NBCC Ltd. v. MCD & Ors.

Delhi High Court · 13 Nov 2006 · 2006:DHC:26527
Pradeep Nandrajog
lA No.9801/1997 & CS(OS) No.2919-A/1996
2006:DHC:26527
civil appeal_dismissed Significant

AI Summary

The Delhi High Court upheld an arbitration award granting additional payments and compensation to the contractor for increased scope, delay caused by the employer, and escalation, dismissing all objections by the Municipal Corporation of Delhi.

Full Text
Translation output
HIGH COURT OF DELHI lA No.9801/1997 & CS(OS) No.2919-A/1996
# NBCC Ltd. Plaintiff I through: MrArvind Minocha,Adv.
VERSUS
$ MCD & Ors. Defendants through: Ms.Pooja Chandra,Adv.
Date of Decision: 13-11-2006
CORAM:
Hon'ble Mr.Justlce Pradeep Nandrajog
JUDGMENT

1. Whether reporters of local papers may be allowed to see the judgment?

2. To be referred to the Reporter ornot?^^

3. Whetherjudgmentshould be reported In Digest?;^--': PRADEEP NANDRAIOG. l.(Oral)

1. Delhi Jai Board, successor-in-interest of the Delhi Water Supply and Sewage Disposal Undertaking (MCD)has filed objections to the unanimous award dated 19.9.1996 pubiished by Shri K.B.Kumar and Shri W.D.Dandage.

2. I have, with the assistance of iearned counsei for the parties, perused the award and have gone through the record of arbitration. CS(OS)No.2919-A/1996 Pg.No.lof23 2006:DHC:26527

3. I shall be noting the relevant facts as I deal with the objections. But, before that, two preliminary objections raised may be taken note of and decided.

4. First preliminary objection raised is that the iearned arbitrators published the award beyond the period of limitation.

5. Objection appears to be that the learned arbitrator becamefunctus officio when they published the award.

6. Objection needs to be noted and rejected for the reason it has been noted by the learned arbitrators that parties, by consent, enlarged time for publication of the award till 30.9.1996.

7. Indeed, various orders passed by the learned arbitrators show that as and when 4 months time was expiring, prior thereto, parties were extending time for the learned arbitrators to publish the award.

8. Second preliminary objection is that the parties did not lead any evidence and therefore the award is based on no evidence.

9. Record of the arbitrators show that documents nearing about 700 pages were filed by the parties.

10. Though not recorded,from the order sheet maintained by the learned arbitrators, which evidence record of CS(OS)No.2919-A/1996 Pg.No.2of23 submissions before the arbitrators, parties reiied upon the documents filed. It is apparent that the parties waived formal proof ofthe relied upon documents.

11. Even otherwise, documents relied by the parties are correspondences exchanged during the period work was in progress. From letter written by one party, authenticity of the letter written by the other party can be inferred from the letter numbers referred to. I clarify, inter se exchange of letters with regard to the letter numbers shows that the parties wrote the relied upon letters.

12. Before dealing with the objections on merits, a few relevant dates may be noted.

26,687 characters total

13. Notice inviting tender for design, construction, supply and erection of the second 100 MGD treatment plant at Haiderpur was issued by the erstwhile Delhi Water Supply and Sewage Disposal Undertaking somewhere towards end of 1988 or early 1989. Offers had to be made by parties by filling up the tender documents. „ 14. Various bidders submitted their offers. Negotiations were held from time to time, probably intending to have a price reduction. Parties revised their bids. In respect of certain items of work, clarificatory letters were issued by respective parties. CS(OS)No.2919-A/1996 Pg.No.3of23 Work was decided to be awarded to the non-objector as Commissioner, MCD in his letter dated 27.11.1989, which letter formed a preamble of consideration by the committee, noted that non-objectdr's tender was as per the terms notified in the tender documents. The committee, vide resolution No.644 relating to item No.563 resolved on 28.11.1989 to award the contract to the non-objector.

