Full Text
HIGH COURT OF DELHI
Date of Decision: 19.03.2024
ADEPT POWER PVT LTD ..... Petitioner
Through: Mr Ravinder Singh, Advocate.
Through: Mr. Rajiv Garg, Mr. Rajeev Kapoor, Mr. Shivam Bharara and Ms. Seema Yadav, Advocates along withRespondent.
JUDGMENT
1. This is a petition filed under section 14(1)(a) and 14(2) of the Arbitration and Conciliation Act, 1996 seeking an order terminating the mandate of the Arbitral Tribunal.
2. The facts are that one Crompton Greaves Ltd. awarded the contract for construction of Uttar Pradesh Power Transmission Corporation Limited (“UPPTCL”) 400kV substation at Muradnagar, Uttar Pradesh to a company named Kunj Power Projects Private Limited. Kunj Power Projects placed a conditional work order on the petitioner to complete the civil work at 400kV substation at Muradnagaras specified in the Work Order bearing ref. no. W.0./400kV/Muradnagar/O[1].
3. Pursuant to the work order dated 09.04.2014, the petitioner and the respondent executed a Memorandum of Understanding (MoU) dated 01.05.2014 for materials and labour on covered area contract basis for the said project. On 28.06.2014, the petitioner and the respondent executed a Contract Execution Agreement to spell out the specific terms and conditions between the parties with regard to the work to be executed at the project.
4. It is stated that the Contract Execution Agreement contained the Arbitration clause.Since there were disputes between the parties, the respondent invoked the Arbitration clause.
5. On 19.10.2016, this Court in Arbitration Petition No. 566/2015 held as under:-
parties arising out of the agreement between them. The Court, at this stage, is only required to examine under Section 11(6A) of the Act whether there exists an arbitration agreement. The Court is not expected to go into the merits of the petition or the counter-claims of the Respondents, if any. In law, therefore, there appears to be no legal basis for the Respondent to oppose the appointment of an arbitrator to refer the disputes arising between the parties.
4. Accordingly, this Court appoints Mr. Pradeep Chaddah (Mobile No. 991 0384665), a former District Judge, Delhi as sole Arbitrator to adjudicate the disputes between the parties including their claims and counter-claims. The learned Arbitrator will fix his own terms. The requirements of the Arbitration and Conciliation Act, 1996 as amended with effect from 23rd October, 2015 shall be complied with.
5. The parties will appear before the learned Arbitrator, in the first instance, on 16th November, 2016 at 4 pm at a venue to be organised by the Petitioner and the expenses for which will be shared equally by the parties.
6. The petition is disposed of. A copy of this order be communicated to the learned Arbitrator forthwith.”
6. Pursuant to the same, the learned Sole Arbitrator entered reference and proceeded to adjudicate the claims between the parties.
7. Since, as per the petitioner, the period of one year as envisaged under Section 29A of the Arbitration and Conciliation Act, 1996 had expired, the petitioner filed an application under Section 29A of the Arbitration and Conciliation Act, 1996to terminate the proceedings.This application was dismissed by the learned Arbitral Tribunal. Hence the present petition.
8. The submissions of Mr. Singh, learned counsel for the petitioner are that:a. There is no Arbitration Agreement between the parties. b. Even assuming that there is an Arbitration Agreement,the same has expired in view of Section 29A of the Arbitration and Conciliation Act, 1996.
9. He further draws my attention to the dates as under:- Dates Events 23.10.2015 The amendment qua section 29A of the Arbitration and Conciliation Act, 1996 came effect 19.10.2016 The Ld. Sole Arbitrator was appointed as the arbitrator in the instant caseon 19.10.2016, it was expressly observed in the order as under:- “...the requirement of the Arbitration and Conciliation Act as amended with effect from 23.10.2015 shall be compliedwith...” 16.11.2016 The Ld. Sole Arbitrator took charge of the proceedings in the terms of the order dated 19.10.2016 of the Hon’ble Delhi High Court 16.05.2017 That the pleadings were complete in the present matter 16.05.2018 The period of 1 year came to an end as prescribed under section 29A(1) of the Arbitration and Conciliation Act, 16.11.2018 Even the maximum extended period of six months has come to end as prescribed under section 29A(3) of the Arbitration and Conciliation Act, 1996 which can done be only with the consent of parties that has not be done in the present case.
