Full Text
Arbitration Petition No. 84/1997
JUDGMENT
1. Whether reporters of local papers may be allowed to see the Judgment? No
2. To be referred to the Reporter or not? No
3. Whether the judgment should be reported in the Digest?No GITA MITTAL, J.
1. By this petition under Section 11 of the Arbitration & Conciliation Act, 1996, the petitioner has sought appointment of an arbitrator. It has been contended that it had entered into a contract with the Rosewood Apartments Co-operative Group Housing Society for the construction of 86 dwelling units at Mayur Vihar. During the course of the execution of the contract, the petitioner was submitting bills time to time to the respondent. A.A No. 84/1997 1 2006:DHC:58 The final bill was admittedly submitted by the petitioner to the respondent on the 10th March, 1992.
2. In terms of the agreement between the parties, the bill required certification from the architect i.e. M/s Garg & Associates. On the 18th of April, 1992, the architect sought clarifications in respect of the bill from the respondent-society. The respondent failed to respond to the architect and consequently, the petitioner remained unpaid. The petitioner had therefore addressed a letter dated 2nd December, 1995 to the architect M/s Garg & Associates. The petitioner had clearly notified the architect that in case no decision was received within 21 days, the petitioner would be constrained to nominate an arbitrator on its behalf as per the arbitration agreement. In this letter, the petitioner also reminded the architect that it had submitted the final bill on 10th March, 1992 and the labour escalation bill on 21st May, 1992. The architect vide a letter dated 18th April, 1992 had sought clarifications from the respondentsociety to which the respondent-society had failed to respond.
3. The letter dated 6th January, 1996 which has been addressed by the architect to the respondent-society has been placed before this court. In this communication, the architect has written thus:- A.A No. 84/1997 2 “ Dated 06.01.96 THE PRESIDENT, ROSE WOOD APARTMENTS, PLOT NO. 4, MAYUR VIHAR EXT.
NEW DELHI SUB: FINAL BILL FOR THE WORK OF CONSTRUCTION 86 DWELLING UNITS FOR M/S ROSEWOOD APARTMENTS COOPERATIVE GROUP HOUSING SOCIETY LTD. (ELECTRICAL WORK)
AT MAYUR VIHAR. Dear Sir, We have received final notice from the M/s Budhiraja Electricals regarding the decision under clause no. 27 of Notice Inviting Tender to act as Arbitrator for payment of his final bill. In this respect, kindly refer our letter dated 18.04.92 and 16.07.95 (copy attached) in which we have demanded certain informations regarding advance payment if any to the contractor after our last certificate of R/A bill NO. 5 & Extra items got done without our recommendations. You are requested to reply the same within a week of receipt of this letter so that action may be taken accordingly. Thanking you, Yours faithfully, Sd/- (I.M. Garg) Garg& Associates”
4. Thereafter, the petitioner has addressed a reminder dated A.A No. 84/1997 3 22nd March, 1996 to the architect M/s Garg & Associates as well as to the respondent-society. The petitioner has also addressed another reminder dated 22nd October, 1996 with a copy to the architect M/s Garg & Associates as well as to Mr. Ravinder Chadha, Advocate wherein it was noted thus:- “Be it noted that in case you fail to appoint the arbitrator on behalf of the Society within the aforesaid time then it would be considered and established that you are not interested in the exercise of the powers vested in you under the Agreement by virtue of clause 27, and in that case the claimants shall be painfully constrained to move an application to the competent Court for appointment of the Arbitrator and in that eventually the Arbitrator so named by the claimant may also be entitled to act as a Sole Arbitrator to decide the disputes and for which you will have no right to raise any objection. Please also note that the proceedings so initiated shall be done at your expense and cost.”
5. This petition was filed on the 26th March, 1997 by the petitioner as the respondent failed to take any action in the matter. The petitioner has placed reliance on the arbitration agreement between the parties which reads thus:-
11. In this behalf, the judicial pronouncements of the Apex Court reported in (1992) 3 SCC 608 S.Rajan Vs. State of Kerala & Anr.; AIR 1988 SC 1007 Inder Singh Rekhi Vs. DDA; and of this court in AIR 1981 Delhi 293 M/s. Oriental Building & Furnishing Co. Ltd. Vs. Union of India can also be adverted to.
12. In view of the binding principles laid down in these judicial pronouncements, there is no merit in the objection taken by the respondents.
13. The respondents have failed to appoint an arbitrator in terms of the arbitration agreement and have thereby forfeited their right to appoint an arbitrator. Accordingly, this petition is allowed. I hereby appoint Justice Devinder Gupta (Retd.), R/o C-89, South Extension Part A.A No. 84/1997 8 II, New Delhi – 110 049 as arbitrator to arbitrate on the disputes between the parties. The learned arbitrator shall fix his fees in consultation with both parties. The learned arbitrator would be entitled to all out of pocket expenses as well. The parties shall pay the fees and expenses in equal shares. Since the issue of limitation stands decided, the learned arbitrator would decide on the merits of the claim.
(GITA MITTAL) JUDGE October 19, 2006 (SD)