15. A formal letter of intent was issued to the non-objector on 28.11.1989. It was followed by a detailed work order which was issued to the non-objector (date unknown). On 30.4.1990, a formal contract was executed between the parties.

16. The formal contract is at pages 367 to 373 of volume 1 ofthe documents filed before the learned arbitrators.

17. The formal agreement notes that 10 letters written by the department after tender was submitted and 27 letters..)■ written by the contractor after tender was submitted would form •.4. ' part of the contract between the parties. Relevant for consideration of the objections is that a letter dated 21.11.1989 written by the non-objector was included as part of the contract.

18. The 10 letters written by the department and the 27 letters written by the non-objector were included in the contract bond which I note consists of the contract executed on CS(OS)No.2919-A/1996 Pg.No.4 of 23 30.4.1990, offer made by the non-objector and the letters exchanged between the parties. Work was to commence on 12.12.1989 (15 days after issuance of letter of intent) and was to be completed within 24 months i.e. by 12.12.1991. However, parties treated work to commence on 22.2.1990 and therefore 24 months expire on 22.2.1992.

19. Contract provided for escalation as per clause lOCC of the contract.

20. Learned arbitrators have rejected ciaims No.3, 5, 7, 15, 16, 18 and 20. Non-objector has not filed any objections thereto. I would thus be dealing with the objections fiied and as raised to the claims allowed.

21. Claim No.l in sum of Rs.32 lacs was allowed by the learned arbitrators holding that vide letter dated 21.11.1989, non-objector had clearly written to the department that if vaives of 600 mm dia are required, Rs.20,000/- per valve would be charged extra for each valve. It has been noted, a fact not disputed,that valves used were of600 mm dia.

22. Noting that 160 valves were used, Rs.32 lacs have been awarded.

23. Learned counsel for the objector states that as per the tender specifications, non-objector was to supply valves of CS(OS)No.2919-A/1996 Pg.No.5of23 --A Indian Bureau of Standards. Counsel urges that the department was justified in requiring contractor to supply valves of Indian Bureau of Standards and therefore, price payable was the one which was quoted for.

24. I have perused the tender documents.

25. The description of valves is to be found at page No.217 of volume 1 of the documents filed. Learned arbitrator has noted that the description of the valves was as per page 217 ofthe contract bond.

26. At page 217 of the contract bond it is recorded that gate valves shall generally conform to IS No.780/IS-2906.

27. Learned arbitrator has noted that the gate valves had to conform to standard IS No.2906.

28. From where is the objector involving Bureau of Indian Standards is unexplained. Probably, intention appears to be that IS! standards are prescribed by the Bureau of Indian Standards.

29. If that be so, learned arbitrator has clearly noted that contract required gate valves to be supplied matching IS No.2906.

30. But, what is relevant is, and as noted by the learned arbitrators that the non-objector, vide letter dated 21.11.1989, CS(OS)No.2919-A/1996 Pg.No.6of23 -J VI ^ • clearly stated that if valves required to be supplied were of 600 mm dia., Rs.20,000/- per valve would be charged in addition to the quoted price.

31. As I have noted above, non-objector's letter dated 21.11.1989 has been included as part of the contractual documents.

32. Objection to claim No.l is therefore without any merit.

33. Claim No.2 in sum of Rs.19,28,265/- has been allowed by the learned arbitrators. The foundation of the claim was that the notice inviting tender and the tender documents stipulated that the water treatment plant to be set up is of 100 MGD capacity. But, while requiring the contractor to design and erect the plant,the department increased the capacity to 103 MGDs.

34. On account of the additional 3% increase in the capacity of the plant, non-objector stated that extra expenditure was incurred.

35. Learned arbitrators have noted that after letter of intent was issued on 23.4.1990,the objector decided to increase the capacity of the plant to 103 MGD inasmuch as 3 MGD water was required periodically to flush the filters by effecting backwashing.

36. Learned arbitrators have noted that decision was CS(OS)No.2919-A/1996 Pg.No.7 of23 conveyed to the non-objector on 10.5.1990.