10. I have heard learned counsel for the parties.
11. The fact that there was an Arbitration Agreement between the parties or not cannot be agitated at this stage. The order dated 19.10.2016 passed in Arbitration Petition No. 566/2015 categorically holds that there is an Arbitration Agreement and proceededto appoint an Arbitrator. Thereafter, the petitioner participated in the arbitration proceedings, appeared and now cannot at this stage urge that there is no Arbitration Agreement.
12. As regards the arguments onSection29A is concerned, the learned Arbitrator has held in order dated 03.11.2022as under:- “Now coming back to facts of the matter in hand, this Tribunal is notconvinced with the stand taken by the Respondent in its application. Proceedingshad commenced before notification of amendment. This position was upheld inabove mentioned case of Republic of India Vs Augusta Westland InternationalLimited CS (COMM) 9/2019 decided on 9.01.2019 (2019) SCC online Delhi 6419by Hon'ble High Court of Delhi. Claimant had issued notice dated 14.09.2015seeking appointment of Arbitrator. The notice was duly received by Respondentwho sent request dated 17.09.2015 seeking three days time to file reply to thenotice. It means that by 17.09.2015 Respondent had been served with noticeseeking appointment of Arbitrator. So the provision of Section 29A of theAmendment Act, 2015 are not applicable to the proceedings in hand.Proceedings had commenced before the amendment in the Act came in force.The application deserves dismissal and is accordingly dismissed. Theproceedings in hand shall continue.”
13. In the present case, the notice invoking Arbitration was issued on 14.09.2015, replied on 17.09.2015 and the petition for appointment of Arbitrator was filed on 08.10.2015 i.e. much prior to 23.10.2015 when Section 29A came into effect.
14. The law is settled in this regard. Learned counsel for the respondent has rightly placed reliance on the judgment of the Hon’ble Supreme Court in Shree Vishnu Constructions v. Military Engg. Service, (2023) 8 SCC 329and more particularly on para 27 which reads as under:-
Amendment Act and the application under Section 11 for appointment of an arbitrator is made post Amendment Act, 2015, the provisions of pre-Amendment Act, 2015 shall be applicable and not the 2015 Amendment Act.” (emphasis added)
15. Further, the Co-ordinate bench of this Court in somewhat similar circumstances in Republic of India through Ministry of Defence v. Agusta Westland International Ltd., 2019 SCC OnLine Del 6419has held as under:-
16. I am in full agreement with the above observations as arbitral proceedings initiated before the Amendment Act of 2015 took effect are not covered by Section 29A of the Arbitration and Conciliation Act, 1996. As in the present case, the notice invoking Arbitration and the petition seeking appointment of Arbitrator was filed before the Amendment came into effect. Therefore, Section 29A will not be applicable.
17. Mr. Singh relies on TATA Sons (P) Ltd. v. Siva Industries &Holdings Ltd., (2023) 5 SCC 421and more particularly on para 34 which reads as under:-
be applicable to all pending arbitral proceedings as on the effective date i.e. 30-8-2019.”
18. The above cited judgment will not help the petitioner as TATA Sons (supra) addresses the contention that whether the timeframe as indicated in Section 29A would apply to the International Commercial Arbitration whereas admittedly, the same is not the issue herein.
19. Further, reliance placed on BCCI v. Kochi Cricket (P) Ltd., (2018) 6 SCC 287 by the learned counsel for the petitioner is also misconceived as the said judgment was dealing with section 34 and 36 of the Arbitration and Conciliation Act, 1996 (before and after amendment of Section 36 in 2015). The judgments of Shree Vishnu Constructions (supra) and Republic of India through Ministry of Defence (supra) squarely cover the issue in hand.
20. For the said reasons, the petition is accordingly dismissed.
21. All pending applications, if any, are hereby disposed of.