Sri Ganesh Engineering Works v. Northern Railway & Anr.

Delhi High Court · 10 Dec 2024 · 2024:DHC:9520
Sachin Datta
ARB.P. 808/2024
2024:DHC:9520
civil appeal_allowed Significant

AI Summary

The Delhi High Court held that pre-arbitral conciliation is directory and appointed a sole arbitrator to adjudicate disputes arising from a terminated railway contract, despite procedural provisions in the contract being outdated.

Full Text
Translation output
ARB.P. 808/2024
HIGH COURT OF DELHI
Date of Decision: 10.12.2024
ARB.P. 808/2024
SRI GANESH ENGINEERING WORKS .....Petitioner
Through: Mr. Rahul Shukla and Mr. Bachita Baruah Shukla, Advs.
VERSUS
NORTHERN RAILWAY & ANR. .....Respondents
Through: Mr. Jagdish Chandra, CGSC and Mr. Karan Khetani, Adv.
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA SACHIN DATTA, J. (ORAL)
JUDGMENT

1. This is an application filed on behalf of the respondents seeking condonation of delay of 71 days in filing counter-affidavit. IA No.47803/2024 (condonation of delay of 71 days in filing counteraffidavit)

2. Considering the averments made in the application, the same is allowed.

3. Copy of the counter-affidavit, which has been handed over during the course of hearing, is taken on record.

4. The present petition filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the A&C Act’) seeks constitution of an arbitral tribunal to adjudicate the disputes between the parties.

5. The disputes between the parties have arisen in the context of a tender floated by the respondent being Tender No.465-Acs-ROB-36-Ganaur-CSB with closing date 07.08.2019 for “Construction of 02 Lane Road Over Bridge having span 1 x 58.040 M (Bow String steel Girder) c/c of pier, along with Limited Height Subway (Internal size 5.500 X 2.60 M) including design and Drawing of sub structure & foundation in lieu of L-xing No. 36 Spl at Km 58/15-17 near Ganaur Railway station on Delhi-Ambala section of Northern Railway.”

6. The petitioner participated in the tender process and the petitioner’s bid was accepted vide letter dated 17.09.2019. The total cost of the work at the accepted rates worked out to Rs.9,58,01,622.03 (Rupees Nine Crore Fifty-Eight Lakh One Thousand Six Hundred and Twenty-Two Rupees and Three Paise Only). The requisite performance guarantee was also submitted by the petitioner in terms of the applicable conditions of contract. The Contract Agreement Number W-259/ROB/36-G/GANAUR/CSB dated 18.03.2020 was signed between the parties for performance of the work.

7. Upon signing of the contract agreement, the date of commencement of the contract was reckoned as 17.09.2019 and the scheduled date of completion of the Contract was stipulated as 16.09.2020.

8. Disputes between the parties have arisen to take requisite steps for land acquisition and for removal of other hindrances for the purpose of execution of the work.

9. Extensive correspondence was exchanged between the parties as regards the respective entitlement of the parties under the contract and as regards the time extension that was sought by the petitioner.

10. Ultimately, the contract was terminated by the respondents vide a communication dated 14.03.2024. It is the petitioner’s case that the termination is illegal.

11. Consequently, a notice of arbitration dated 08.05.2024 was issued by the petitioner wherein the petitioner sought reference of the disputes between the parties to arbitration. The claims sought to be raised in the arbitration proceedings were also set out therein.

12. Admittedly, the relevant contract conditions between the parties contains an arbitration clause which is as under: “SETTLEMENT OF DISPUTES – INDIAN RAILWAY ARBITRATION AND CONCILIATION RULES

