Full Text
Translation output
HIGH COURT OF DELHI
LA.APP. 582/2011
SMT KAMLESH PATEL Appellant
Through : Mr. Deepak Khosla, Adv.
LA.APP. 582/2011
SMT KAMLESH PATEL Appellant
Through : Mr. Deepak Khosla, Adv.
VERSUS
UNION OF INDIA & ANR. Respondents
Through : Mr. S.K. Pathak, Adv. for R-1/UOI.
Mr. Paramhansh Sahni, proxy counsel for Mr. Arun Birbal, Adv. for R-2/DDA
Through : Mr. S.K. Pathak, Adv. for R-1/UOI.
Mr. Paramhansh Sahni, proxy counsel for Mr. Arun Birbal, Adv. for R-2/DDA
CORAM:
HON'BLE MS. JUSTICE HIMA KOHLI
09.09.2011 C.M. No.16870/2011 (by the anpellant for condonation of delay)
The present application is filed by the appellant praying inter a/ia for condonation of delay of 312 days in preferring the accompanying appeal.
At the outset, counsel for the appellant states that in case the delay of 312 days in preferring the accompanying appeal is condoned, S the appellant shall not claim interest on the enhanced amount for the period of delay as also the costs of the appeal.
Counsel for respondent No. 1/Union of India, who appears on advance copy, states that he has no objection to the aforesaid suggestion made by the counsel for the appellant Accordingly, the
09.09.2011 C.M. No.16870/2011 (by the anpellant for condonation of delay)
The present application is filed by the appellant praying inter a/ia for condonation of delay of 312 days in preferring the accompanying appeal.
At the outset, counsel for the appellant states that in case the delay of 312 days in preferring the accompanying appeal is condoned, S the appellant shall not claim interest on the enhanced amount for the period of delay as also the costs of the appeal.
Counsel for respondent No. 1/Union of India, who appears on advance copy, states that he has no objection to the aforesaid suggestion made by the counsel for the appellant Accordingly, the
LA.APP. 582/2011
2011:DHC:19008 present application is allowed with the condition that the appellant shall not be entitled to claim interest on the enhanced amount for the period of delay of 312 days in preferring the appeal and the costs of the appeal.
The application is disposed of.
By way of the present appeal, the appellant has assailed the
2011:DHC:19008 present application is allowed with the condition that the appellant shall not be entitled to claim interest on the enhanced amount for the period of delay of 312 days in preferring the appeal and the costs of the appeal.
The application is disposed of.
By way of the present appeal, the appellant has assailed the
ORDER
29.07.2010 passed by the Reference Court in LAC No.14/08 arising out of Award No.13/DCW/2006-07 pertaining to village
Mundka, pursuant to the notification dated 17.06.2005 issued under
Section 4 of the Land Acquisition Act 1894 (in short 'the Act').
Counsel for the appellant submits that the present case is squarely covered by the judgment of a co-ordinate Bench (Pradeep
Nandrajog, J.) passed in a batch of matters, lead matter being
LA.APP.No.784/2005 entitled 'Jamna vs. UOI & Ors.' decided as recently as on 08.07.2011. Learned counsel particularly draws the attention of this Court to the operative paras 31 and 33 of the aforesaid judgment, relevant portions of which are reproduced herein below:-
"31. As noted hereinabove, in Chiranji Lal's case (supra), pertaining to the notification dated 6.2.2003, fair market value assessed by me was 4,03,425/- per bigha and
)7 thus, increasing the same by bOb for 2 years and 131 days, the figure comes to 4,98,589/- per bigha, which comes to 23,93,227.20 per acre. The same is held by me to be the fair market value of land in Village Mundka and Village Bakkarwala as of 17.6.2005. I decree the same. xxx
Accordingly, the appeals filed by the Union of India require to be dismissed and I hereby dismiss the same.
The appeals filed by the land owners and the cross- objections filed by the land owners stands decreed as under:- xxx
S . xxx For the land situated in village Mundka the fair market value is fixed at 4,98,589/- per bigha, i.e.