37. Learned arbitrators have noted that the contract nowhere stipulates that while designing the filters or the plant, contractor had to design the same 3% above the notified capacity. On said reasoning,claim has been allowed.

38. It is sought to be urged that 3% of the total output of the plant was required for back-flushing and since it was known to the prospective bidders that the plant has to treat 100 MGD water and purify the same, prospective bidders ought to have taken into consideration requirement of waterfor back-flushing.

39. I am afraid, this line of argument cannot be accepted for the reason, learned arbitrators have correctly noted that the tender documents never informed the bidders that the plant to be designed ought to match the specifications of 103 MGD.

40. That apart, this decision was conveyed to the nonobjector on 10.5.1990. As noted above, letter of intent was issued on 27.11.1989. Formal contract was executed on 30.4.1990.

41. Learned counsel urges that the learned arbitrators have not noted that it was made known to the prospective bidders that individual filters would be closed once every 24 hours for backwashing. Thus, 1 out of 20 filters in each filter CS(OS)No.2919-A/1996 Pg.No.8of23 house had to generally remain non-functional.

42. I do not understand as to how this line of argument would advance the case of the objector, issue is of the capacity notified to the contractors for construction of the water treatment plant. As I understand it, if a person is called upon to design and construct a water treatment plant of 100 MGD capacity it would mean that the water treatment plant should f-; ' be capable of purifying 100 million gallons of water per day. How that water is finally used is irrelevant.

43. Objection to the award pertaining to claim No.2 is accordingly rejected.

44. Claim No.4 is also allowed, but in part. As against a claim of Rs.4,30,609.44, Rs.45,121.38 has been allowed.

45. Claim by the contractor was for laying a lean concrete foundation as also reinforcement on the sides of the 1200 mm t dia water pipeline. ■<

46. Learned arbitrators have noted that the contract stipulated that in case, after digging, it is found that the soil is loose, at no extra cost, contract or had to lay a lean concrete foundation.

47. Holding so, learned arbitrators have denied claim of the non objector pertaining to the foundation. Learned CS(OS)No.2919-A/1996, Pg.No.9of23 H[5] arbitrators have noted that when dug up, the soil was found to be soft.

48. But, in relation to the reinforcement work forming the sides of water pipe, non objector has been recompensed.

49. Indeed, the contract only required the non objector to lay a lean concrete foundation if soil was loose. It did not stipulate that in such eventuality even the sides of the water pipeline would be reinforced.

50. I find no infirmity in the award pertaining to claim No.4.

51. Claim No.6 in sum of Rs.5,97 I- has been allowed in sum of Rs.3,40,584.24.

52. Learned arbitrators have noted that the work got prolonged due to high tension cables and the pillars erected by DESU. The site of the said HT cables was where filter house had to be constructed.

53. Learned arbitrators have noted that site pertaining to the filter house was made available belatedly to the nonobjector. Learned arbitrators have noted that contract stipulated period came to an end in February 1992 and by consent was extended to May 1992

54. Learned arbitrators have noted that the work CS(OS)No.2919-A/1996 Pg.No.lO of23 pertaining to the filter house got completed on 4.6.1993.

55. On the backdrop of facts as afore-noted, learned arbitrators recompensed the non-objector on account of stone and stone grit used in the execution ofthe work noting that due to directions issued by the Supreme Court of India, mines in Delhi had to close down. Non-objector had to procure material from the State of Haryana at a higher price.

56. Learned arbitrators have partially recompensed the non-objector for work done beyond May 1992 and up to 4.6.1993.

57. Considering the position that the work in question had indeed been prolonged due to HT cables,learned counsel forthe objector urges that learned arbitrators ignored the fact that directions were issued by the department to the non-objector to procure 5000 cum of stone during the period 31.5.1990 to 31.3.1992 but the non-objector procured only 3785.85 cum stone.