63. Reconciliation of disputes: All disputes and differences of any kind whatsoever arising out of or in connection with the contract, whether during the progress of the work or after its completion and whether before or after the determination of the contract, shall be referred by the Contractor to the "Chief Engineer" or "Divisional Railway Manager" through “Notice of Dispute” provided that no such notice shall be served later than 30 days after the date of issue of Completion Certificate by the Engineer. Chief Engineer or Divisional Railway Manager shall, within 30 days after receipt of the Contractor’s “Notice of Dispute”, notify the name of conciliator(s) to the Contractor. The Conciliator(s) shall assist the parties to reach an amicable settlement in an independent and impartial manner within the terms of contract. If the parties reach agreement on a settlement of the dispute, they shall draw up and sign a written settlement agreement duly signed by Engineer In-charge, Contractor and conciliator(s).When the parties sign the settlement agreement, it shall be final and binding on the parties. The parties shall not initiate, during the conciliation proceedings, any arbitral or judicial proceedings in respect of a dispute that is the subject matter of the conciliation proceedings. The conciliation proceedings shall be terminated: By the signing of the settlement agreement by the parties on the date of agreement; or • By written declaration of the conciliator, after consultation with the parties, to the effect that further efforts at conciliation are no longer justified, on the date of declaration; or • By a written declaration of any party to the conciliator to the effect that the conciliation proceedings are terminated, on the date of declaration; or 63.[1] Matters Finally Determined by the Railway: All disputes and differences of any kind whatsoever arising out of or in connection with the contract, whether during the progress of the work or after its completion and whether before or after the determination of the contract, shall be referred by the Contractor to the GM and the GM shall, within 120 days after receipt of the Contractor’s representation, make and notify decisions on all matters referred to by the Contractor in writing provided that matters for which provision has been made in Clauses 8, 18, 22(5), 39, 43(2), 45(a), 55, 55-A(5), 57, 57A,61(1), 61(2) and 62(1) of Standard General Conditions of Contract or in any Clause of the Special Conditions of the Contract shall be deemed as ‘excepted matters’ (matters not arbitrable) and decisions of the Railway authority, thereon shall be final and binding on the Contractor; provided further that ‘excepted matters’ shall stand specifically excluded from the purview of the Arbitration Clause. 64.(1): Demand for Arbitration: 64.(1)(i): In the event of any dispute or difference between the parties hereto as to the construction or operation of the contract, or the respective rights and liabilities of the parties on any matter in question, dispute or difference on any account or as to the withholding by the Railway of any certificate to which the Contractor may claim to be entitled to, or if the Railway fails to make a decision within 120 days, then and in any such case, but except in any of the “excepted matters” referred to in Clause 63.[1] of these Conditions, the Contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters shall demand in writing that the dispute or difference be referred to arbitration. 64.(1)(ii)(a): The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item-wise. Only such dispute or difference, in respect of which the demand has been made, together with counter claims or set off, given by the Railway, shall be referred to arbitration and other matters shall not be included in the reference. 64.(1)(ii)(b): The parties may waive off the applicability of Sub-Section 12(5) of Arbitration and Conciliation (Amendment) Act 2015, if they agree for such waiver in writing, after dispute having arisen between them, in the format given under Annexure XV of these conditions. 64.(1)(iii)(a): The Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway. 64.