National Highways and Infrastructure Development Corporation Limited v. JKM-KCL (JV)

Delhi High Court · 10 Jul 2026 · 2026:DHC:5531
Om Prakash Shukla
O.M.P. (COMM) 43/2025
2026:DHC:5531
civil petition_allowed

AI Summary

The Delhi High Court allowed withdrawal of a Section 34 arbitration petition following an amicable settlement under the Vivad Se Vishwas Scheme-III.

Full Text
Translation output
O.M.P. (COMM) 43/2025
HIGH COURT OF DELHI
O.M.P. (COMM) 43/2025
NATIONAL HIGHWAYS AND INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED .....Petitioner
Through: Mr. Bikash Mohanty, Mr. Shashwat Prateek Panda, Mr. Aiman Zamir, Mr. Vikramaditya Mohanty and Mr. Suryans Sritej Mohanty, Advs.
VERSUS
JKM-KCL (JV) .....Respondent
Through: Mr. Suman Chetia, Mr. Kaushik Choudhary, Mr. Jyotirmoy Chatterjee and Ms. Aaheli Roy, Advs.
CORAM:
HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
ORDER(ORAL)
10.07.2026
I.A. 17732/2026 (withdrawal of Petition)
JUDGMENT

1. This is an application filed under section 151 Code of Civil Procedure, 1908 seeking withdrawal of the section 34 petition of the Arbitration and Conciliation Act, 1996[1] in OMP (COMM) 43/2025.

2. Mr. Bikash Mohanty, learned Counsel for the Petitioner submits that the parties have reached an amicable settlement under “Vivad Se Vishwas Scheme-III”. “the Act” hereinafter O.M.P. (COMM) 43/2025

3. In view of the settlement arrived at between the parties, the present application is allowed.

4. Accordingly, the present petition along with pending application(s), if any, is disposed of as withdrawn.

5. The next date i.e. 05.08.2026 stands cancelled.

OM PRAKASH SHUKLA, J JULY 10, 2026