Full Text
HIGH COURT OF DELHI
ARB.A. 1/2023, I.A. 10996/2023
KHERA BUILDCON PVT. LTD. AND ANR. ..... Appellants
Through: Mr. Amit Seth, Mr. Mukul Saluja, Mr. D. N. Kumar, Advs.
Through: Mr. Mahip Dattta Parashar, Mr. Aman Vasisth, Advs.
Date of Decision: 16.01.2024.
JUDGMENT
1. The present appeal has been filed under Section 37 of the Arbitration and Conciliation Act, 1996 (herein referred to as “the A&C Act”) against the order dated 23.02.2023 passed by the learned Arbitral Tribunal comprising of Sole Arbitrator in case Ref. No. DAC/3210/09- 21 titled as “B.K. Bansal vs. Khera Buildcon Pvt. Ltd. & Anr.”.
2. Briefly stated the facts are that the matter was referred to the learned Arbitrator in arbitration petition bearing No. 773/2021 titled as B.K. Bansal vs. Khera Buildcon Pvt. Ltd. & Anr. vide order dated 09.09.2021.
3. During the proceedings the claim petition was filed by the claimant/respondent on which primarily the following claims were raised: “Claim No.1 Mandatory Injunction Directing Respondents To Remove Himself The His Representatives / Staff / Agents From The Property Admeasuring 360 Sq. Yards Bearing No. D-145, Situated In The Railway Board Employs Cooperative Housing Society Ltd., Anand Vihar, Delhi-110092. Claim No.2 Recovery Of Rs. 9,00,000/- (Rupees Nine Lakhs Only) Outstanding Towards The Malba, Fixtures And Woods Of Existing Structure alongwith Interest @ 18% Compounded Annually In Terms of Collobaration Agreement Dated 18.07.2012. Claim No.3 Recovery Of Rs. 64,73,380/- (Rupees Sixty Four Lakh Seventy Three Thousand Three Hundred Eighty Only) Against The Financial Assistance Provided By The Claimant In Terms Of Supplementary Agreement Dated 26.11.2016 Along With Interest @ 18% Compounded Annually. Claim No.4 Recovery Of Rs. 86,52,948/- (Rupees Eighty Six Lakh Fifty Two Thousand Nine Hundred Forty Eight Only) In Lieu Of The Amount Spent By The Claimant and His Sons On His Behalf On The Pending Construction Of The Property admeasuring 360 Sq.Yards Bearing No. D-145, Situated In The Railway Board Employs Cooperative Housing Society Ltd., Anand Vihar, Delhi-110092 Out Of Their Own Funds And Resources Alongwith Interest @12% Compounded Annually. Claim No.5 Recovery For An Amount Of Rs. 2,55,00,000/- (Rupees Two Crore Fifty Five Lakh Only) Against The Damages In Terms Of Collaboration Agreement Alongwith Interest @18% Compounded Annually. Claim No.6 Recovery For A Sum Of Rs. 84,00,000 (Rupees Eighty Four Lakh Only) On Account Of The Rent To The Paid By The Respondents To The Claimant Along With Interest @12% Compounded Annually. Claim No.7 Recovery For A Sum Of Rs.1,20,00,000/- (Rupees One Crore Twenty Lakh Only) For Future Expenses To Be Incurred On Completion Of The Pending Civil And Finishing Work At The Subject Premsies. Claim No.8 Recovery For A Sum Of Rs.1,00,00,000/- (Rupees One Crore Only) Towards Mental Harassment Suffering, Pain And Agony. Claim No.9 Recovery For Damages On Account Of Depreciation Of The Building Being Constructed On Admeasuring 360 Sq.Yards Bearing No. D-145, Situated In The Railway Board Employs Cooperative Housing Society Ltd., Anand Vihar, Delhi- Ll0092. Claim No.10 Claim For Pendent-Lite Interest From 30.08.2021 To The Date Of Making Of The Award And Future Interest From The Date Of The Award Till The Date Its Realization. Claim No.11 Costs.”