(1)(iii)(b): The claimant shall submit his claims stating the facts supporting the claims alongwith all the relevant documents and the relief or remedy sought against each claim within a period of 30 days from the date of appointment of the Arbitral Tribunal. 64.(1)(iii)(c): The Railway shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from Tribunal, unless otherwise extension has been granted by Tribunal. 64.(1)(iii)(d): Place of Arbitration: The place of arbitration would be within the geographical limits of the Division of the Railway where the cause of action arose or the Headquarters of the concerned Railway or any other place with the written consent of both the parties. 64.(1)(iv): No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original claim or defense thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it. 64.(1)(v): If the Contractor(s) does/do not prefer his/their specific and final claims in writing, within a period of 90 days of receiving the intimation from the Railways that the final bill is ready for payment, he/they will be deemed to have waived his/their claim(s) and the Railway shall be discharged and released of all liabilities under the contract in respect of these claims. 64.(2): Obligation During Pendency of Arbitration: Work under the contract shall, unless otherwise directed by the Engineer, continue during the arbitration proceedings, and no payment due or payable by the Railway shall be withheld on account of such proceedings, provided, however, it shall be open for Arbitral Tribunal to consider and decide whether or not such work should continue during arbitration proceedings. 64.(3): Appointment of Arbitrator: 64.(3)(a): Appointment of Arbitrator where applicability of section 12 (5) of Arbitration and Conciliation Act has been waived off: 64.(3)(a)(i): In cases where the total value of all claims in question added together does not exceed ₹ 1,00,00,000/ - (Rupees One Crore), the Arbitral Tribunal shall consist of a Sole Arbitrator who shall be a Gazetted Officer of Railway not below Junior Administrative Grade, nominated by the General Manager. The sole arbitrator shall be appointed within 60 days from the day when a written and valid demand for arbitration is received by General Manager. 64.(3)(a)(ii): In cases not covered by the Clause 64(3)(a)(i), the Arbitral Tribunal shall consist of a panel of three Gazetted Railway Officers not below Junior Administrative Grade or 2 Railway Gazetted Officers not below Junior Administrative Grade and a retired Railway Officer, retired not below the rank of Senior Administrative Grade Officer, as the arbitrators. For this purpose, the Railway will send a panel of at least four (4) names of Gazetted Railway Officers of one or more departments of the Railway which may also include the name(s) of retired Railway Officer(s) empanelled to work as Railway Arbitrator to the Contractor within 60 days from the day when a written and valid demand for arbitration is received by the General Manager. Contractor will be asked to suggest to General Manager at least 2 names out of the panel for appointment as Contractor’s nominee within 30 days from the date of dispatch of the request by Railway. The General Manager shall appoint at least one out of them as the Contractor’s nominee and will, also simultaneously appoint the balance number of arbitrators either from the panel or from outside the panel, duly indicating the ‘presiding arbitrator’ from amongst the 3 arbitrators so appointed. General Manager shall complete this exercise of appointing the Arbitral Tribunal within 30 days from the receipt of the names of Contractor’s nominees. While nominating the arbitrators, it will be necessary to ensure that one of them is from the Accounts Department. An officer of Selection Grade of the Accounts Department shall be considered of equal status to the officers in Senior Administrative Grade of other departments of the Railway for the purpose of appointment of arbitrator. 64.3.(a).iii: The serving railway officer working in arbitral tribunal in the ongoing arbitration cases as per clause 64.(3)(a)(i) and clause 64.(3)(a)(ii) above, can continue as arbitrator in the tribunal even after his retirement. 64.(3)(b): Appointment of Arbitrator where applicability of Section 12 (5) of Arbitration and Conciliation Act has not been waived off:

