Full Text
HIGH COURT OF DELHI
Date of Decision: -8th January, 2024.
12524/2023 NATIONAL RESEARCH DEVELOPMENT CORPORATION & ANR. ..... Petitioners
Through: Mr. Rama Shankar, Adv.
Through: Mr Balaji Subramanian, Adv. (M.
9958110162)
JUDGMENT
1. This hearing has been done through hybrid mode.
2. The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 has been filed by the Petitioners-National Research Development Corporation (hereinafter, ‘NRDC’) and the Department of Scientific and Industrial Research (hereinafter, ‘DSIR’) under the Ministry of Science and Technology, Government of India. NRDC is an enterprise of DSIR and is involved in the Technology Development and Demonstration Programme (hereinafter, ‘TDDP’).
3. The Respondent-company is engaged in manufacturing drugs and intermediates, established in 2006. Its director approached the Petitioners with a proposal to develop a rapid molecular diagnostics kit for malaria detection. A royalty agreement dated 18th October, 2011 was entered into between the Petitioners and the respondent, outlining the development of the malaria diagnostics kit, including design, standardization, validation, and expenses estimation. As per the said royalty agreement, the Respondent is also liable to transfer the ‘know-how document’ and other improvements if they fail to commercialize the technology within the specified timeframe. The Respondent is also obligated to pay interest and royalties as per the agreement. The relevant clauses of the said royalty agreement are as follows: “11.
UTILISATION OF TECHNOLOGY a. CBPL will enter into an agreement with NRDC within 120 days from the date of first sanction letter by DSIR under the "Project" to enable NRDC to collect lumpsum royally as mentioned in clause 4.1(f) and 4.1(g) above, and will pay to NRDC a lumpsum royalty on the sale of the "Product" as per clauses 4.1(f) and 4.1(g) of this Agreement. b. CBPL will have the right to utilize the technology developed or other IPRS generated through the "Project for production and sale of "Products on commercial basis. For such commercial utilization of technology by CBPL, CBPL will pay to NRDC, who will receive on behalf of DSIR, royalty/lumpsum premium as envisaged in clause 4.1(f) and/or 4.1(g) above. c. After commercialisation of technology by CBPL as stated in clause 11(b) above, CBPL may do third party licensing, if CBPL and DSIR perceive that such a need arises. This third-party licensing and related terms and conditions would be finalised by CBPL with the approval of DSIR. The revenue so generated by such third-party licensing shall be shared between CBPL and DSIR in the ratio of their actual financial contributions towards the project as assessed at the end of the project. d. CBPL may, if they so desire, utilise the services of NRDC for third party licensing as per mutually agreed terms and in consultation with DSIR. The revenue so collected by NRDC on behalf of DSIR by way of third party licensing shall be shared between CBPL and DSIR in ratio of their actual financial contributions towards the Project as assessed at the end of the Project. e. CBPL shall assign the technology proposed to be developed under this Project with right to license the intellectual property owned by them and transfer the know-how document to NRDC within 60 days from the occurrence of any of the following:
(i) If CBPL refuses to exercise its right, within one year of completion of the Project, its option to commercialise technology
(ii) If CBPL fails to commercialise technology within four years of completion of the project.
(iii) If fails to execute agreement referred to in clause 11(a) above.
NRDC will have an exclusive right to license the technology developed through the Project to third parties in case of occurrence of either of the events referred in clause 11(e) above. CBPL will provide to NRDC full details of any improvement(s) made on the Product(s) and the process of manufacture and any additional information, which NRDC may require to license this technology to third parties, in the event of third party licensing under the circumstances given in clause 11(e) above. In such cases, CBPL will also provide training to third party licensees on request from NRDC on mutually agreed terms. Revenues earned by NRDC through third party licensing under this clause will be shared in the ratio of actual financial for sale by CBPL Xxxxx
13.
TERMINATION OF THE PROJECT a. DSIR will have the right to terminate the Agreement based on recommendation of the Project Review Committee (PRC) at any stage, if it is satisfied that: • the moneys released have not been properly utilized, or • appropriate progress on the Project is not being made, or • the project is not being carried out as per the terms and conditions and/or as per the nature and scope of work as defined in the approved project proposal. b. DSIR will have the right to recover from CBPL at any time the moneys disbursed by DSIR for the Project along with 12% simple interest, if CBPL abandons the Project on its own without approval of DSIR or if the Project is terminated as above, c. If the Project is abandoned for any techno-economic and other reasons, other than the above, based on the recommendations of the Project Review, Committee and as directed by DSIR. CBPL shall pay back all unspent DSIR grants released for the Project and interest accrued thereon and any amounts recoverable by way of disposal of assets procured out of DSIR funds.
XXXXXX
15.
ARBITRATION AND JURISDICTION a) If any dispute or difference arises between the parties hereto as to the construction, interpretation, effect and implication of any provision of this Agreement including the rights or liabilities or any claim or demand of any Party (or its extent) against other party or its sub-contractor or in regard to any matter under these presents but excluding any matters, decisions or determination of which is expressly provided for in this Agreement such disputes or differences shall be referred to the sole arbitration of the Secretary of Department of Legal Affairs, Govt. of India or his nominee. A reference la the arbitration under this clause shall be deemed to be submission within the meaning of the Arbitration and Conciliation Act 1996 and any modification or re-enactment thereof and the rules framed there under for the Ume being in force. b) The venue of the Arbitration shall be at Delhi.
(ii) Each Party shall bear and pay its own cost of the arbitration proceedings unless the arbitrator otherwise decides in the award.