4. While the proceedings were pending, an application under Section 17 of the A&C Act was moved by the respondent herein with the following prayer: “i. Ad-interim order be passed in favour of the Claimant and against the Respondents for restoring back the physical possession of the subject property in favor of the Claimant from the Respondents and their employees, successors, administrators, representatives; and executors, agents, ii. Ad-interim order be passed in favour of the Claimant and against the Respondents putting the Claimant back into the physical possession of the subject property; and iii. Ad-interim injunction restraining the Respondent, their employees, successors, executors, agents, administrators, representatives from frivolously representing to the third party its authorization on behalf of the present Claimant to deal with the said property in any manner, whatsoever; and iv. Pass such other further order(s) as this Hon'ble Tribunal may deem fit and proper in the facts and circumstances and in the interest of justice,”
5. The appellant has duly filed the reply taking various objections to the application and predominantly including that the reliefs claimed in the application filed under Section 17 of the A&C Act are the same which have been claimed in the main petition and if this prayer is allowed it would amount to passing an award in favor of the claimant. However, the learned Arbitrator after considering the entire material on record allowed the application and passed the order in favor of the respondent.
6. Learned counsel for the appellant has challenged the order of the learned Arbitrator on the ground that the impugned order is manifested wrong, perverse, and not based upon the settled principles of law. It has been submitted that the claim of the respondent is malafied, vexatious, and liable to be rejected.
7. It has further been submitted that the learned Arbitrator has wrongly granted the final relief prayed by the respondent in the claim petition vide the impugned order. Learned counsel submits that this relief could have been granted only after due adjudication by the Arbitral Tribunal on the claims of the respondent.
8. It has further been submitted that by virtue of the impugned order the learned Arbitrator has wrongly dispossessed the appellants from the premises i.e., from D-145, situated in the Railway Board Employs Cooperative Housing Society Ltd., Anand Vihar, Delhi-110092 in which the appellants were in a settled position.
9. Learned counsel has further submitted that the learned Arbitrator has granted the prayer of permitting the respondent to let out the disputed property on rent, lease, or license which was not even claimed by the respondent. It has further been submitted that there was no material on the record that the appellant handed over the possession to the respondent and there was not even a prima facie proof vide which the respondent had re-entered into the possession of the property.
10. It has been submitted that there was no cause of action with the respondent to file an application under Section 17 of the A&C Act
11. Learned counsel has further submitted that the work is 80% complete and the appellant has invested a lot of money and the remaining work could not be completed on account of the act and conduct of the respondent. The attention has also been invited to the various e-mails which have been exchanged between the parties and have also been reproduced by the learned Arbitrator.
12. Learned counsel submitted that the learned Arbitrator did not take into account the reasons attributed to the respondent which caused the delay in completion of the project.
13. Learned counsel has relied upon U.P. Junior Doctors’ Action Committee and Others vs. Dr. B. Sheetal Nandwani and Others 1992 Supp (1) SCC 680 in which it was inter alia held that it is a well known rule of practice and procedure that at interlocutory stage a relief which is asked for and is available at the disposal of the matter is not granted.
14. The reliance has also been placed upon Metro Marins and Ors. vs. Bonus Watch Co. Pvt. Ltd. and Ors. 2004 SCC 54 wherein it was held that an interim mandatory injunction can be granted only in exceptional cases coming within the exceptions noticed in “Dorab Cmvasji Warden v. Coomi Sorab Warden”.
15. Learned counsel submits that in these circumstances the impugned order is liable to be set aside.
16. Learned counsel for the respondent has submitted that the learned Arbitrator has passed a reasoned order after taking into account the submissions and counter submissions of the parties. It has been submitted that the learned Arbitrator has properly secured the interest of both parties. Learned counsel has further submitted that the jurisdiction of this court while entertaining an appeal under Section 37 is very limited and has relied upon Konkan Railway Corporation Limited vs. Chenab Bridge Project Undertaking in Civil Appeal NO. 2903 of 2023 dated 17.08.2023. Learned counsel submits that therefore the appeal is liable to be dismissed.