(i) In cases where the total value of all claims in question added together does not exceed₹ 50,00,000/ - (Rupees Fifty Lakh), the Arbitral Tribunal shall consist of a Retired Railway Officer, retired not below the rank of Senior Administrative Grade Officer, as the arbitrator. For this purpose, the Railway will send a panel of at least four (4) names of retired Railway Officer(s) empanelled to work as Railway Arbitrator duly indicating their retirement dates to the Contractor within 60 days from the day when a written and valid demand for arbitration is received by the General Manager. the panel for appointment as arbitrator within 30 days from the date of dispatch of the request by Railway.The General Manager shall appoint at least one out of them as the arbitrator.

(ii) In cases where the total value of all claims in question added together exceed ₹ 50,00,000/- (Rupees Fifty Lakh), the Arbitral Tribunal shall consist of a Panel of three (3) retired Railway Officer, retired not below the rank of Senior Administrative Grade Officer, as the arbitrators. For this purpose, the Railway will send a panel of at least four (4) names of retired Railway Officer(s) empanelled to work as Railway Arbitrator duly indicating their retirement date to the Contractor within 60 days from the day when a written and valid demand for arbitration is received by the General Manager. the panel for appointment as Contractor’s nominee within 30 days from the date of dispatch of the request by Railway. The General Manager shall appoint at least one out of them as the Contractor’s nominee and will, also simultaneously appoint the balance number of arbitrators either from the panel or from outside the panel, duly indicating the ‘Presiding Arbitrator’ from amongst the 3 arbitrators so appointed. General Manager shall complete this exercise of appointing the Arbitral Tribunal within 30 days from the receipt of the names of Contractor’s nominees. While nominating the arbitrators, it will be necessary to ensure that one of them has served in the Accounts Department. 64.(3)(c)(i): If one or more of the arbitrators appointed as above refuses to act as arbitrator, withdraws from his office as arbitrator, or vacates his/their office/offices or is/are unable or unwilling to perform his functions as arbitrator for any reason whatsoever or dies or in the opinion of the General Manager fails to act without undue delay, the General Manager shall appoint new arbitrator/arbitrators to act in his/their place in the same manner in which the earlier arbitrator/arbitrators had been appointed. Such re-constituted Tribunal may, at its discretion, proceed with the reference from the stage at which it was left by the previous arbitrator (s). 64.(3) (c) (ii): (a) The Arbitral Tribunal shall have power to call for such evidence by way of affidavits or otherwise as the Arbitral Tribunal shall think proper, and it shall be the duty of the parties hereto to do or cause to be done all such things as may be necessary to enable the Arbitral Tribunal to make the award without any delay. The proceedings shall normally be conducted on the basis of documents and written statements. (b) Before proceeding into the merits of any dispute, the Arbitral Tribunal shall first decide and pass its orders over any plea submitted/objections raised by any party, if any, regarding appointment of Arbitral Tribunal, validity of arbitration agreement, jurisdiction and scope of the Tribunal to deal with the dispute (s) submitted to arbitration, applicability of time ‘limitation’ to any dispute, any violation of agreed procedure regarding conduct of the arbitral proceedings or plea for interim measures of protection and record its orders in day to day proceedings. A copy of the proceedings duly signed by all the members of tribunal should be provided to both the parties. 64.3(c)(iii): (i) Qualification of Arbitrator (s): (a) Serving Gazetted Railway Officers of not below JA Grade level. (b) Retired Railway Officers not below SA Grade level, one year after his date of retirement.

22,845 characters total

(c) Age of arbitrator at the time of appointment shall be below 70 years.

(ii) An arbitrator may be appointed notwithstanding the total number of arbitration cases in which he has been appointed in the past.

(iii) While appointing arbitrator(s) under Sub-Clause 64.(3)(a)(i), 64.(3)(a)(ii),

64.(3)(b)(i) & 64.(3)(b)(ii) above, due care shall be taken that he/they is/are not the one/those who had an opportunity to deal with the matters to which the contract relates or who in the course of his/their duties as Railway servant(s) expressed views on all or any of the matters under dispute or differences. A certification to this effect as per annexure- XVI shall be taken from Arbitrators also. The proceedings of the Arbitral tribunal or the award made by such Tribunal will, however, not be invalid merely for the reason that one or more arbitrator had, in the course of his service, opportunity to deal with the matters to which the contract relates or who in the course of his/their duties expressed views on all or any of the matters under dispute. 64.(3)(d)(i): The arbitral award shall state item wise, the sum and reasons upon which it is based. The analysis and reasons shall be detailed enough so that the award could be inferred therefrom. 64.(3)(d)(ii): A party may apply for corrections of any computational errors, any typographical or clerical errors or any other error of similar nature occurring in the award of a Tribunal and interpretation of a specific point of award to Tribunal within 60 days of receipt of the award. 64.(3)(d)(iii): A party may apply to Tribunal within 60 days of receipt of award to make an additional award as to claims presented in the arbitral proceedings but omitted from the arbitral award. 64.(4): In case of the Tribunal, comprising of three members, any ruling on award shall be made by a majority of members of Tribunal. In the absence of such a majority, the views of the Presiding Arbitrator shall prevail. 64.(5): Where the arbitral award is for the payment of money, no interest shall be payable on whole or any part of the money or any period till the date on which the award is made.

