r .\\ #18 HIGH COURT OF DELHI
CO.PET. 515/2010 & CO. APPLS. 2406/2010
O/o VINODKUMAR
Through
VERSUS
MIS PAL INFRASTRUCTURE & DEVELOPERS PVT LTD
Through
CORAM: ..... Petitioner Mr. Amiet Andley with Mr. Arun K. Sharma, Advocates ..... Respondent
Ms. Anu Bagai, Advocate
HON'BLE MR. JUSTICE MANMOHAN
10.10.2011 Today in Court, Ms. Anu Bagai, learned counsel for respondent has handed over to Mr. Amiet Andley, learned counsel for petitioner a Pay
Order No. 008464 dated 101 h October, 2011 drawn upon IDBI Bank, Gurgaon Branch for Rs. 3,25,000/- in full and final settlement of petitioner's dues.
In view of receipt of the aforesaid pay order, Mr. Amiet Andley states that the petitioner has no further claim upon the respondent-company.
Accordingly, the present petition and pending application are disposed ofas satisfied.
OCTOBER 10, 2011 rn \\~ MANMOl1AN,J 2011:DHC:9102
JUDGMENT