S.K. Garg v. M/S SKY CITY HOTELS (P) LTD

Delhi High Court · 07 Sep 2009 · 2009:DHC:3697
Rajiv Sahai Endlaw
OMP No.470/2009
2009:DHC:3697
civil petition_dismissed

AI Summary

The Delhi High Court dismissed the petition seeking interim injunction restraining completion of construction and removal of tools, holding that delayed application and substantial completion preclude such relief under Section 9 of the Arbitration Act.

Full Text
Translation output
HIGH COURT OF DELHI
OMP No.470/2009.
Date of Decision: 07.09.2009
SHRI S.K. GARG .…Petitioner
Through: Mr. Man Mohan Singh, Advocate for the Petitioner.
VERSUS
M/S SKY CITY HOTELS (P) LTD. ... Respondent
Through: Mr. Sangram Patnaik, Mr. Shante Pandey & Ms. Bimola Irom, Advocates for the Respondent.
CORAM :-
HON’BLE MR. JUSTICE RAJIV SAHAI ENDLAW
JUDGMENT

1. Whether reporters of Local papers may be allowed to see the judgment? NO

2. To be referred to the reporter or not? NO

3. Whether the judgment should be reported NO in the Digest?

RAJIV SAHAI ENDLAW, J.

1. The petitioner claiming to be a building contractor engaged by the respondent for carrying out the construction work has filed this application for interim measures of restraining the respondent from getting the balance construction work done from any third party till the measurement of the work done by the petitioner are recorded. The counsel for the petitioner, on enquiry, had on the last date stated that the construction works were carried out till 15th November, 2008. Since this petition was preferred after over ten months from the cessation of the works, no ex-parte order against the respondent was granted. 2009:DHC:3697 petitioner was terminated on 22nd April, 2008 and w.e.f. 13th April,

2008. He also states that the construction work has since been completed and the Haryana Urban Development Authority has on 6th April, 2009 already issued the Completion Certificate. The transcript of the e-mail dated 22nd April, 2008 of termination of contract and the photocopy of the Completion Certificate dated 6th April, 2009 are handed over in the court and are taken on record.

3. The counsel for the petitioner on enquiry states that the petitioner had done the work of construction till the upper ground floor only. Though, the counsel for the respondent controverts the aforesaid statement but from the Completion Certificate handed over, it is borne out that the same is till the stage of laying of the roof of the 8th floor. Thus, it appears that no purpose would be served in directing any measurements at this stage when substantial work has already been carried out at site.

4. The petitioner has also sought the relief of restraining the respondent from interfering with the petitioner removing his tools, machinery, plants, material lying at site. The counsel for the respondent, on instructions, states that none of the machinery, tools, plants, material of the petitioner are lying at site. In these proceedings under Section 9 of the Act, such disputed questions cannot be adjudicated and in view of the stand of the respondent and long lapse of time and intervening events, this relief also cannot be granted. It shall however be open to the petitioner to, if permissible in law, in the arbitration proceedings claim relief in this regard and/or as to the value of any machinery, tools, plants, material left at

5. With the aforesaid observations, the petition is dismissed. However, in the circumstances, parties are left to bear their own costs.

RAJIV SAHAI ENDLAW (JUDGE) September 7th, 2009 pp