17. It is settled preposition that the intention of the legislature is that while entertaining an appeal under Section 37, the jurisdiction of the court is very limited. Though the legislature unlike Section 34 has not laid any parameter defining the scope of jurisdiction of an appeal filed under Section 37. But it has to be understood that if the jurisdiction of the court while entertaining an objection against final award is very limited, therefore by implication the jurisdiction of the court while entertaining an appeal filed under Section 37 against interim measure under section 17 of the A&C Act, 1996 has to be very narrow.
18. In Konkan Railway Corporation Limited vs. Chenab Bridge Project Undertaking the Hon’ble Supreme Court has inter alia held as under:
19. It is pertinent to mention here that it is an admitted fact that property bearing No. D-145, situated in The Railway Board Employs Cooperative Housing Society Ltd., Anand Vihar, Delhi-110092 is owned by the respondent. The appellant is a developer. The parties entered into a collaboration agreement on 18.07.2012 for the construction of the said property. Initially, it was agreed upon that the construction would be completed within twenty-four months. However, since it could not be completed the supplementary agreement was entered into on 25.11.2016. However, for reasons that may not be relevant here to discuss in detail the work is yet not fully completed.
20. The contention of the appellant is that by virtue of the collaboration agreement, he is in physical possession of the same and remains to be the same. The contention is that the plea raised by the respondent that he was illegally dispossessed on 21.01.2021 is entirely false and contrary to the court.
21. Per contra, the plea of the learned counsel for the respondent is that in fact time was the essence of the contract. It has further been submitted that the appellant was only in permissive possession. Learned counsel has further invited the attention to paragraph Nos. 6A and B of the collaboration agreement which defined the portion of owner/first party and the portion of builder/second party.
22. The perusal of the same indicates that the developer was given the right to dispose of the share of his portion with the fully constructed second floor (with two car parking spaces; one big-sized car and one smallsized car) with a common right to use entrance, passage, and stair-case and lift with electrical meter and water meter with proportionate undivided, indivisible and impartible ownership rights in the land underneath together with all fittings, fixtures, connections, structure standing thereon on the said floor, with proportionate rights in the other common facilities and amenities provided therein of the redeveloped/reconstructed residential building on the said property except roof rights of the terrace. However, this right was subject to the condition of the completion of the redevelopment of the proposed residential building.
23. The perusal of the impugned award also indicates that the learned Arbitrator vide a detailed and reasoned order has taken into account the submissions of both parties. It is advantageous to reproduce the inter alia findings of the learned Arbitrator:
24. Thus taking into account the factual matrix and the law, it has to be seen whether the present case is entitled for any interference by this court. In Dinesh Gupta and Ors vs. Anand Gupta and Ors. in ARB. A. 4/2020 dated 17.09.2020 the court while dealing with the scope of appeal filed under Section 37 went into a detailed analysis and inter alia held as under:
25. Catena of the judgments has made it clear that the scope of the supervisory role of the court in the Arbitral proceedings has to be minimized and the court while exercising any kind of jurisdiction is required to maintain an extremely circumspect approach.
26. A coordinate bench of this court in Asia Hotels (North) Ltd. v. Sital Dass Sons & Anr. 2022/DHC/005842 inter alia held as under:
27. It is an established principle that arbitration serves as an alternative method of resolving disputes, and it is the court's responsibility to ensure that such resolution is treated with appropriate deference. The powers granted by section 37 of the A&C Act do not provide carte blanche to the courts and must be utilized while considering the principles of minimum judicial intervention advocated by the 1996 Act. The arbitrator in present case as discussed above has passed a detailed and a well-reasoned order after taking into account the contention of the parties. There is nothing on record to suggest that the order is not sustainable or the interest of the appellant has not been protected. I consider that there is no scope for intervention.
28. Hence, the appeal along with pending application stands dismissed.
DINESH KUMAR SHARMA, J JANUARY 16, 2024/AR/HT