58. Second objection urged is that escalation had to be determined under clause lOCC ofthe contract.

59. Third objection urged is that there is no evidence that the stone was procured from Haryana.

60. As regards the third objection raised, I take judicial notice of the fact, evidenced by the various orders of Supreme Court published in various legal journals that quarrying was banned in Delhi by the Supreme Court in the year 1992. As regards the first objection, suffice would it be to note that stand taken by the non-objector is that since the site was not available, where would the non-objector stack stones.

61. indeed, record of the arbitrators show that the objector has written numerous letters on the issue pointing out that till DESU removed the HT cables and pillars were removed, the non-objector could do nothing at the site.

62. Non-objector was not obliged to block his capital by purchasing stones and stacking the same at.site.

63. As regards the applicability of clause lOCC, suffice would it be to note that escalation provided as per contract would hold good during contract agreed period. Once contract agreed period is over and default is committed by a party, non defaulting party would be entitled to the benefit of Section 55 of the Contract Act.

64. in relation to clause IOC of which provides for partial recompense, a Division Bench of this Court, in the decision reported as AIR 1980 Delhi 266, M/s.Metro Electric Co.vs. Delhi DevelopmentAuthority has held as afore-noted by me. CS(OS)No.2919-A/1996 Pg.No.l2of23

65. On facts, learned arbitrators have noted that rates of stone increased to Rs.280/- per cum towards the end of the stipulated period ofthe contract i.e. by May 1992.

66. As noted above, for the work done beyond May 1992 and up to 4.6.1993, learned arbitrators had recompensed the non-objector due to increase in price ofstone.

67. The findings cannot be called perverse. I accordingly < repel the challenge to the sum awarded under claim No.6.

68. Laying a challenge to claim No.8 and 9, it is urged that the department was justified in adopting the prices as of November 1989 as the base Index.

69. It Is not In dispute that contract stipulated that any increase and decrease in price of material as also electrical and mechanical equipment to be used in the execution of the works would be recompensed to the non-objector as per the agreed formula.

70. Price rise had to be determined in the context of cost indices pertaining to civil works as issued by the Government of India. In relation to electrical and mechanical works, escalation had to be worked out as per cost indices published by lEMA (Indian Electrical Manufacturers Association) and IPMA (Indian Pumps Manufacturing Association). CS(OS)No.2919-A/1996 Pg.No.13 of23

71. Learned arbitrators have noted that the tender documents stipulated that the cost indices as applicable on the date when the price bid is opened would apply.

72. I find nothing objectionable or perverse committed by the learned arbitrators. Indeed, clause 27(page 220 of Volume 1)records as under:- "Statutory violation shall be applicable both ways i.e. index of increase, it will be payable and index of decrease, it shall be recoverable. The base date will be taken as the opening date of price bid."

73. Under no circumstances could the objector shift the base date. The contract clearly stipulates that the base date will be the date when price bids are opened.

74. It is not in dispute that the price bids were opened on 10.4.1989. Learned arbitrators have therefore correctly opined that the base date has to be 10.4.1989.

75. It is not in dispute that if the base date adoption is correct, sums awarded under claim No.8 and 9 would be justified.

76. I, therefore,find no merits in the objections pertaining to claim No.8 and 9.

77. Claim No.10 and 11 have been allowed by the learned arbitrators holding, pertaining to claim No.lO, that during execution of the work,the non-objector was required to provide CS(OS)No.2919-A/1996 Pg.No.l4of23 one electronic LOH meter notwithstanding that the contract did not require any to be installed. In relation to claim No.11, learned arbitrators have noted that the tender documents required the non-objector to provide only 2 earthing points in the filter house No.l but[6] were directed to be provided for.

78. Treating the two works as extra works, claims of the non-objector have been allowed.

79. Objections raised are to the effect that the learned arbitrators wrongly allowed claim No.lO and 11.

80. It is urged that no approval was granted by the department to the rates quoted by the non objector for additional works.

81. It is a usual practice in the departments to get works executed but not settle the rates. What is relevant is, whether extra work was got done from the non objector. If yes, department had to pay for the same.

