Budhiraja Electricals v. M/S Rosewood Apartments Co-op. Group Housing Society

Delhi High Court · 19 Oct 2006 · 2006:DHC:58
Gita Mittal
Arbitration Petition No. 84/1997
2006:DHC:58
civil appeal_allowed Significant

AI Summary

The Delhi High Court held that failure to appoint an arbitrator within the stipulated time forfeits the right, and appointed an arbitrator under Section 11 of the Arbitration & Conciliation Act, 1996, rejecting limitation objections.

Full Text
Translation output
HIGH COURT OF DELHI
Arbitration Petition No. 84/1997
JUDGMENT
reserved on : October 6, Date of Decision: October 19, 2006
BUDHIRAJA ELECTRICALS ... Petitioner through: Ms. Anusuya Salwan, Advocate
VERSUS
M/S ROSEWOOD APARTMENTS CO-OP. GROUP HOUSING SOCIETY .....Respondent through: Nemo
CORAM:
HON'BLE MS. JUSTICE GITA MITTAL.

1. Whether reporters of local papers may be allowed to see the Judgment? No

2. To be referred to the Reporter or not? No

3. Whether the judgment should be reported in the Digest?No GITA MITTAL, J.

1. By this petition under Section 11 of the Arbitration & Conciliation Act, 1996, the petitioner has sought appointment of an arbitrator. It has been contended that it had entered into a contract with the Rosewood Apartments Co-operative Group Housing Society for the construction of 86 dwelling units at Mayur Vihar. During the course of the execution of the contract, the petitioner was submitting bills time to time to the respondent. A.A No. 84/1997 1 2006:DHC:58 The final bill was admittedly submitted by the petitioner to the respondent on the 10th March, 1992.

2. In terms of the agreement between the parties, the bill required certification from the architect i.e. M/s Garg & Associates. On the 18th of April, 1992, the architect sought clarifications in respect of the bill from the respondent-society. The respondent failed to respond to the architect and consequently, the petitioner remained unpaid. The petitioner had therefore addressed a letter dated 2nd December, 1995 to the architect M/s Garg & Associates. The petitioner had clearly notified the architect that in case no decision was received within 21 days, the petitioner would be constrained to nominate an arbitrator on its behalf as per the arbitration agreement. In this letter, the petitioner also reminded the architect that it had submitted the final bill on 10th March, 1992 and the labour escalation bill on 21st May, 1992. The architect vide a letter dated 18th April, 1992 had sought clarifications from the respondentsociety to which the respondent-society had failed to respond.

3. The letter dated 6th January, 1996 which has been addressed by the architect to the respondent-society has been placed before this court. In this communication, the architect has written thus:- A.A No. 84/1997 2 “ Dated 06.01.96 THE PRESIDENT, ROSE WOOD APARTMENTS, PLOT NO. 4, MAYUR VIHAR EXT.

NEW DELHI SUB: FINAL BILL FOR THE WORK OF CONSTRUCTION 86 DWELLING UNITS FOR M/S ROSEWOOD APARTMENTS COOPERATIVE GROUP HOUSING SOCIETY LTD. (ELECTRICAL WORK)

AT MAYUR VIHAR. Dear Sir, We have received final notice from the M/s Budhiraja Electricals regarding the decision under clause no. 27 of Notice Inviting Tender to act as Arbitrator for payment of his final bill. In this respect, kindly refer our letter dated 18.04.92 and 16.07.95 (copy attached) in which we have demanded certain informations regarding advance payment if any to the contractor after our last certificate of R/A bill NO. 5 & Extra items got done without our recommendations. You are requested to reply the same within a week of receipt of this letter so that action may be taken accordingly. Thanking you, Yours faithfully, Sd/- (I.M. Garg) Garg& Associates”

4. Thereafter, the petitioner has addressed a reminder dated A.A No. 84/1997 3 22nd March, 1996 to the architect M/s Garg & Associates as well as to the respondent-society. The petitioner has also addressed another reminder dated 22nd October, 1996 with a copy to the architect M/s Garg & Associates as well as to Mr. Ravinder Chadha, Advocate wherein it was noted thus:- “Be it noted that in case you fail to appoint the arbitrator on behalf of the Society within the aforesaid time then it would be considered and established that you are not interested in the exercise of the powers vested in you under the Agreement by virtue of clause 27, and in that case the claimants shall be painfully constrained to move an application to the competent Court for appointment of the Arbitrator and in that eventually the Arbitrator so named by the claimant may also be entitled to act as a Sole Arbitrator to decide the disputes and for which you will have no right to raise any objection. Please also note that the proceedings so initiated shall be done at your expense and cost.”

