costs.
11. On the issue of payment of the arbitral fees and costs, learned counsel for the petitioner has submitted that Rule 21(3) of the Maritime Arbitration Rules of the Indian Council of Arbitration permits the petitioner to withhold said payments since the respondent has not filed any counterclaim in the arbitration proceedings. He has further submitted that the Arbitral Tribunal has taken note of this issue in its Minutes of Proceedings dated 27.10.2022, and has conclusively put this issue to rest. Additionally, learned counsel for the petitioner submitted that the payment of arbitration fees to the Arbitral Tribunal is outside the scope and domain of the present application under Section 27 of the A&C Act. Analysis and Findings
12. I have perused the record and heard learned counsel for the parties.
13. Ordinarily an order passed by the Arbitral Tribunal, granting permission to the applicant to apply to the Court for seeking assistance in taking evidence, is not liable to be disturbed since this Court while exercising powers under Section 27 of the A&C Act is not hearing an appeal over the decision of the Arbitral Tribunal. However, the order dated 13.04.2023 passed by the Arbitral Tribunal, in this case, granting permission to the petitioner to apply to this court for seeking its assistance in taking evidence, is a non-speaking order, based on a misconception of law that the Arbitral Tribunal is not required to examine, even prima-facie, into the relevancy or materiality of the evidence sought to be produced, before allowing the application under Section 27 of A&C Act filed by the petitioner.
14. The Arbitral Tribunal although not bound by the rules of procedure envisioned under Code of Civil Procedure, Evidence Act, and entitled to conduct the proceedings in the manner it considers appropriate, was still required to form an opinion/exercise discretion in permitting the witness to be examined by the petitioner. An application filed before the Arbitral Tribunal under Section 27 of the A&C Act cannot be allowed mechanically by the Arbitral Tribunal, it must scrutinize, at least on a prima facie basis, that there is relevancy of the witness sought to be produced. This Court in Hindustan Petroleum Corpn. Ltd. v. Ashok Kumar Garg, 2006 SCC OnLine Del 1056, has held as under:
15. The Court in Hindustan Petroleum (supra) further held as under:
16. This Court in Silor Associates v. Bharat Heavy Electrical Ltd., 2014 SCC OnLine Del 3407, approved by Division Bench in Bharat Heavy Electricals Ltd. v. Silor Associates, 2014 SCC OnLine Del 4442, has held as under:
17. Further, it is not for this Court for the first time to determine the relevancy or materiality of evidence sought to be produced by the petitioner. The powers of this Court under Section 27 are not adjudicatory powers when r/w Section 5 & Section 19 of the A&C Act. The adjudication has to be done by the Arbitral Tribunal, which is the chosen forum by the parties. This court in Thiess Iviinecs India v. NTPC Limited, 2016 SCC OnLine Del 1819, has held as under:
18. The Bombay High Court in Dilip v. Errol Moraes, 2022 SCC OnLine Bom 129, has held as under:
19. In view of the aforesaid, and particularly in view of the decision of this Court in Hindustan Petroleum (supra), the present petition is dismissed with a direction to the Arbitral Tribunal to consider, even if only on a prima facie conspectus, the relevancy or materiality of the evidence sought to be produced by the petitioner, before allowing the petitioner to approach this Court for seeking assistance in taking evidence.
20. The rival contentions of the parties with respect to non-payment of arbitral fees and costs by the petitioner cannot be made the subject matter of these proceeding under Section 27 of the A&C Act, at this stage.
SACHIN DATTA, J DECEMBER 01, 2023