(iii) The provision of this clause shall not be frustrated, abrogated or become in-operative, notwithstanding this Agreement expires or ceases to exist or is terminated or revoked or declared c) The Courts at Delhi shall have exclusive jurisdiction in all matters containing this Agreement, including any matter related to or arising out of the arbitration proceedings or any award made therein.”
4. In the above background, the DSIR was informed by the Respondent that the project was completed on 17th October, 2014. Thereafter, the Respondent admitted in a letter dated 29th March, 2017 their inability to pay the royalty at that time, but made no efforts to return the technology developed under the project. Finally, vide communication dated 17th March, 2021, the Respondent offered to return the technology after seven years, which was declined by the Petitioners, leading to the constitution of the Arbitral Tribunal in December, 2021.
5. Vide order dated 23rd May, 2022, this Court appointed a sole arbitrator in the matter. The Award has been pronounced by the ld. Arbitrator on 10th December, 2022. The ld. Arbitrator held that the Claimants-NRDC are not entitled to any amount against the Respondent, either on account of royalty, damages, interest or cost as claimed by them in the SOC. Therefore, their claims were rejected by the ld. Arbitrator. The main findings of the said Award are extracted below:
6. An application has been filed seeking condonation of delay in filing the present petition. According to Section 34(3) of the Arbitration and Conciliation Act, 1996, the time period of ninety plus thirty days expired on 9th April, 2023.
7. An application being I.A. 12524/2023 has been filed seeking condonation of 54 days delay in refiling the present petition. The case of the Petitioner is that petition was filed on 2nd March, 2023 and was returned under objections on 4th March, 2023.
8. However, on behalf of the Respondent, it is submitted that the statement of truth itself was signed on 24th May, 2023. Thereafter, vakalatnama was executed on 2nd May, 2023.
9. Heard.
10. The Supreme Court in Union of India v. Popular Construction (2001) 8 SCC 470 observed that that the scheme of the Arbitration and Conciliation Act, 1996 lends credence to the conclusion that the time-limit prescribed under Section 34 of the Arbitration and Conciliation Act, 1996 is absolute. The relevant extract of the said judgment is as follows: “As for as the language of Section 34 of the 1996 Act is concerned, the crucial words are 'but not thereafter' used in the proviso to sub-section (3). In our opinion, this phrase would amount to an express exclusion within the meaning of Section 29(2) of the Limitation Act, and would therefore bar the application of Section 5 of that Act. Parliament did not need to go further. To hold that the Court could entertain an application to set aside the Award beyond the extended period under the proviso, would render the phrase 'but not thereafter' wholly otiose. No principle of interpretation would justify such a result. Apart from the language, 'express exclusion' may follow from the scheme and object of the special or local law. “Even in a case where the special law does not exclude the provisions of Sections 4 to 24 of the Limitation Act by an express reference, it would nonetheless be open to the Court to examine” Here the history and scheme of the 1996 Act support the conclusion that the time limit prescribed under Section 34 to challenge an Award is absolute and unextendable by Court under Section 5 of the Limitation Act. The Arbitration and Conciliation Bill, 1995 which preceded the 1996 Act stated as one of its main objectives the need "to minimise the supervisory role of courts in the arbitral process."
11. Further, in Simplex Infrastructure Ltd. v. Union of India (2019) 2 SCC 455, the Supreme Court held that the proviso to Section 34(3) of the Arbitration and Conciliation Act, 1996 allows the said period to be further extended by another period of thirty days on sufficient cause being shown by the party for filing an application. It observed that the intent of the legislature is evinced by the use of the words “but not thereafter” in the proviso. According to the Supreme Court, these words make it abundantly clear that as far as the limitation for filing an application for setting aside an arbitral award is concerned, the statutory period prescribed is three months which is extendable by another period of upto thirty days (and no more) subject to the satisfaction of the Court that sufficient reasons arere provided for the delay. The relevant portion of the said decision is as follows:
12. Further, in any case, while dealing with an application for condonation of delay in re-filing of a petition beyond the time prescribed under Section 34(3) of the Arbitration and Conciliation Act, 1996, the Division Bench in Delhi Development Authority v. Durga Construction Co. [2013 (139) DRJ 133 (DB)] held that though the Court is empowered to condone delay beyond the extended period of limitation of three months and thirty days, it is requisite for the party seeking the condonation to show that despite his diligence, the rectification of defects and re-filing could not be carried out within the limitation period, for bonafide reasons beyond its control. The relevant portion of the said decision is as follows:
13. In view of the above facts, it is not possible for the petition to have been filed in March, 2023 without the vakalatnama having been executed and the statement of truth having been filed only on 24th May, 2023. Moreover, no proof of filing in March 2023 has been placed on record. No draft of the petition which was filed is also on record. A mere averment without any support to show that the filing was done in March 2023 cannot be accepted.
14. On the last date, 5th January, 2024 Ld. Counsel for the Respondent had made a submission that his client is willing to give the technology to NRDC. The matter was then adjourned to enable the ld. Counsel to place some documents or seek instructions. However, he submits today that NRDC does not wish to take the technology from the Respondent.
15. In view of the decisions in Popular Construction (supra) and Simplex Infrastructure Ltd. (supra), the law in respect of Section 34 of the Arbitration and Conciliation Act 1996 is clear. Delay beyond three months plus one month is not condonable. Further, no reasonable explanation has been proffered by the Petitioner for this Court to be convinced for condonation of delay under Section 34(3) of the Arbitration and Conciliation Act, 1996.
16. Under these circumstances, the petition is dismissed as being delayed beyond the time period provided under Section 34(3) of the Arbitration and Conciliation Act, 1996. Needless to state, this Court has not opined on the merits of the case.
17. All pending applications are also disposed of.
PRATHIBA M. SINGH JUDGE JANURARY 08, 2024 mr/dn