5. This petition was filed on the 26th March, 1997 by the petitioner as the respondent failed to take any action in the matter. The petitioner has placed reliance on the arbitration agreement between the parties which reads thus:-

“27. The Contractor shall not go to the court in
case of dispute arising out of the execution of
this works, items, conditions of the contract. At
the first instance, it shall be decided by the
architect M/s Garg & Associates, in case of
10,644 characters total
disagreement it shall be binding on both parties.
The arbitration will comprise as follows:-
(i) One person appointed by the Society.
(ii) One person appointed by the Contractor.
(iii) Third person – Umpire – shall be the
6. The respondents put in appearance upon receipt of notice and have filed a detailed reply clearly denying the claim of the petitioner and asserted that the petition was barred by limitation. Even though none appeared to press this petition when the matter was called out, however, in as much as such an objection was raised in the written statement, learned counsel for the petitioner was heard in answer to the same.
7. It has been pointed out that the respondent failed to respond to the request of the petitioner for giving the clarifications which the architect has sought. In the communication dated 6th January, 1996, the architect had pointed out that it had written letters dated 18th April, 1992 and 16th July, 1995 to the respondent-society seeking clarifications and informations. The respondent had failed to respond to the same despite receipt of the communication dated 6th January, 1996 from the architect.
8. It has been submitted that in these circumstances, the matter remained pending for consideration before the architect A.A No. 84/1997 5 and it is only when the respondent did not settle the claims of the petitioner nor respond to the nomination of its arbitrator, that the cause of action arose in favour of the petitioner to raise the claim and seek appointment of the arbitrator before this court.
9. I have given my considered thought to the submissions made and the record of the case. It is apparent from the reading of the letter dated 6th January, 1996 addressed by the architect to the respondent-society that the matter was pending consideration before the architect who had kept the final bill dated 10th March, 1992 of the petitioner pending before him. The petitioner asserted its right and entitlement when it wrote reminders to the architect as well as to the respondent-society. Thereafter when it nominated its arbitrator on the 22nd October, 1996, the respondents refused to comply with the demand made by the petitioner in respect of the claim raised in the final bill or by way of nomination of an arbitrator.
10. My attention has been drawn to the principles laid down by this court in 2002 (Suppl.) Arb. LR 659 (Delhi) (DB) Pandit Munshi Ram & Associates (Pvt.) Ltd. Vs. DDA & Anr. The respondents had raised a similar contention based on A.A No. 84/1997 6 the claim being barred by limitation in this case as well. Upon a detailed consideration of the pronouncement of the Apex Court and of the High Court of Orissa, the Division Bench of this court held thus:-
“13. Assuming that the signature of the petitioner's representative on measurement book dated 2nd February, 1994 amounts to acceptance of the final bill, the dispute regarding the payment of final bill still persists as is clear from the pleadings of the parties. According to the petitioner, the amounts are still outstanding. According to the respondent, final bill was paid on 5th May, 1995. As already noted, the measurement book dated 2nd February, 1994 did not contain any particular figure showing the amount payable to the petitioner. Moreover, there is a letter dated 15th April, 1997 where is the question of its having been paid on 5th May, 1995? It is on the receipt of the final bill vide letter dated 15th April, 1997 that the petitioner started writing letters claiming the balance amount due and ultimately invoking arbitration clause. Under these circumstances, we think that the period of limitation for filing the petition under Section 11d(6) of the Arbitration Act would begin to run when the respondent served the final bill vide letter dated 15th April, 1997 and the petitioner raised his claim which remained unpaid. As observed in the cases of Major I.S. Rekhi dand L.K. Ahuja's case the contractor had given no claim declaration on 19th June, 1976 i.e. after the expiry of more than four years. This claim was disputed. The matter went up to the Supreme Court but the Supreme Court rejected the appeal of the UOI. In the present case, it appears that the respondent had been making payments from time to time.
A.A No. 84/1997 7 According to them the last payment was made on 5th May, 1995. The application under Section 11(6) was filed on 30th July, 1999 i.e. well within three years from the date of petitioner raising the claim which was rejected vide respondent's letter dated 22nd September, 1998. So in view of the law laid down by the Supreme Court in the case of Major I.S. Rekhi and L.K. Ahuja referred to above, we think that the petitioner's application under Section 11ss(6) of the Arbitration and Conciliation Act, 1996 was well within the limitation period prescribed in Article 137 of schedule to the Limitation Act, 1963.”

11. In this behalf, the judicial pronouncements of the Apex Court reported in (1992) 3 SCC 608 S.Rajan Vs. State of Kerala & Anr.; AIR 1988 SC 1007 Inder Singh Rekhi Vs. DDA; and of this court in AIR 1981 Delhi 293 M/s. Oriental Building & Furnishing Co. Ltd. Vs. Union of India can also be adverted to.

12. In view of the binding principles laid down in these judicial pronouncements, there is no merit in the objection taken by the respondents.

13. The respondents have failed to appoint an arbitrator in terms of the arbitration agreement and have thereby forfeited their right to appoint an arbitrator. Accordingly, this petition is allowed. I hereby appoint Justice Devinder Gupta (Retd.), R/o C-89, South Extension Part A.A No. 84/1997 8 II, New Delhi – 110 049 as arbitrator to arbitrate on the disputes between the parties. The learned arbitrator shall fix his fees in consultation with both parties. The learned arbitrator would be entitled to all out of pocket expenses as well. The parties shall pay the fees and expenses in equal shares. Since the issue of limitation stands decided, the learned arbitrator would decide on the merits of the claim.

(GITA MITTAL) JUDGE October 19, 2006 (SD)