64. (6): The cost of arbitration shall be borne by the respective parties. The cost shall inter-alia include fee of the arbitrator(s), as per the rates fixed by Railway Board from time to time and the fee shall be borne equally by both the parties, provided parties sign an agreement in the format given at Annexure XV to these condition after/ while referring these disputes to Arbitration. Further, the fee payable to the arbitrator(s) would be governed by the instructions issued on the subject by Railway Board from time to time irrespective of the fact whether the arbitrator(s) is/are appointed by the Railway Administration or by the court of law unless specifically directed by Hon’ble court otherwise on the matter. 64.(7) Subject to the provisions of the aforesaid Arbitration and Conciliation Act 1996 and the rules thereunder and relevant para of General Conditions of Contract (GCC) and any statutory modifications thereof shall apply to the appointment of arbitrators and arbitration proceedings under this Clause.”

13. Respective counsel for the parties do not dispute that the procedure for appointment, as contemplated in the aforesaid clause is no longer valid in view of the judgment in Central Organisation for Railway Electrification v. ECI SPIC SMO MCML (JV) A Joint Venture Company, MANU/SC/1190/2024. However, learned counsel for the respondents seeks to oppose the present petition on the ground that prior to seeking arbitration, the petitioner has not exhausted the avenue of seeking reconciliation of disputes as per the procedure prescribed in Clause 63 of the contract between the parties.

14. The aforesaid objection is untenable.

15. As pointed out by learned counsel for the petitioner, request/s was made to the respondents for conciliation of the disputes; however, the same was not acceded to. Besides, it has been held in numerous judgments of this Court that pre-arbitral procedures such as conciliation / mediation are directory in nature and not mandatory, and non-exhaustion thereof does not preclude a party from taking recourse to arbitration.

16. In this regard, reference may be made to Oasis Projects Ltd. v. National Highway & Infrastructure Development Corporation Limited (2023) 1 HCC (Del) 525, Kunwar Narayana v. Ozone Overseas Pvt. Ltd 2021:DHC:496 and Jhajharia Nirman Ltd v. South Western Railways Through Dy. Chief Engineer/IV Construction 2024:DHC:7801

17. In the circumstances, given that there is no controversy about existence of arbitration agreement, there is no impediment to constituting an arbitral tribunal to adjudicate the disputes between the parties, as mandated in In Re: Interplay between Arbitration Agreement under the Arbitration and Conciliation Act, 1996 and the Indian Stamp Act, 1899 In re, 2023 SCC OnLine SC 1666, and SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 SCC OnLine SC 1754.

18. Moreover, in terms of Perkins Eastman Architects DPC v. HSCC (India) Ltd (2020) 20 SCC 760, TRF Limited v. Energo Engineering Projects Ltd, (2017) 8 SCC 377 and Bharat Broadband Network Limited v. United Telecoms Limited, 2019 SCC OnLine SC 547 it is incumbent on this Court to appoint an independent Sole Arbitrator.

19. Accordingly, Mr. R. Badri Narayan, Former Chief Administrative Officer (Traffic), Transportation and Business Research Unit, [Indian Railway Traffic Service] (Mobile- + 91 9958198410) is appointed as the Sole Arbitrator to adjudicate the disputes between the parties.

20. The respondents shall be entitled to raise objections as regards jurisdiction / arbitrability, if any, before the learned Sole Arbitrator which shall be considered by the arbitrator on merits.

21. It is further directed that before adjudication of the disputes on merits, the arbitrator shall take steps to encourage settlement of disputes and take recourse to such measures for this purpose, as contemplated under Section 30 of the Arbitration and Conciliation Act, 1996.

22. The learned Sole Arbitrator may proceed with the arbitration proceedings subject to furnishing to the parties the requisite disclosure as required under Section 12 of the A&C Act.

23. At request of respective counsel, it is directed that the arbitration shall take place under the aegis of and as per the rules of the Delhi International Arbitration Centre (DIAC).

24. All rights and contentions of the parties in relation to the claims/counter claims are kept open, to be decided by the learned Sole Arbitrator on their merits, in accordance with law.

25. Needless to say, nothing in this order shall be construed as an expression of opinion of this court on the merits of the case.

26. The present petition stands disposed of in the above terms.

SACHIN DATTA, J DECEMBER 10, 2024