Full Text
W.P.(C) 3310/2026
Date of Decision: 16.03.2026 IN THE MATTER OF:
TPF GETINSA EUROESTUDIOS S L .....petitioner
Through: Mr.K. K .Sharma Sr. Advocate with Mr. Rajiv Bakshi and Mr. Ram Pravesh Rai Advocates.
Through: Ms Neetica Sharma and Mr Naman Saraswat Advocates.
JUDGMENT
1. Exemption allowed, subject to all just exceptions.
2. The application stands disposed of. W.P.(C) 3310/2026 and CM APPL. 16001/2026
1. The instant petition is for the following reliefs:- “i) issue a writ of certiorari or any other appropriate writ, order or direction, quashing Office Circular/Order No. NHAI/NH- CHH P/3801 0/2/IE-Getinsa/Pkg-11/2024/18052 dated 03.02.2026 issued by respondent. ii) pass any other or further order/s which this Hon'ble Court may deem fit and proper in the interest of justice.”
KUMAR KAURAV
2. The facts of the case would indicate that the petitioner in association with Segmental Consultancy and Infrastructure Advisory Private Limited was awarded the work to act as Consultant/Independent Engineer to supervise the work of Four laning of Jhansi-Khajuraho section (Package-11) of NH-75/76 from Design Chainage Km. 76.[3] (Existing Chainage 82.[1] 00) near village Chhatipahari to Design Chainage Km. 161.[7] (Existing Chainage Km.57.9) near Bamitha town in the State of Uttar Pradesh & Madhya Pradesh under NHDP (Phase-11 I) on Hybrid Annuity Mode which was to be executed by Concessionaire under the Concession Agreement. On 12.03.2018, the petitioner mobilized and commenced consultancy services at the project site.
3. The dispute arose over the Right of Way (ROW) fencing work in the four-laning of the Jhansi-Khajuraho section (Package-11) of NH-75/76, that whether the Right of Way (ROW) fencing was within the scope of work of the petitioner, acting as Independent Engineer, or the concessionaire under the Concession Agreement, and whether the petitioner was required to ensure its execution.
4. There were concerns whether the petitioner failed to exercise due diligence in reviewing the plans, profiles, and supporting documents submitted by the concessionaire, which allegedly resulted in nonimplementation of Right of Way (ROW) fencing and the respondent contends that this amounted to a breach of Clause 3.1.[1] of the General Conditions of Contract and Section 6 of the Terms of Reference.
5. Thereafter, respondent issued a show cause notice on 28.09.2024 alleging that the petitioner failed to exercise the due diligence in reviewing drawings and documents submitted by the Concessionaire for ROW fencing along the four-laning of the Jhansi–Khajuraho section (Package-11).
6. Subsequently Vide the impugned order dated 03.02.2026 passed by the respondent, the petitioner has been declared „non-performer‟ for a period of six months and a penalty of Rs.9,47,975/- has been imposed on it.
7. The aforenoted factual narration reveals that the work in question, which is the genesis of the entire dispute, has taken place outside the jurisdiction of this Court. The petitioner seems to have approached this Court merely on the ground that the impugned order has been passed in, and the office of the Respondent-Authority is situated at, New Delhi.
8. This Court in The Indure Pvt. Ltd. v. Government of NCT of Delhi,[1] took note of the decisions in Shristi Udaipur Hotels v. Housing and Urban Development Corp.,[2] Riddhima Singh v. Central Board of Secondary Education,[3] Smt. Manjira Devi Ayurveda Medical College and Hospital v. Uttarakhand University of Ayurveda and Ors.,[4] Michael Builders and Developers Pvt. Ltd. v. National Medical Commission and Ors.,[5] which declare that the situs of the head office/registered office of the respondent, does not determine whether the Court has the requisite territorial jurisdiction to entertain a writ petition.
9. The Court in The Indure Pvt. Ltd. importantly noted, at para. 36:
10. On the issue of a claimant approaching this Court on the sole-ground of the respondent-authority, an arm of the union government, being situated within the jurisdiction of this Court, it was observed at para. 37-38:
11. Ultimately, the Court concluded that the substance of a matter must be adjudged, and not the unchanging constant which is present in every petition against a state-authority, to arrive at a conclusion on whether to entertain a petition in the context of territorial jurisdiction and forum non conveniens. At para. 42 this Court observed:
12. In the facts of the instant case, there may be a part of cause of action which has arisen in Delhi, however, the same should not be the sole reason to entertain the instant petition.
13. The Supreme Court in the case of Kusum Ingots & Alloys Ltd. v. Union of India and Anr.,[6] has held that even if a small part of cause of action arises within the territorial jurisdiction of the High Court, the same by itself may not be considered to be a determinative factor compelling the High Court to decide the matter on merit. In appropriate cases, the Court may refuse to exercise its discretionary jurisdiction by invoking the doctrine of forum conveniens. The material portion of the aforenoted decision reads as under: “Forum conveniens
30. We must, however, remind ourselves that even if a small part of cause of action arises within the territorial jurisdiction of the High Court, the same by itself may not be considered to be a determinative factor compelling the High Court to decide the matter on merit. In appropriate cases, the Court may refuse to exercise its discretionary jurisdiction by invoking the doctrine of forum conveniens. [See Bhagat Singh Bugga v. Dewan Jagbir Sawhney [AIR 1941 Cal 670: ILR (1941) 1 Cal 490], Madanlal Jalan v. Madanlal [(1945) 49 CWN 357: AIR 1949 Cal 495], Bharat Coking Coal Ltd. v. Jharia Talkies & Cold Storage (P) Ltd. [1997 CWN 122], S.S. Jain & Co. v. Union of India [(1994) 1 CHN 445] and New Horizons Ltd. v. Union of
14. In view of the above, petition stands dismissed, along with the pending application. Liberty is, however, granted in favour of the petitioner to approach the jurisdictional High Court to agitate the instant lis, if so advised.
15. All rights and contentions of the parties are left open.
PURUSHAINDRA KUMAR KAURAV, J MARCH 16, 2026 Nc