82. If the officers of the department did not settle the rates, it is for them to suffer the necessary consequences.

83. Be that as it may, it has not been shown to me as to on what account sum awarded under claim No.lO and 11 is excessive. I may note that the sum awarded under the two claims is Rs.35,200/- and Rs.22,211/- respectively. CS(OS)No.2919-A/1996 Pg.No.15 of23

84. Laying a challenge to claim No.l[2] and 13, it is urged by the counsel for the objector that a hand-pump/tube-well installed by the non-objector, when tested for purity of the water,showed that the water was not fit for drinking purposes. It is accordingly urged that the learned arbitrators have wrongly held that the department could not effect recoveries towards the water charges.

85. To appreciate the objection, it would be relevant to note that under the contract, water for drinking purposes and construction purposes had to be provided for by the objector, but cost thereof had to be borne by the non-objector. Meaning thereby, objector was authorised to deduct water charges if water was supplied by the objector and consumed by the non objector.

86. Learned arbitrators have noted that metered water ' supply was made available only on 4.3.1991. Accordingly, for the prior period, deductions made by the objector have been held to be unjustified.

87. I do not understand as to how objector could effect deduction towards water charges before it started supplying water to the non-objector. The non-objector may have cheated on his labour by supplying them drinking water which was not CS(OS)No.2919-A/1996 Pg.No.l6of23 up to the requisite specifications, for which non-objector could be otherwise penalised. But, under no circumstances recovery towards water charges could have been effected with effect from a date prior to the one on which metered water supply was made available.

88. It is not in dispute that the non objector had bored a tubeweli/borewell for providing water, it is also not in dispute that metered water supply was made available on 4.3.1991.

89. Sums involved under claim No.l[2] and 13 are Rs.25,352.34 and Rs.7,681.57 respectively.

90. I do not find any merit in the objections pertaining to the said two claims.

91. Claim No.14 was on account of escalation in price of material and other consumables used beyond February 1992 till works were completed on 1.6.1993.

92. Learned arbitrators were called upon to decide the basic issue whether the objector was responsible for the delay. If yes, learned arbitrators were called upon to determine the compensation payable to the non objector due to increase in prices of various materials and consumables used by the non objector.

93. - On the issue of delay, learned arbitrators have noted CS(OS)No.2919-A/1996 Pg.No.17 of23 -V i that as per the letter of intent, the work was to start on 13.12.1989 and had to be completed in 24 months. Immediately after issuing the letter of intent on 15.12.1989 (C-

176) learned arbitrators have noted that the department wrote to the non-objector not to start the work. On 20.2.1990, contractor was required to commence the work with effect from 22.2.1990.

94. Learned arbitrators noted that the formai contract was executed on 30.4.1990 recording that 24 months would reckon with effect from 22.2.1990.

95. In relation to the execution of the work, learned arbitrators noted that 3 different agencies were invoived in respect of 3 parts of the total works to be executed to complete the entire water treatment plant. Learned arbitrators have noted that the exact location of the piant was not clearly laid down. As I understand it, learned arbitrators intend to convey that the layout ofthe plant was notfrozen with certainty.

96. Learned arbitrators, in the context of Ex.C-6 and C- 210, being objector's letters dated 24.4.1990 and 25.6.1990 noted that in April 1990 non-objector was asked to proceed ahead with designing work.

97. Learned arbitrators have noted that the objector took CS(OS)No.2919-A/1996 Pg.No.18 of23 / undue tinne in approving the design. Learned arbitrators have further noted delay ofthe objector in certifying the safe bearing capacity of the soil. Learned arbitrators have also noted delay in releasing mobilization advance to the non-objector. Above all, learned arbitrators have noted that since February 1990, non-objector had been writing to the department that HT cables laid by DESU were interfering with one of the two filter houses. Thereafter, objector took up the issue with DESU which demanded Rs.60 lacs for shifting the cables. Learned arbitrators have noted that DESU shifted the cables by 30.12.1991.

98. Issue of delay is a question of fact. Learned arbitrators have noted the evidence on record and have returned a finding against the department.