23,93,227.20 per acre, as on 17.06.2005. iv) xxx xxx
Appellants and cross-objectors who have succeeded would also be entitled to solatium and interest as per statute and as clarified in the decision reported as
. 93(2001) DLT 569 Sunder vs. UOI, for the compensation, paid originally and as enhanced by the
Reference Court and finally on the sum enhanced by the present judgment and decree.
The appellants and cross-objectors who succeed would also be entitled to proportionate costs.
All pending applications stand disposed of in terms of the prayers made therein."
It is submitted by the counsel for the appellant that the appellant is also entitled to the relief as granted to other similarly placed appellants in the aforesaid batch of matters, to which counsel for the respondent/UOI has no objection.
Following the aforesaid decision dated 08.07.2011 in the case of
Jamna (supraL the present appeal is also disposed of on the same lines, while granting the same relief to the appellant as granted to the other similarly placed appellants of village Mundka, covered by
. notification dated 17.06.2005, subject matter of LA.APP.784/2005.
However, it is clarified that the appellant shall not be entitled to claim interest on the enhanced compensation for the period of delay of 312 days in filing the appeal as also the costs of the appeal, in terms of the orders passed today in C.M. No.16870/2011 preferred by the appellant for condonation of delay in filing the appeal.
HIMA KOHLI,J SEPTEMBER 09, 2011
• sk
Mundka, pursuant to the notification dated 17.06.2005 issued under
Section 4 of the Land Acquisition Act 1894 (in short 'the Act').
Counsel for the appellant submits that the present case is squarely covered by the judgment of a co-ordinate Bench (Pradeep
Nandrajog, J.) passed in a batch of matters, lead matter being
LA.APP.No.784/2005 entitled 'Jamna vs. UOI & Ors.' decided as recently as on 08.07.2011. Learned counsel particularly draws the attention of this Court to the operative paras 31 and 33 of the aforesaid judgment, relevant portions of which are reproduced herein below:-
"31. As noted hereinabove, in Chiranji Lal's case (supra), pertaining to the notification dated 6.2.2003, fair market value assessed by me was 4,03,425/- per bigha and
)7 thus, increasing the same by bOb for 2 years and 131 days, the figure comes to 4,98,589/- per bigha, which comes to 23,93,227.20 per acre. The same is held by me to be the fair market value of land in Village Mundka and Village Bakkarwala as of 17.6.2005. I decree the same. xxx
Accordingly, the appeals filed by the Union of India require to be dismissed and I hereby dismiss the same.
The appeals filed by the land owners and the cross- objections filed by the land owners stands decreed as under:- xxx
S . xxx For the land situated in village Mundka the fair market value is fixed at 4,98,589/- per bigha, i.e.
23,93,227.20 per acre, as on 17.06.2005. iv) xxx xxx
Appellants and cross-objectors who have succeeded would also be entitled to solatium and interest as per statute and as clarified in the decision reported as
. 93(2001) DLT 569 Sunder vs. UOI, for the compensation, paid originally and as enhanced by the
Reference Court and finally on the sum enhanced by the present judgment and decree.
The appellants and cross-objectors who succeed would also be entitled to proportionate costs.
All pending applications stand disposed of in terms of the prayers made therein."
It is submitted by the counsel for the appellant that the appellant is also entitled to the relief as granted to other similarly placed appellants in the aforesaid batch of matters, to which counsel for the respondent/UOI has no objection.
Following the aforesaid decision dated 08.07.2011 in the case of
Jamna (supraL the present appeal is also disposed of on the same lines, while granting the same relief to the appellant as granted to the other similarly placed appellants of village Mundka, covered by
. notification dated 17.06.2005, subject matter of LA.APP.784/2005.
However, it is clarified that the appellant shall not be entitled to claim interest on the enhanced compensation for the period of delay of 312 days in filing the appeal as also the costs of the appeal, in terms of the orders passed today in C.M. No.16870/2011 preferred by the appellant for condonation of delay in filing the appeal.
HIMA KOHLI,J SEPTEMBER 09, 2011