99. I may note that in relation to certain periods, learned arbitrators have noted that the non-objector was not executing the works with the required pace so as to complete the same within 24 months.

100. A perusal of the award pertaining to the issue of delay shows that the learned arbitrators have considered rival versions and the evidence on record.

101. It would not be insignificant to note that one of the major works to be executed was construction of 2 filter houses. CS(OS)No.2919-A/1996 Pg.No.l[9] of23 Work pertaining to onecouid notcommenceeven by December

1991. This ieft the non-objector hardly 2 months to complete the said work.

102. Learned arbitrators have noted that they have considered and recompensed the non-objectorfor extra cost of stone metal under claim i\lo.[6] and escalation for electrical and mechanical works was considered under claim No.8 and 9. ^ Learned arbitrators have recompensed the non-objectorforcivil works.

103. I do not find any error committed by the learned arbitrators, who, for the period contract got prolonged have recompensed the non-objector on account of civil works.

104. Pertaining to claim No.l[7] which has been allowed in sum of Rs.l,03,121.40, objection raised is that the sum awarded is contrary to the terms and conditions ofthe contract.

105. Claim ofthe non objector was on account of deploying operational and maintenance staff beyond one month trial run period stipulated under the contract.

106. Learned arbitrators have noted that although non objector notified completion of the filter house on 28.2.1993, objector provided water for regular operations only with effect from 18.3.1993. Learned arbitrators have noted that for one CS(OS)No.2919-A/1996 Pg.No.20 of23 month thereafter, non objector had to deploy the electrical and mechanical staff till 17.4.1993. Learned arbitrators have further noted that even thereafter, objector did not take over the piant. Learned arbitrators have noted that the non objector had to station stafffor operating the piant tili 21.8.1993.

107. It is not in dispute that under the contract, obiigation of the non objector was to station operating staff for a period of one month only. Obviously, reason thereof was for the staff of the non objector to train empioyees of the objector in running and maintaining the piant.

108. It is not the case pleaded in the objections that the dates noted by the learned arbitrators are incorrect.

109. Learned arbitrators have noted that detaiis of the staff deployed by the non-objector was to befound in Ex.C-282.

110. Learned arbitrators have compensated the non objectorfor the period 18.4.1993to 21.8.1993.

111. The award has taken into consideration aii reievant parameters. Reievant dates as also conditions of the contract have been noted.

112. I find no merits in the objection raised to ciaim No.l[7].

113. Laying a challenge to claim No.19, it is urged that the interest granted by the learned arbitrators is excessive. CS(OS)No.2919-A/1996 Pg.No.21of23 J /■'

114. The learned arbitrators have awarded interest to the non-objector @18% per annum in respect of claims 1to 5, 7 to 13 and 17 with effect from 4.6.1993.

115. I do not find the interest awarded as exorbitant or excessive considering the period in question.

116. On the totality of the award and the objections raised, keeping in view the evidence before the learned arbitrators, I find no infirmity in the award regarding finding qua claim of nonobjector.

117. Pertaining to the counter claims raised by the objector it may be noted that the learned arbitrators have noted that none of the counter claims could form the subject matter of reference to them as the department never notified the same when respective parties nominated their arbitrator. In any case, learned arbitrators have noted that the so called counter claims were nothing but a facet of the amounts payable to the nonobjector. Learned arbitrators have held that in view of the indepth analysis of the claim of the non-objector, no useful purpose would be served in dealing with the counter claims.

118. I find no merits in the objections. lA No.9801/1997 is dismissed. CSfOS) N0.2919-A/1996 CS(OS)No.2919-A/1996 Pg.No.22 of 23 X-

1. In view of the decision above dismissing lA No.9801/1997, award dated 19.9.1996 published by Shri K.B.Kumar and Shri W.D.Dandage is made a rule of the Court. Post decretal interest from the date of decree till date of realization is awarded to the non-objector and against the objector @9% per annum. Decree shall follow.

2. No costs. November 13,2006 PRADEEP NANDRAJOG,J. dk CS(OS)No.2919-A/1996 Pg.No.23 of23